Dеfendant Ahrens Construction, Inc., appeals by right the judgment entered after a bench trial for plaintiff, Miller-Davis Company, on its breach of contract claim. Plaintiff cross-appeals the trial court’s entry of a judgment of no cause of action on plaintiffs claim for contractual indemnity of the amount awarded for breach of contract and its attorney *292 fees for this action. Ahrens (hereafter defendant) argues that the trial court clearly erred regarding several factual findings underlying the trial court’s key ruling that defendant’s workmanship installing a roof caused a severe condensation problem in the natatorium housing the indoor pool at a YMCA complex at Sherman Lake near Augusta, Michigan. Defendаnt also contends that the trial court clearly erred in calculating plaintiffs damages and prejudgment interest. Also, defendant argues that the trial court abused its discretion by not granting it a default judgment after learning during trial that plaintiff had violated a discovery order by failing to disclose the identity of an expert plaintiff had consulted during its investigation of the condensation problem. Finally, defendant argues that the trial court erred by not granting it judgment based on the statute of repose, MCL 600.5839(1). We agree. Our resolution of this issue renders all other issues moot. We reverse and remand for entry of judgment for defendant.
A. BACKGROUND AND TRIAL
Plaintiff, a general contractor and construction manager, brought this breach of contract action against subcontrаctor Ahrens and its bondsman, Merchants Bonding Company, alleging faulty workmanship by Ahrens when installing a wooden (Timber-Deck) roofing system covering the natatorium of a YMCA recreational complex at Sherman Lake, Augusta, Michigan. During cold weather, condensation would form and drip from the ceiling of the natatorium; the parties referred to this as the natatorium moisture problem (NMP). Plaintiffs theory of the case was that the NMP was caused by rips, tears, and missing sections of a Visqueen vapor barrier installed above the inner wood tongue and groove decking system, which was supported by a “T” *293 and “sub-T” superstructure, and by defendant’s failing to install Styrofoam block insulation “tight” enough in rectangular cells that were formed by the T’s and sub-T’s. This roofing system was а last-minute cost-saving substitution for a roofing system consisting of a four-by-six inch plank ceiling, with nail-based Styrofoam insulation covered by oriented strand board (OSB or plywood), roofing felt, and a standing seam steel shell.
Defendant’s theory of the case was that the NMP was the result of several design errors, the most serious of which allowed the vapor barrier covering the uninsulated tops of the T’s to come in contact with cold outside air. Defendant supported its theory of the case with the testimony of an expert with a Ph.D. in engineering who specialized in building moisture problems. Defendant’s expert opined that moisture from the humid pool air migrated through both the wood T’s to their tops and the gaps in the tongue and groove ceiling planks, then along the underside of the vapor barrier to the top of the T’s, where it condensed and fell back down through the ceiling. Defendant’s expert also opined that any of the alleged defects in defendant’s workmanship that plaintiff found after tearing off the outer portions of the roof actually helped prevent the NMP because it allowed moisture to escape through the airspace between the insulation and the outer roof structure. Defendant also argued that the alleged defects plaintiff found were caused by plaintiff’s deconstruction of the roof.
Plaintiff theorized that the NMP was eventually “fixed” when, after a series of attempts at correcting it, 1 *294 it deconstructed the roof system in 2003 to inspect it. Plaintiff contracted with the architect and the YMCA to perform “corrective work,” which included three items that were not a part of the original plans and specifications for the roof system: (1) a spray-on rubberized waterproofing substance (Procor), (2) the sealing of any gaps between the Styrofoam block insulation and the wood “T” decking structure with spray-on, self-expanding, urethane foam, and (3) caulking the top of the T’s and sub-T’s with silicone, thereby sealing a polyethylene vapor barrier placed on top of the Procor. Plaintiff demanded that defendant perform the corrective work without compensation, but defendant refused because it believed that the NMP was the rеsult of design defects, not its workmanship. At trial, defendant’s expert testified that the added elements in the corrective work trapped moisture in the wooden structure of the roof facing the interior of the pool so that it would temporarily fix the condensation problem until sometime in the future when the Procor might break down, particularly at the tongue and groove gaps.
