History
  • No items yet
midpage
168 So. 3d 905
Miss.
2015
Read the full case

Background

  • Blanton appeals challenge to MPC rate increases approved by the Public Service Commission under Mississippi's Base Load Act (CWIP/ mirror-CWIP).
  • Base Load Act authorizes prudently-incurred preconstruction, construction, operating costs in rate base, but requires prudency findings and hearings.
  • MPC proposed Kemper Project costs grow dramatically from $2.88B to over $6.17B with no prudency hearings held.
  • Commission approved rate increases for 2013–2014 based on mirror-CWIP without proper prudency determinations or notice to ratepayers.
  • Settlement agreement between MPC and the Commission was negotiated privately, later challenged as ex parte and improper, and notice to ratepayers was deficient.
  • Court reverses the March 5, 2013 order, remands for compliance with the opinion, and requires refunds and notice for future proceedings.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether CWIP under the Base Load Act is an unlawful tax Blanton: CWIP taxes violate the Constitution MPC/Commission: CWIP valid under Act as rate mechanism CWIP is not a tax (and not unconstitutional on this ground)
Whether the Base Load Act and CWIP recovery comply with constitutional constraints Blanton contends Act violates due process and state/federal constitutions MPC/Commission: Act provides lawful regulatory framework Record shows lack of prudency findings and compliance; holding depending on remand
Whether ratepayers received due process due to lack of notice Blanton: notice was insufficient to ratepayers MPC/Commission: ratepayers participated; notice adequate Due process concerns acknowledged; remand with notice requirements mandated
Whether ex parte settlement negotiations invalidated the settlement and CWIP approval Blanton: ex parte communications violated §77-2-13; settlement invalid MPC/Commission: negotiations were on appeal or not prejudicial Settlement invalid if prejudicial; court determines proceedings remanded where appropriate
Whether the Settlement Agreement and CWIP approval withstand statutory constraints Blanton: private agreement outside statutory authority MPC/Commission: authority exists under Base Load Act Settlement and CWIP approval contests sustained for remand and compliance with law

Key Cases Cited

  • Pittman v. Miss. Pub. Serv. Comm’n, 520 So.2d 1355 (Miss. 1987) (limits Commission to lawful authority; no rate increases for services never delivered)
  • City of Starkville v. 4-Cnty. Elec. Power Ass’n, 909 So.2d 1094 (Miss. 2005) (strong presumption of validity; constitutional questions may be decided on other grounds)
  • Warner-Lambert Co. v. Potts, 909 So.2d 1092 (Miss. 2005) (preserves judicial approach to constitutional challenges where other grounds exist)
  • Memphis Light, Gas & Water Div. v. Craft, 436 U.S. 1 (U.S. 1978) (due process notice requirement in public proceedings)
  • Power Comm’n v. Hope Natural Gas Co., 320 U.S. 591 (1944) (abandoned fair value; end-result standard in ratemaking)
  • Smyth v. Ames, 169 U.S. 466 (1889) (original basis for rate regulation principles; used-and-useful concept evolution)
  • Jersey Central Power & Light Co. v. FERC, 810 F.2d 1168 (D.C. Cir. 1987) (used-and-useful principle; CWIP debate in DC Circuit trilogy)
  • Albritton v. City of Winona, 178 So.2d 799 (Miss. 1938) (state may invest public funds for public purposes; not arbitrary under §258)
  • Londoner v. City & County of Denver, 210 U.S. 373 (1908) (due process notice requirement in assessments)
Read the full case

Case Details

Case Name: Mississippi Power Co. v. Mississippi Public Service Commission
Court Name: Mississippi Supreme Court
Date Published: Jun 11, 2015
Citations: 168 So. 3d 905; 2015 WL 3823153; Nos. 2012-UR-01108-SCT, 2013-UR-00477-SCT
Docket Number: Nos. 2012-UR-01108-SCT, 2013-UR-00477-SCT
Court Abbreviation: Miss.
Log In
    Mississippi Power Co. v. Mississippi Public Service Commission, 168 So. 3d 905