Mendoza v. Fonseca McElroy Grinding Co. Inc.
3:15-cv-05143
N.D. Cal.Nov 28, 2016Background
- Plaintiffs were union operating engineers employed by Fonseca McElroy Grinding (FMG) and later Granite Rock on California public works road projects; they operated milling machines on-site and performed offsite "mobilization" tasks (loading, securing, truck checks, transporting milling machines to/from Granite Rock/FMG yards).
- Plaintiffs were paid DIR prevailing wage rates for on-site operation of milling machines but were paid a lower "Lowbed Transport" rate under a Memorandum of Agreement (MOA) with the union for the offsite mobilization work.
- The MOA applied to mobilization work and acknowledged DIR could later determine noncompliance; Granite Rock and FMG were signatories to the MOA and the Master Agreement.
- Plaintiffs sued, asserting among other claims that mobilization work was subject to California prevailing wage law; the court considered cross-motions for partial summary judgment limited to that prevailing-wage issue.
- Key undisputed facts: the yards/storage locations where mobilization occurred were permanent and not established for any particular public works project; no public-works contracts or industry customs were presented showing the mobilization was required by the contracts.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether offsite mobilization (loading, securing, truck checks, transporting milling machines from permanent yards) is "in the execution of" a public works contract and thus covered by California prevailing wage law | Mobilization is integral: without the machine on-site the contract cannot be executed; travel/transport time is compensable under DIR guidance; applying prevailing wage furthers protective purpose | Mobilization is independent, performed at permanent yards not dedicated to projects and thus not an integrated part of the construction "flow"; MOA properly set lower transport rate | Court held mobilization work is not "in the execution" of the public works contracts and not subject to prevailing wage; granted defendant summary judgment and denied plaintiffs’ motion |
Key Cases Cited
- O.G. Sansone Co. v. Department of Transportation, 55 Cal. App. 3d 434 (explains when hauling is integral to a public works contract)
- Williams v. SnSands Corp., 156 Cal. App. 4th 742 (sets factors for whether offsite transport is integral to execution of contract)
- Sheet Metal Workers’ Int’l Ass’n, Local 104 v. Duncan, 229 Cal. App. 4th 192 (offsite fabrication at permanent, nonexclusive facilities not covered by prevailing wage)
- Lusardi Constr. Co. v. Aubry, 1 Cal. 4th 976 (overview of prevailing wage law purpose and statutory interpretation approach)
- Morillion v. Royal Packing Co., 22 Cal. 4th 575 (travel time may be compensable when employees are under employer control)
- H.B. Zachry Co. v. United States, 344 F.2d 352 (Davis–Bacon context: bona fide material suppliers and limits on coverage)
