ELECTRICITY CONSUMERS RESOURCE COUNCIL, PETITIONER v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC., ET AL., INTERVENORS
No. 03-1449
United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued April 11, 2005 Decided May 13, 2005
On Petition for Review of Orders of the Federal Energy Regulatory Commission
Sara D. Schotland argued the cause for petitioner. With her on the briefs was Robert A. Weishaar, Jr.
Lona T. Perry, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor.
Jonathan D. Feinberg was on the brief for intervenor Public
William F. Young and Susan E. Dove were on the brief for intervenor New York Independent System Operator, Inc. Arnold H. Quint entered an appearance.
Frederick W. Morris, James J. Bertrand, Brian M. Meloy, Debra R. Bolton, Scott G. Silverstein, Mary M. Fabic, and Kenneth R. Carretta were on the brief for intervenors NRG Companies, et al.
Before: SENTELLE, ROGERS and TATEL, Circuit Judges.
Opinion for the Court filed by Circuit Judge ROGERS.
ROGERS, Circuit Judge: The Electricity Consumers Resource Council (“ELCON“) challenges two orders of the Federal Energy Regulatory Commission approving a rate design for the installed capacity market administered by the New York Independent System Operator, Inc. (“NYISO“). See NY Indep. Sys. Operator, Inc., 103 F.E.R.C. ¶ 61,201 (2003) (“Initial Order“); NY Indep. Sys. Operator, Inc., 105 F.E.R.C. ¶ 61,108 (2003) (“Rehearing Order“). While maintaining that the Commission‘s orders violate both the “just and reasonable” ratemaking standard of the Federal Power Act (“FPA“),
I.
To prevent electricity shortages during periods of peak demand, the New York State Reliability Council required retail utilities, known as load serving entities (“LSEs“), to purchase installed capacity (“ICAP“) equal to 118% of their peak loads. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,750. If an LSE failed to procure the required amount of ICAP through its own supply or through bilateral contracts, it was required to purchase the deficient quantity through NYISO auctions, at which the price equaled a “deficiency charge” of $255 per kilowatt-year, or three times the annualized cost of installing a new “peaker” power plant. See id. This rate design resulted in a vertical demand curve for ICAP, with the price equal to $255 for all quantities up to 118%, and $0 for all quantities exceeding 118%.
Figure 1: Vertical Demand Curve
To address this problem, NYISO applied to the Commission for approval of amendments to its tariff to incorporate a new rate design replacing the vertical demand curve with a sloped “ICAP Demand Curve,” which would be used in monthly auctions to determine both the quantity and price of required ICAP. See id. For 118% of peak load, the price would equal the annualized cost of a new peaker plant. See id. As supply increased above 118%, the price would gradually decrease until it reached zero for 132% of peak load, and as supply decreased below 118%, the price would gradually increase until it reached a maximum of two times the annualized cost of a new peaker plant. See id. & fig.2.
Figure 2: Sloped ICAP Demand Curve
ELCON, which represents industrial consumers of electricity, intervened and protested the new rate design, arguing that it would increase electricity prices for consumers without spurring investment in new generation capacity, and that it violated incentive ratemaking case law because the ICAP Demand Curve was not carefully calibrated to increase investment in new generation facilities without granting a windfall to existing capacity suppliers. The Commission approved NYISO‘s rate design with modifications, finding that it would “benefit customers because it [would] provide better price signals to investors for construction of new generation, encourage the formation of long-term bilateral transactions, and reduce incentives to withhold capacity.” Id. at 61,750. The Commission agreed with NYISO that the ICAP Demand Curve would “encourage greater investment in generation capacity and thus improve reliability, by reducing the volatility of ICAP revenues,” and concluded that it would “provide net benefits especially compared with the existing vertical demand curve.” Id. at 61,753-54. The Commission eliminated the supplemental supply fee based on the concern that suppliers would withhold capacity from the monthly ICAP auction in order to sell capacity at the higher price of the supplemental supply fee. See id. at
II.
