Opinion
Plaintiffs O. G. Sansone Co. and Robert E. Fulton Co., as joint venturers, were prime contractors for defendant Department of Transportation on a federally funded public works project for the construction of 17.4 miles of Interstate Highway 5 in Kings County, California. After plaintiffs’ work on the project had been accepted as complete, defendant withheld from the amount earned by plaintiffs the sum of $29,578.65 on the ground that there had been violations of both state and federal laws relating to the payment of prevailing wages on a public works construction project. Thereafter plaintiffs brought this action seeking declaratory relief with respect to the constitutionality of Labor Code sections 1726, 1727 and 1775 and the Work Hours Standards and Safety Act of 1962 and with respect to the applicability of those statutes under the circumstances of this case. Plaintiffs also sought release of the sum withheld from them by defendant.
At the trial the case was submitted by plaintiffs and defendant on the “facts established by the pleadings, Answers to Interrogatories, response to Request for Admissions, and stipulation of the parties,” as well as certain other evidence which was documentary in nature. The court made findings óf fact and conclusions of law and rendered its judgment in favor of defendant.
*439 The trial court found that defendant awarded to plaintiffs the contract to construct 17.4 miles of Interstate Highway 5 in Kings County, California, which was to be part of the Federal Interstate Highway System, for the bid sum of $7,656,921.80. The contract included, among other matters, the general prevailing wage rate publication dated May 1970. The construction involved federal financing. Federal prevailing wage rate provisions were included in section 5-2 of the contract special provisions.
Plaintiffs subcontracted pay item 18 under the contract which called for “incorporation of approximately 126,000 cubic yards of Class 3 aggregate subbase into the construction project.” On June 23, 1971, plaintiffs requested “that the State approve an intention to subcontract 33 percent of pay item 18 to L. D. Folsom, Inc., of Coalinga, California, that work being loading, placing, and compacting of the material, and 41 percent of pay item 18, involving hauling only, to Wright Brothers Transportation of Visalia, California.” The state approved the request as to a subcontract with Wright Brothers on July 21, 1971.
Plaintiffs entered into an agreement, designated as a subcontract, with Buddy Wright, an individual doing business as Wright Brothers Transportation, which incorporated the provisions of the prime contract and directed the attention of the subcontractor to section 7 of the State Highway Contract Special Provisions entitled “Federal Requirements for Federal Aid Construction Projects.”
Wright Brothers Transportation (hereinafter designated as “Wright”) subcontracted a portion of its work to John W. Heck Trucking, Inc. (hereinafter designated as “Heck”). The court found that “there was no privity of contract between plaintiffs and Heck, and Heck was never specifically requested as a subcontractor nor approved by the State . . . but did function as a second-tier subcontractor to Wright.” At all times herein involved Wright and Heck were “independent truckers serving the general public” and at no time were they licensed as contractors by the State of California.
Wright and Heck hauled .“Class 3 aggregate subbase materials from locations not on the project site, but located adjacent to and established exclusively to serve the project site pursuant to private borrow agreements between plaintiffs and third parties.”
The court found that from June 21, 1971, through July 14, 1971, and from September 8, 1971, through October 19, 1971, and on November *440 23, 1971, employees of Wright and Heck worked on the project and during that time Wright and Heck “submitted false and fraudulently certified weekly payroll documents to plaintiffs for submission to the State” and that those “certified documents purported to evidence the payment of at least the minimum contract prevailing wage rates specified to the employees of Wright and Heck.” The state notified plaintiffs by letter dated December 23, 1971, that Wright and Heck had failed to pay prevailing wages and fringe benefits to their employees pursuant to the terms of the contract. Plaintiffs’ work was accepted by the state as having been completed and notice of completion was filed on February 29, 1972.
As a result of the wage underpayments and violations of both state and federal prevailing wage laws, the state withheld the sum of $29,578.65 from money earned by plaintiffs. The state determined that the underpayment of wage and fringe benefits with respect to the employees of Wright and Heck and the penalties resulting therefrom were as follows:
“ Wage and
Fringe State Federal
Benefits Penalties Penalties
Wright Brothers Transportation $8,102.45 $9,850.00 $1,470.00
John W. Heck Trucking, Inc. $4,677.96 $9,850.00 $1.340.Q0”
The court further found: “Plaintiffs were not given prior notice, apart from the language of the controlling State and Federal statutes and the terms of the contract documents, that defendants would withhold amounts earned by plaintiffs for work performed on the project by reason of the specific alleged failure of Wright and Heck to pay prevailing wages. [H] . . . There was no hearing conducted by defendant, either prior to or subsequent to the withholding of amounts earned by plaintiffs for work performed on the project here involved by reason of the failure of Wright and Heck to pay the contract minimum prevailing wage rates.”
Plaintiffs filed a claim with the State Board of Control which was denied. Thereafter this action was timely commenced.
