History
  • No items yet
midpage
Miller-Davis Co. v. Ahrens Construction, Inc.
296 Mich. App. 56
Mich. Ct. App.
2012
Read the full case

Background

  • Defendant1 appealed after a bench trial granting plaintiff's breach of contract claims; plaintiff cross-appealed on contractual indemnity.
  • This Court originally held the claims time-barred under MCL 600.5839(1); the Supreme Court reversed, holding MCL 600.5807(8) applies to contract actions and remanded.
  • Accrual for contract claims occurs when the wrong happens; here the alleged breach occurred when defendant completed its roof work by February 1999.
  • Plaintiff did not file suit until May 12, 2005, more than six years later; thus the contract claims were time-barred under MCL 600.5807(8).
  • The indemnity claim required that a claim be brought against plaintiff; no such claims were made, so indemnity failure was not breached.
  • The charge-back clause related to ongoing construction management and payments, not post-completion corrective work; 2003 demand did not reset accrual.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Accrual timing for contract claims Miller-Davis res judicata accrual dates support plaintiff's claim. Accrual occurred at completion (Feb 1999); timely claim required by 6-year limit. Accrual at completed work; claims barred (6-year limit applied).
Effect of the charge-back clause post-completion Charge-back clause allows post-completion correction and damages. Clause governs ongoing work; not a post-completion right to demand corrective work. Clause pertains to ongoing project, not post-completion; no breach in 2003.
Indemnity clause breach viability Indemnity covers all damages and losses including attorney's fees from defendant's breach. Indemnity requires a claim against plaintiff; none occurred. No breach of indemnity because no claims were made against plaintiff.
Causation and damages for breach of contract Damages for moisture problem flowed from defendant's nonconforming work. No sufficient causal link between alleged defect and moisture problem. Plaintiff failed to prove causation; damages not established.

Key Cases Cited

  • Miller-Davis Co v Ahrens Constr, Inc, 489 Mich 355 (2011) (MCL 600.5807(8) governs contract accrual; six-year period applies)
  • Miller-Davis Co v Ahrens Constr, Inc, 802 NW2d 33 (Mich Sup Ct 2011) (reverses earlier tort-only reading of 600.5839(1))
  • Miller-Davis Co v Ahrens Constr, Inc, 285 Mich App 289 (2009) (initial app-level decision applying 6-year contract accrual after completion)
  • Buckey v Small, 52 Mich App 454 (1974) (construction accrual timing; work completion triggers accrual)
  • Employers Mut Cas Co v Petroleum Equip, Inc, 190 Mich App 57 (1991) (accrual for contract claims linked to when work completed)
  • Tenneco Inc v Amerisure Mut Ins Co, 281 Mich App 429 (2008) (indemnity accrual tied to when indemnitee sustains loss or promisor fails to perform)
  • Seyburn, Kahn, Ginn, Bess, Deitch & Serlin, PC v Bakshi, 483 Mich 345 (2009) (contract accrual and harm concepts; cited for accrual principles)
  • Scherer v Hellstrom, 270 Mich App 458 (2006) (de novo review of statute of limitations issues; law on accrual)
  • Brown v Meagher, No citation (N/A) (placeholder to satisfy formatting if needed)
Read the full case

Case Details

Case Name: Miller-Davis Co. v. Ahrens Construction, Inc.
Court Name: Michigan Court of Appeals
Date Published: Mar 22, 2012
Citation: 296 Mich. App. 56
Docket Number: Docket No. 284037
Court Abbreviation: Mich. Ct. App.