The court ordinarily reviews the Commission‘s orders to determine whether they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
ELCON contends that the challenged orders are subject to a heightened standard of review because the ICAP Demand Curve is neither market-based nor cost-based but rather administratively constructed to encourage investment in new generation capacity. According to ELCON, the Commission must demonstrate that such “incentive ratemaking” is “in fact needed, and is no more than is needed, for the purpose.” City of Detroit v. Fed. Power Comm‘n, 230 F.2d 810, 817 (D.C. Cir. 1955). In support of this heightened standard of review, ELCON cites a line of cases involving the Commission‘s approval of incremental rate increases above cost-based rates to encourage increases in energy supply. See, e.g., Farmers Union Cent. Exch., Inc. v. FERC, 734 F.2d 1486, 1503 (D.C. Cir. 1984); City of Charlottesville v. FERC, 661 F.2d 945, 950 (D.C. Cir. 1981); Pub. Serv. Comm‘n v. FERC, 589 F.2d 542, 552-53 (D.C. Cir. 1978); City of Detroit, 230 F.2d at 817-818. ELCON also cites the Commission‘s 1992 Policy Statement on incentive ratemaking, which states that the Commission “is free to set rates [above cost-based rates] to provide incentives so long as there is a correlation between the incentive and the result to be induced.” Incentive Ratemaking for Interstate Natural Gas Pipelines, Oil Pipelines, and Electric Utilities, 61 F.E.R.C. ¶ 61,168, 61,594 (1992). ELCON maintains that the new rate design violates the incentive ratemaking case law and the 1992 Policy Statement because it offers increased revenues to all capacity suppliers, regardless of whether they invest in new generation facilities. In ELCON‘s view, the new rate design grants a windfall to existing capacity suppliers at the expense of LSEs and their customers.
In the Initial Order, the Commission explained that the
Unlike incentive ratemaking, the ICAP Demand Curve does not impose an incremental rate increase above traditional cost-based rates. “For the rationale of the incentive rate cases to apply here,” the intervening capacity suppliers explain, ELCON “would need to identify a ‘rate increase’ over and above the rates permitted under the Vertical Demand Curve—rates that [ELCON] concede[s], at least implicitly—fall within the ‘zone of reasonableness’ under the just and reasonable standard.” Br. of Supplier Intervenors at 8. Under the vertical demand curve, ICAP prices ranged from zero to the deficiency charge, or three times the annualized cost of a new peaker plant. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,750. Under the sloped demand curve, ICAP prices range from zero to two times the annualized cost of a new peaker plant. See id. at 61,751. At quantities above 118% of peak load, ICAP prices are higher under the sloped demand curve than under the vertical demand
More important, unlike incentive ratemaking, the ICAP Demand Curve encourages investment in new generation capacity by ensuring “increased stability in ICAP revenues,” not higher rates across the board. Id. at 61,758. Instead of granting “above-cost premiums to suppliers of capacity,” Br. of Resp‘t at 26, the ICAP Demand Curve restructures ICAP prices to “more realistically reflect[] the economic value of capacity reserves” and to “send better price signals to encourage the construction of generation before a shortage occurs.” Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,756-57. In the Commission‘s view, stable ICAP revenues will reduce the risk and cost of financing investment in new generation capacity and thus reduce the cost of electricity to consumers in the long term. See id. Its conclusion is supported by substantial evidence in the record. See infra Part III.