After a bench trial, the trial court concluded that Ahrens breached its contract with plaintiff, and that this breach caused the NMP Plaintiffs damages were calculated on the basis of expenses plaintiff incurred tearing off and reinstalling the roofing system with the “corrective measures” noted above, plus 10 percent for “overhead,” 15 perсent for a “fee,” and interest of “prime plus 2%” from December 2003 (after completion of the corrective work) to September 2007 (during trial). The trial court determined that plaintiff used Procor as a cost saving measure to mitigate its damages *295 by avoiding completely removing the roofing system elements. Both the trial court in its opinion and findings and plaintiff in its brief on appeal fail to cite any testimony or other evidence specifically establishing a causal link between Ahrens’s alleged defective workmanship and the NME Plaintiffs theory, which the trial court obviously accepted, appears to be based on the following logic: (1) deconstructing the roof revealed defective workmanship in the installatiоn of the vapor barrier and insulation; (2) the corrective work was performed using Procor as a cost saving measure, and (3) after the roof was reconstructed, the NMP was solved. However, plaintiffs CEO admitted at trial that plaintiff never determined what caused the NME On the basis of photographs taken during plaintiffs disassembly of the roof system and good old-fashioned common sense, the trial court decided that Ahrens’s poor workmanship caused the NME
The trial court concluded that “Ahrens materially and substantially breached [its] contract by performing the nonconforming and defective work described above, and upon notice and the opportunity, Ahrens failed to correct its work, or to otherwise cause it to come into conformance.” Further, the trial court determined that plaintiff “suffered damages of $348,851.50” performing corrective work. The trial court also awarded the same amount against Merchants with respect to the performance bond it had issued. 2 The court also ruled that plaintiff had no cause of action for contractual indemnity because “no claims, suits, actions, recoveries, or demands were ever made, brought or recovered against” plaintiff within the meaning of the indemnity clause in the parties’ contract. This ruling is the subject of plaintiffs cross-appeal.
*296 B. PROCEDURAL HISTORY REGARDING THE STATUTE OF REPOSE
The statute of repose at issue, MCL 600.5839, provides, in pertinent part:
(1) No person may maintain any action to recover damages for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an imрrovement to real property, nor any action for contribution or indemnity for damages sustained as a result of such injury, against any state licensed architect or professional engineer performing or furnishing the design or supervision of construction of the improvement, or against any contractor making the improvement, more than 6 years after the time of occupancy of the completed improvement, use, or acceptance of the improvement ....
(4) As used in this section, “contractor” means an individual, corporation, partnership, or other business entity which makes an improvement to real property. [Emphasis added.]
By the end of February 1999, defendant completed all its tasks regarding constructing the roof system, including installing all the wood parts, the vapor barrier, the T’s and sub-T’s, the insulation, all of which were covered by OSB nailed on top of two-by-four inch “sleepers” running perpendicular over the T’s to the top ridge of the roof. Defendant asserts that the part of the roof system it constructed was a completed “improvement” within the meaning of the statute of repose, and that the statute began to run when plaintiff immediately began “using” the “improvement” by directing another subcontractor to apply roofing felt and the standing seam steel weather barrier on top of it. Defendant certified to plaintiff that it had completed its *297 work on the roof on April 26, 1999, and plaintiff paid defendant for this work the next day. Defendant asserts that this constituted “acceptance” by plaintiff within the meaning of the statute. A temporary certificate of occupancy was issued for the entire project on June 11, 1999. 3 Plaintiff filed its complaint in this matter on May 12, 2005, more than six years, dеfendant asserts, after the “improvement” it built was used and accepted by plaintiff.
