History
  • No items yet
midpage
Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC
363 S.W.3d 901
Tex. App.
2012
Read the full case

Background

  • Morrell Masonry Supply, as a derivative claimant, supplied materials to Joyce's Stucco Design for Lupe's Shenandoah Reserve project and sought fund-trapping and retainage remedies against Lupe's and its insurer Berkley.
  • Morrell mailed a January 13, 2009 notice of claim to Lupe's, Comanche (original contractor), and Joyce's for invoices totaling $20,719.33, covering October 2008 and November 2008 deliveries.
  • Chapter 53 requires separate timely notices to the original contractor and then to the owner for perfection of a derivative lien, with specific two- and three-month timelines and a later lien affidavit deadline.
  • Morrell's notice was timely as a three-month notice but untimely as a two-month notice for October 2008 materials; the October 2008 lien was not perfected.
  • The trial court granted Lupe's summary judgment on fund-trapping and retainage for October 2008, and Morrell prevailed only on a November 2008 amount, with other relief denied; Lupe's obtained a large attorney's fee award.
  • The appellate court overruled Don Hill to the extent it allowed perfecting a lien without timely notices, and affirmed the trial court's denial of Morrell's October 2008 lien and related relief.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Derivative lien perfection requires timely notice Morrell contends late first notice to Comanche is harmless Lupe's asserts timely notice to original contractor is required for lien validity Yes; timely notice required; Don Hill overruled
Effect of late pre-lien notice on fund-trapping Late notice to Comanche should not defeat fund-trapping against owner Late notice prevents perfection and fund-trapping recovery Late pre-lien notice defeats fund-trapping for October 2008
Effect on retainage when lien not perfected Retainage claim should survive despite late notices Retention rights hinge on perfected lien Retainage claim failed for October 2008
Foreclosure and bond effect Bond does not bar claims against Lupe's beyond foreclosure Bond precludes foreclosure on property Foreclosure barred; bond precluded lien foreclosure but not personal liability
Attorney's fees award reasonableness Fees should reflect Morrell's success and reasonable work Fees reasonable given complexity and duration Court acted within discretion; fee award upheld

Key Cases Cited

  • Don Hill Construction Co. v. Dealers Electrical Supply Co., 790 S.W.2d 805 (Tex. App.—Beaumont 1990) (don’t overlook lien perfection requirements; Don Hill limited by later overruling)
  • Sledge v. Dealers Elec. Supply Co., 653 S.W.2d 283 (Tex. 1983) (subcontractor liens depend on statutory notice timing; original vs. owner liability)
  • Dealers Elec. Supply Co. v. Scoggins Constr. Co., 292 S.W.3d 650 (Tex. 2009) (McGregor Act remedies not exclusive; trust fund considerations)
  • First Nat'l Bank in Graham v. Sledge, 653 S.W.2d 283 (Tex.1983) (early precedent on lien perfection and subcontractor notices)
Read the full case

Case Details

Case Name: Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC
Court Name: Court of Appeals of Texas
Date Published: Mar 22, 2012
Citation: 363 S.W.3d 901
Docket Number: 09-11-00284-CV
Court Abbreviation: Tex. App.