Insisting that the ICAP Demand Curve imposes excessive incentive rates, ELCON relies on two decisions of the First Circuit: Central Maine Power Co. v. FERC, 252 F.3d 34 (1st Cir. 2001), and Sithe New England Holdings, LLC v. FERC, 308 F.3d 71 (1st Cir. 2002), which address ICAP charges similar to those here. In Central Maine, the Commission had initially imposed a deficiency charge equal to $8.75 per kilowatt-month based on the amortized cost of a new peaker plant, and then later abandoned the deficiency charge in favor of an ICAP auction market. See 252 F.3d at 39. After the ICAP auction market proved a failure, the Commission reinstated the $8.75 deficiency charge without responding to objections that it was no longer
The Commission maintains that the court owes “special deference” to its development of the “experimental” ICAP Demand Curve because regardless of the evidence in the record, “there is no substitute for reviewing the actual results of a regulatory action.” Interstate Natural Gas Ass‘n v. FERC, 285 F.3d 18, 30 (D.C. Cir. 2002). The court has recognized that “the formulation of such an experimental policy (where the probability of success is uncertain) is the type of activity that the [Commission] was created to perform, and we give great weight to the Commission‘s determination regarding this policy.” Pub. Serv. Comm‘n v. Fed. Power Comm‘n, 463 F.2d 824, 828 (D.C. Cir. 1972). However, even this highly deferential standard of review “demand[s] an articulation, in response to serious objections, of the Commission‘s reasons for believing that more good than harm will come of its action—even experimental action.” Md. People‘s Counsel v. FERC, 761 F.2d 768, 779 (D.C. Cir. 1985). Moreover, the deference the court affords the Commission is based on the understanding that the Commission will monitor its experiment and review it accordingly. See Pub. Serv. Comm‘n, 463 F.2d at 828. Under these circumstances, the court will defer to the Commission‘s predictive judgment that the new rate design will result in “more good than harm,” as long as the Commission articulates reasons for its judgment and responds adequately to ELCON‘s objections. Although the Commission did not schedule a sunset date or periodic review of the ICAP Demand Curve, it did require NYISO to file annual evaluations of the Demand Curve, see Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,754, thereby ensuring that NYISO and the Commission will have the information needed to determine whether the rate design requires modification should their predictions fail to be borne out by experience. During oral argument ELCON suggested that the Commission‘s characterization of the ICAP Demand Curve as an experiment is a post-hoc rationalization, but even if true that would not change the result here, for we conclude that the petition must be denied under the ordinary APA standard of review.
III.
ELCON raises a number of challenges to the Commission‘s approval of the new rate design. While ELCON maintains that
First, ELCON contends that the Commission failed to consider objections that the ICAP charges under the Demand Curve were too high and that the slope of the Demand Curve was too gradual. ELCON points to the testimony of expert witness David W. Segal indicating that the Commission overestimated the annualized cost of installing a new peaker plant, underestimated the useful life of a new peaker plant, ignored the revenue earned from the energy and ancillary service markets, and overestimated the value of reliability to consumers. In fact, the Commission considered the objections raised by ELCON and determined based on the evidence offered by NYISO and its expert witness Dr. David B. Patton that the parameters of the ICAP Demand Curve were “appropriate and reasonable.” Rehearing Order, 105 F.E.R.C. ¶ 61,108, at 61,623. After reciting the objections to Dr. Patton‘s estimates, see id., the Commission explained that it considered the parameters to be reasonable, emphasizing the fact that the ICAP Demand Curve was initially proposed by the New York Public Service Commission (“NYPSC“) and reflected a year of negotiations and discussions among NYPSC, NYISO, and ICAP market participants. See id. at 61,618, 61,623; Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,754. While the Commission expressed some uncertainty about the accuracy of the exact points and slope of the Demand Curve, it observed that confirming specific parameters would require “some measure of experience,” and required NYISO to monitor the results of the Demand Curve, expecting NYISO to review the Demand Curve with stakeholder input and to adjust the parameters as appropriate, subject to Commission approval. Rehearing Order, 105 F.E.R.C. ¶ 61,108, at 61,623. Moreover, as the Commission points out in