Defendant moved for summary disposition under MCR 2.116(C)(7) on August 1, 2005. Defendant’s argument then is identical to its argument now on appeal. Defendant Merchants also moved for summary disposition but on different grounds. Merchants argued that plaintiff failed to comply with a condition precedent to suit under the performance bond: filing suit within two years of defendant’s ceasing work on the project. Both motions were argued before Judge William G. Schma. 4 By opinion and order filed November 18, 2005, Judge Schma denied both motions, but he only addressed Merchants’ argument. Defendant applied for leave to appeal in this Court. This Court denied leave “for failure to persuade the Court of the need for immediate appellate review.” Unpublished order of the Court of Appeals, entered March 6, 2006 (Docket No. 266936).
This case was tried in May and September 2007 before Judge Gary C. Giguere, Jr., who succeeded Judge Schma. Defendant raised the statute of repose both in closing argument and in its written submission of proposed findings of fact and conclusions of law. The trial court issued its opinion, findings of fact, and *298 conclusions of law on December 21, 2007. Although the trial court found facts consistent with defendant’s claims regarding the application of the statute of repose, the court did not address the statute of repose. Judge Giguere found that Ahrens “completed the natatorium roof by February 18, 1999. Ahrеns submitted its final request for pay on April 26, 1999, and Miller-Davis paid Ahrens the very next day.” The trial court also described the manner in which the roof was constructed and that another subcontractor completed the final tasks after Ahrens finished its work.
C. PRESERVATION
Generally, an issue is not properly preserved for appeal if it has not been raised in, and addressed and decided by the lower court or administrative tribunal.
Polkton Charter Twp v Pellegrom,
D. STANDARD OF REVIEW
This Court reviews de novo a trial court’s ruling regarding a motion for summary disposition.
Abbott v John E Green Co,
A trial court’s findings of fact following a bench trial are reviewed for clear error, MCR 2.613(C), and the court’s conclusions of law are reviewed de novo.
In re Kostin Estate,
*300
The primary goal of judicial interpretation of a statute is to ascertain and give effect to the intent of the Legislature.
New Properties, supra
at 136. The Court must first review the language of the statute, and if it is unambiguous, must assume that the Legislature intended its plain meaning and must enforce the statute as written.
Id.; Alvan Motor Freight, Inc v Dep’t of Treasury,
Wlien reading a statute, the Court must assign to every word or phrase its plain and ordinary meaning unless otherwise defined in the statute, or unless the Legislature has used technical words or phrases that “may have acquired a peculiar and appropriate meaning in the law. . . .” MCL 8.3a;
Alvan Motor Freight, supra
at 40. Additionally, the Court may not read a word or phrase of a statute in isolation but must read each word or phrase and its placement in the context of the whole act.
Id.; Village of Holly v Holly Twp,
E. ANALYSIS
We conclude that defendant’s argument on this issue is meritorious. Because defendant is a contractor that made an improvement to real property, and because plaintiff filed its lawsuit against defendant “for any injury to propеrty . . . arising out of the defective and unsafe condition of an improvement to real property” more than six years after the “use, or acceptance of the improvement,” MCL 600.5839(1), all of plaintiffs claims against defendant are barred by the statute of repose.
MCL 600.5839 has on several occasions been subjected to judicial scrutiny. Our Supreme Court has upheld the statute as originally adopted,
*302
This Court on several occasions has opined regarding the purpose of MCL 600.5839. Specifically, “[t]he purpose of the statute of repose is to shield architects, engineers, and contractors from stale claims and relieve them of open-ended liability for defects in workmanship.”
