Mission1st Group, Inc.
ASBCA No. 62461, 62646
A.S.B.C.A.Aug 16, 2021Background
- Army awarded Mission1st Group (M1) a firm‑fixed‑price task order (Sept. 24, 2013) with a 9‑month base period and two 9‑month evaluated option periods; the task order also included an "Option to Extend Services" (up to 6 months) under FAR 52.217‑8 and option clauses under FAR 52.217‑9.
- M1 proposed fixed prices for base and two option periods and a not‑to‑exceed price for up to six months of extended services; M1 later experienced staffing/cost problems at proposed rates.
- The Army issued a notice of intent to exercise the first option 91 days before base‑period end (Mar. 25, 2014); M1 warned it would seek repricing or challenge any option exercise.
- The government proposed a three‑month partial extension; on June 19, 2014 it notified M1 it was exercising the Option to Extend Services; Modification P00009 (dated June 23, 2014) priced a three‑month extension.
- Parties subsequently executed bilateral Modifications P00010, P00011 and P00012, which adjusted the option funding and added a labor position; M1 later filed a certified claim seeking $3,694,336.73 for alleged improper option exercise.
- The ASBCA decided on the parties’ written submissions and denied M1’s appeals.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the FAR 52.217‑8 option to extend services was an out‑of‑sequence "option period 3" requiring prior exercise of the two evaluated options | The placement and wording in the task order show the "Option to Extend Services" is effectively option period three, so it could only be exercised after options 1–2 | The FAR 52.217‑8 option may be exercised independently; task order language and prior ASBCA precedent allow using the extend‑services option separate from evaluated option periods | The Board held the contract permitted exercise of the FAR 52.217‑8 extend‑services option independent of the evaluated option periods; Glasgow precedent bindingly supports this result |
| Whether the government timely exercised the extend‑services option "within 90 days before the expiration of the contract" | "Within 90 days" should be read as "at least 90 days before" (i.e., exercise must occur prior to the 90th day before expiration) | "Within" means inside that 90‑day window; June 19 exercise was inside the 90‑day period and the June 23 modification executed the exercise within the base period | The Board interpreted "within" by its ordinary meaning and held the June 19/23 exercise was timely (inside the 90‑day period) |
| Whether M1 waived any claim by subsequently signing bilateral modifications that funded the extension | Signing the modifications did not waive M1’s right to seek additional compensation; at most M1 waived the right to stop performance | By signing bilateral modifications that changed option funding and confirmed performance terms (including P00011), M1 accepted payment for the contested period and thus waived its claim (accord and satisfaction) | The Board held that, even assuming any initial defect, M1 waived its claim by agreeing to and signing the bilateral modifications that priced and funded the extension |
Key Cases Cited
- Lockheed Martin Corp. v. Walker, 149 F.3d 1377 (Fed. Cir. 1998) (Federal Circuit decision finding an out‑of‑sequence option exercise improper based on contract schedule and pricing)
- Bell BCI Co. v. United States, 570 F.3d 1337 (Fed. Cir. 2009) (discussing accord and satisfaction in government contract disputes)
- Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575 (Fed. Cir. 1993) (authority on accord and satisfaction principles)
- Sharp Elec. Corp. v. McHugh, 707 F.3d 1367 (Fed. Cir. 2013) (distinguishing GSA schedule terms from agency‑inserted contract terms)