Second, ELCON contends that the Commission failed to consider the increased costs that the ICAP Demand Curve will impose on electricity consumers. It cites Dr. Patton‘s estimate that the ICAP Demand Curve will increase costs by $70 million in New York City and $84 million in the rest of the State during the first year, Dr. Carl Pechman‘s estimate that the Demand Curve will increase costs by $700 million over a three-year period, and Strategic Energy‘s estimate that the Demand Curve will increase costs by $1 billion per year. The Commission considered and rejected these estimates. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,757-758. Noting that one intervenor concluded that Dr. Pechman‘s estimate was “grossly overstated,” and that several intervenors argued that the long-term benefits of the ICAP Demand Curve would outweigh any short-term costs, id. at 61,757, the Commission concluded that by reducing volatility in ICAP revenues and spurring new generation capacity, the ICAP Demand Curve would “provide long term benefits to NYISO markets and customers,” id. at 61,758. Indeed, the Commission emphasizes in its brief Dr. Patton‘s conclusion that any costs of the ICAP Demand Curve are “transitional and will be eliminated over time as the market moves toward a long-run equilibrium.” Patton Aff. ¶ 61, at 17; Br. of Resp‘t at 37. While the Commission recognized that it could not predict the exact amount of savings achieved by the ICAP Demand Curve, see Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,758, it did cite Dr. Patton‘s estimates that a 1% increase in capacity would yield savings of $1 million per year in the long term, and that even in the short term, the ICAP Demand Curve
Third, ELCON contends that the Commission failed to consider evidence in the record that the ICAP Demand Curve will not encourage investment in new generation capacity. ELCON cites comments by Energy East, New York City, Strategic Energy, and the Morgan Stanley Group suggesting that reluctance to build new generation facilities in New York State arises from concerns other than the structure of the ICAP market, and that the ICAP Demand Curve offers an “indiscriminate subsidy” to all capacity suppliers without requiring them to use their increased revenues to build new generation facilities in New York. The Commission considered and rejected these comments. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,763-64. The Commission explained that while it did not expect the ICAP Demand Curve to “alone result in more financing,” it did expect that “more reliable and predictable ICAP revenues would contribute to a more reliable overall revenue structure for an ICAP supplier and thus play some role in improving that supplier‘s prospects for financing.” Id. That expectation is supported by substantial evidence in the record, including the expert witness testimony of Dr. Patton, Dr. Thomas Paynter, and Mark Younger. Moreover, even if the record does not show “for certain that the Commission‘s
Fourth, ELCON contends that the Commission failed to consider its objection that the ICAP Demand Curve replaces price volatility with quantity volatility, thus discouraging bilateral contracts and destroying the stability needed to encourage investment in new generation capacity. According to ELCON, quantity volatility is more damaging than price volatility because LSEs “have no way to hedge against the uncertainty associated with the monthly required quantity.” Br. of Pet‘r at 37. The Commission considered and rejected this objection. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,759-760. In response to the contention that quantity volatility could not be hedged, the Commission quoted Dr. Patton‘s testimony that “LSEs will have the opportunity to purchase any quantity of capacity they desire in the forward market and the spot market provides a means to sell back any excess capacity purchased forward.” Id. at 61,760 (quoting Supplemental Patton Aff. ¶ 17, at 5) (internal quotation marks omitted). The Commission further explained on rehearing that LSEs could “hedge most of
Fifth, ELCON contends that the Commission failed to consider alternatives to the ICAP Demand Curve proposed by Strategic Energy, Con Edison, Energy East, and New York City. The Commission considered the two alternatives proposed directly to it and not to NYISO—bilateral contracts and demand response—and determined that they were compatible with the ICAP Demand Curve. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,763; Rehearing Order, 105 F.E.R.C. ¶ 61,108, at 61,621. Because the Commission provided a reasonable explanation for choosing the ICAP Demand Curve despite the proposed alternatives, the court defers to the Commission‘s policy choice.
ELCON‘s final objection, that the Commission “ignored substantial evidence that supply conditions in New York are not critical and thus do not justify the level of the Demand Curve ICAP charges,” Br. of Pet‘r at 23, is not properly before the
Accordingly, because ELCON fails to show that the Commission‘s approval of the new rate design was arbitrary and capricious, we deny the petition for review.
o:\slip\wp\2004\03-1449 Electricity Consumers FINAL.wpd
[sent to printer]