Ali v Detroit,
This Court has also addressed the meaning of the undefined word “improvement,” as used in MCL 600.5839. In
Pendzsu,
this Court reviewed the reasoning of the Sixth Circuit Court of Appеals in
Adair v Koppers Co, Inc,
741 F2d 111 (CA 6, 1984), which construed a similar Ohio statute of repose applicable to actions for damages “ ‘arising out of the defective and unsafe condition of an improvement to real property.’ ”
Pendzsu, supra
at 410, quoting
Adair, supra
at 112. Noting that this Court in
Fennell v Nesbitt, Inc,
This Court in
Travelers Ins Co v Guardian Alarm Co,
An improvement is a “permanent addition to or betterment of real property that enhances its capital vаlue and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.” The test for an improvement is not whether the modification can be removed without damage to the land, but whether it adds to the value of the realty for the purposes for which it was intended to be used. In addition, the nature of the improvement and the permanence of the improvement should also be considered. Furthermore, if a component of an improvement is an integral part of the improvement to which it belongs, then the component constitutes an improvement to real property. [Travelers, supra at 478 (citations omitted; emphasis added).]
*304 The Court then held that “the new cirсuit panel box and transformer were integral components of an electrical system that was essential to the operation of the facility”; consequently, they were “an improvement to real property for the purposes of the statute of repose.” Id. at 478-479.
Also, following the Pendzsu decision, this Court in Abbott rejected the plaintiffs claim that the statute applied only to the completed improvement, not the contractor’s workmanship in making the improvement. Abbott, supra at 199-201. This Court observed that like statutes of limitations, the statute of repose must be construed in a manner that advances its purpose, i.e., to “protect engineers, architects, and contractors from stale claims and to eliminate open-ended liability for ‘defects in workmanship.’ ” Id. at 200, quoting Pendzsu, supra at 410. The Court held that the statute protected the defendant from the plaintiffs stale workmanship claims. “Contractors would not enjoy the ‘repose’ that the statute intends to guarantee if plaintiffs, barred from bringing claims arising out of the finished result of an improvement, could nonetheless bring claims arising out of the construction practices employed in making the improvement.” Abbott, supra at 201.
Applying the reasoning of these cases to the undisputed facts of the instant case, we conclude that defendant was a “contractor” that made an improvement to real property. Specifically, the wooden roof deck system that defendant constructed or installed, with its component parts of T’s, sub-T’s, vapor barrier, insulation, sleepers, and OSB, was itself an integral component of the natatorium’s roof to which another subcontractor added roofing felt and an outer steel skin. The completed roof was an integral component of the building. The wooden roof deck system was a permanent addition *305 to real property that enhanced its value, involved the expenditure of labor and money, and was designed to make the property more useful or valuable. Travelers, supra at 478. In sum, defendant is a “contractor” who made “an improvement to real property.” MCL 600.5839(4). Further, the cases reviewed suggest that plaintiffs claim against defendant for defective workmanship is within the ambit of the statute. Abbott, supra at 200; Pendzsu, supra at 410; Ali, supra at 587-588.
Plaintiff, however, argues that MCL 600.5839(1) does not apply to this case because its claim is for breach of an express promise, not for “damages for any injury to property ....” Plaintiff relies on
City of Litchfield v Union Constr Co,
unpublished opinion per curiam of the Court of Appeals, issued October 17, 1997 (Docket No. 189823), which is without binding precedential authority. MCR 7.215(C)(1). Likewise, lower federal court decisions on which
Litchfield
relied lack binding authority.
Abela v Gen Motors Corp,
While the underlying claim in this cаse is arguably closer to the roofing tiles that did not perform as warranted in
Weeks
than to the roof that collapsed in
Michigan Millers,
we still conclude that the
Litchfield-Huhtala-Weeks
reasoning is inapposite to the present case. First, the more specific provisions of MCL 600.5839(1) apply over an arguably applicable general statute of limitations. See
Citizens Ins Co, supra
at 664,
citing Michigan Millers, supra
at 378; See also
Ostroth v Warren Regency, GP, LLC,
Second, the analysis of
Litchfield-Huhtala-Weeks
examines the nature of the plaintiffs claim to determine which potentially applicable statute of limitations might apply whereas MCL 600.5839(1) by its plain terms applies to
“any action
to recover damages for
any injury
to property, real or personal,. . . arising out of the defective and unsafe condition of an improvement to real property. . . .” (Emphasis added.) The terms that the Legislature used in MCL 600.5839(1) are broad and all-inclusive. Courts may consult a dictionary to learn the common and approved meaning of undefined statutory terms.
Halloran v Bhan,
Next, we address the question whether the six-year limitations period of MCL 600.5839(1) exрired before plaintiff filed its complaint on May 12, 2005. The statute provides for three potential events that might trigger the running of its limitations period: “the time of occupancy of the completed improvement, use, or acceptance of the improvement... .” MCL 600.5839(1) (emphasis added). The Court in Beauregard-Bezou discussed this language, observing that “[w]here the use of the disjunctive ‘or’ creates ambiguity in a statute, the language of the statute must be construed to give effect to the Legislature’s intent, and the words of the statute must be construed in light of the general purpose sought to be accomplished by the Legislature.” Beauregard-Bezou, supra at 393. The Court noted that the words “and” and “or” are often misused in drafting statutes, but “the literal meaning of ‘or’ should be followed unless it renders thе statute dubious.” Id. The Court, id., concluded that the literal interpretation of the word “or” as used in MCL 600.5839(1) would not *309 render that portion of the statute dubious. Other panels of the Court have agreed with Beauregard-Bezou. See Abbott, supra at 204 n 6, and Travelers, supra at 481. The Travelers Court opined: “The statute of repose is triggered by the time of occupancy or use or acceptance of the improvement. Only one of the criteria set forth in the statute of repose must be met to trigger the running of the period of limitation.” Id. (emphasis in original; citations omitted).
Here, the parties agree that plaintiff filed its complaint within six years following “occupancy of the completed improvement.” Specifically, the parties agree that this event occurred on or after June 11, 1999, the date on which the proper authority issued a temporary certificate of occupancy and the date on which the parties agree the entire project was substantially completed. But it is undisputed, and the trial court so found, that defendant completed its work on its part of the natatorium’s roof by the end of February 1999. Thereafter, the evidence clearly establishes that another contractor completed the final phase of the roofs construction by attaching the roofing felt and the standing seam steel skin. Plaintiffs exhibit 9, the minutes of a work-progress meeting on February 18, 1999, indicates that over the prior two weeks Ahrens completed its roof work at the recreational building, and that work for the next two weeks contemplated subcontractor Architectural Glass & Metals’ completing the metal roof at the recreation building. We agree with defendant that this evidence establishes that the “improvement” it made, the wooden roof deck system, was completed and in “use” by plaintiff and other subcontractors who were finishing the project. Clearly, Architectural Glass & Metals was using the wooden roof deck system to install the outer steel roof covering in February 1999. Thus, the wooden deck system was in use by plaintiff as the *310 construction manager directing the work of the various subcontractors for the purpose of completing the entire project.
Plaintiffs contention that “use” of the “improvement” could not have occurred until after June 11, 1999, the date the tempоrary occupancy certificate was issued, would require one to read the statute to mean that only the owner of the real property can trigger the running of its limitations period. Although policy arguments could be advanced for or against such an interpretation of the statute, the rules of judicial construction of statutes require that statutes be enforced as written. Alvan Motor Freight, supra at 39. The triggering event of “occupancy of the completed improvement” certainly implies “occupancy” by the owner, or at least one having the right to occupy the completed improvement. But the statute does not so limit “use, or acceptance of the improvement....” It is contrary to the rules of statutоry construction to read into a statute a provision that is not within the manifest intention of the Legislature as derived from the language of the statute itself. Roberts, supra at 63.
Additionally, assuming that the Legislature’s failure to specify whose “use” of the “improvement” triggers the running of the limitations period renders the statute ambiguous, the statute must be given a reasonable construction consistent with its purpose. See Michigan Millers, supra at 373; Beauregard-Bezou, supra at 393 (“the words of the statute must be construed in light of the general purpose sought to be accomplished by the Legislature”). “The purpose of the statute of repose is to shield architects, engineers, and contractors from stale claims and relieve them of open-ended liability for defects in workmanship.” Ali, supra at 587-588. The purposе of the statute is not to protect owners; they *311 remain potentially liable to third parties for defects in the premises even if caused by a contractor’s defective workmanship. Id. In light of the statute’s purpose, it is reasonable to construe the word “use” in the statute as “use” of the “improvement” for its intended purpose by any lawfully authorized person or entity. So construed, the improvement that defendant made, the wooden roof system, was used by authorized persons and entities in February 1999 for the purpose intended when plaintiff and plaintiffs designated subcontractor completed the roofs construction by installing roofing felt and the outer steel skin. At the same time, plaintiff and other authorized subcontractors used the roof deck completed by defendant for the purpose intended: shielding the interior of the building and its occupants from the elements.
With respect to “acceptance of the improvement,” plaintiff does not argue that it could not trigger “acceptance” under the statute, only that the facts show that it never, in fact, accepted the roof deck system that defendant constructed. Moreover, even if the owner of the improvement must trigger “acceptance,” plaintiff as the general contractor-construction manager for the project was the authorized representative of the owner for purposes of supervising construction, deeming whether subcontractor work was acceptable under the subcontract’s “charge-back” provision, and having the ability to withhold payment for unacceptable work. Here, the undisputed facts, and as found by the trial court, establish that defendant “completed the natatorium roof by February 18, 1999[,] .. . submitted its final request for pay on April 26, 1999, and Miller-Davis paid Ahrens the very next day.” Although plaintiff asserts it never “accepted” defendant’s work on the roof, plaintiffs own actions in accepting defendant’s certification that the roof work had been completed, and then paying *312 for that work, speaks louder than its litigation denials. In sum, we conclude that the facts establish that by the end of April 1999 plaintiffs actions constituted “acceptance of the improvement” defendant made to real property triggering the running of the six-year limitations period of MCL 600.5839(1). Travelers, supra at 481.
Plaintiff misplaces reliance on foreign caselaw to argue that acceptance cannot waive its right of action on defective workmanship because such cases are not binding precedent,
Mable Cleary Trust v Edward-Marlah Muzyl Trust,
On the basis of the foregoing analysis, we hold that the statute of repose with respect to the improvement *313 to real property that defendant made, the wooden roof deck system over the YMCA’s natatorium, commenced running as a result of “use” by plaintiff, other subcontractors, or the owner, by the end of February 1999. Further, we hold that the facts establish that plaintiff “accepted” the improvement by the end of April 1999 when plaintiff accepted defendant’s certification that its work on the roof had been completed and paid defendant for that work. Both these dates occurred more than six years before plaintiff filed its complaint, which states a claim “for any injury to property.. . arising out of the defective and unsafe condition of an improvement to real property” and a claim for “indemnity for damages sustained as a result of such injury . ...” MCL 600.5839(1). Consequently, plaintiffs claims against defendant are time-barred. Michigan Millers, supra at 378; Beauregard-Bezou, supra at 394.
Because we have resolved the argument regarding the statute of repose in defendant’s favor, all other issues raised in defendant’s appeal and in plaintiffs cross-appeal are moot.
We reverse the judgment of the trial court awarding plaintiff damages for breach of contract. We remand this case to the trial court for entry of a judgment in defendant’s favor on all of plaintiffs claims against defendant. Defendant, being the prevailing party, may tax costs pursuant to MCR 7.219. We do not retain jurisdiction.
Notes
These attempts at solving the NMP included experimentation with building temperature and pressurization, sealing the juncture between *294 the roof and walls, installing roof ridge vents, adding vents below skylights, experimenting with ceiling fans, and additional work on the soffits. These efforts helped but did not resolve the NME
Merchants did not appeal and settled with plaintiff.