*441 I
The Coverage Issue
At the times pertinent herein Labor Code section 1771 provided as follows: “Not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the public work is performed, and not less than the general prevailing rate of per diem wages for holiday and overtime work fixed as provided in this chapter, shall be paid to all workmen employed on public works exclusive of maintenance work.” Labor Code section 1772 was as follows: “Workmen employed by contractors or subcontractors in the execution of any contract for public work are deemed to be employed upon public work.” Labor Code section 1774 provided: “The contractor to whom the contract is awarded, and any subcontractor under him, shall pay not less than the specified prevailing rates of wages to all workmen employed in the execution of the contract.”
Plaintiffs contend that the California and federal statutes relating to payment of prevailing wages on public works projects apply only to wages paid by either the contractor or a subcontractor and that Wright and Heck were not subcontractors within the meaning of the state and federal prevailing wage statutes.
We have found no California cases discussing who is and who is not a subcontractor under the state’s prevailing wage laws. In contending that Wright and Heck were not subcontractors under the circumstances of this case, plaintiffs rely on cases dealing with the definition of a subcontractor under the mechanic’s lien law.
(Theisen
v.
County of Los Angeles,
*442
However, the reasoning of another case, also cited by plaintiffs, affords more guidance with respect to the resolution of the question presented in this case. In
H. B. Zachry Company
v.
United States
(1965)
In Zachry the court held that Glover was not a subcontractor, stating (344 F.2d at pp. 360-361): “The suppliers from which the material for the contracts in suit were obtained were in the business of selling such materials to the general public and were not established specifically to furnish materials for plaintiff’s contracts. Glover was and is an indepen *443 dent trucking concern and indeed appears to have been the major transporter of construction materials in the area. . . . [1Í] In this case we hold that Glover’s employees were not covered by the labor statutes because of the nature of the function Glover performed, namely, the delivery of standard materials to the site—a function which is performed independently of the contract construction activities. We think this decision is a logical extension of the congressional intent to exclude employees of materialmen from the coverage of the Davis-Bacon Act.”
In the case presently before this court the subbase materials were not obtained from an established independent material supplier. Rather, as stipulated by the parties: “28. The subbase materials hauled by Wright Bros. Transportation and John W. Heck Trucking, Inc. were not furnished to plaintiffs by the State of California; the subbase materials were acquired by plaintiffs from third parties pursuant to private borrow agreements. [18] [If] 29. The subbase materials hauled by Wright Bros. Transportation and John W. Heck Trucking, Inc. were taken from locations adjacent to and established exclusively to serve the project site, though not located physically on the project site, and were delivered by the said firms to the project site. [18]”
The parties further stipulated as follows: “30. The subbase materials hauled by Wright Bros. Transportation and John W. Heck Trucking, Inc. were used by plaintiffs in the performance of work item 18 of the prime contract identified as: Class 3 Aggregate Subbase.”
In section 25-1.01 of the Standard Specifications the work to be performed under work item 18 of the prime contract was described as follows: “This work shall consist offurnishing, spreading and compacting aggregate subbases as specified in these specifications and the special provisions.” (Italics added.) Plaintiffs did not furnish the subbase materials by securing them through a standard commercial supplier. Instead plaintiffs acquired the materials “from third parties pursuant to private borrow agreements.” In performance of plaintiffs’ agreement to furnish these subbase materials under the prime contract, plaintiffs subcontracted the hauling of the materials from the locations “adjacent to and established exclusively to serve the project site.”
In
Green
v.
Jones,
In the course of determining wheth'er Jones’ employees were covered under the state’s prevailing wage law the court made reference to an opinion of the Wisconsin Attorney General (38 Ops.Wis.Atty.Gen. 481, 483) which the court treated as embodying authoritative internal legislative history of the statute. The court stated (
The Wisconsin court decided that Jones’ employees were covered because under the facts of that case the materials hauled were dumped or spread directly on the roadbed and were immediately used in the construction of the project. Thus, the court stated (
In the case presently before this court plaintiffs, contracted to furnish the subbase material. In order to fulfill the contract, plaintiffs entered into private borrow agreements with third parties so as to obtain borrow sites designed to supply the project site exclusively with subbase materials and plaintiffs contracted with Wright to haul the material to the adjacent project site. Wright and Heck were not materialmen or employees of materialmen. Rather, plaintiffs contracted with Wright to perform an integral part of plaintiffs’ obligation under the prime contract. The trial court properly determined that under the circumstances of the instant case Wright and Heck were subcontractors.
II
The Due Process Issue
Plaintiffs contend as follows: “No person may be deprived of his property without prior notice of proceedings held for such purpose and an opportunity to be heard therein. Such notice and an opportunity to be heard must be provided by the statute itself. Defendant has withheld funds admittedly earned by plaintiffs to pay additional wages to employees of subcontractors and to satisfy penalties and forfeitures provided by law for violation of the prevailing wage laws. The statutes upon which the State of California relies in this matter provide for the appropriation of plaintiffs’ property to satisfy claims and penalties that are the responsibility of a subcontractor without provision for notice or hearing in violation of the constitutional guarantees of due process of law.”
The statutory scheme which plaintiffs challenge herein provides for a penalty or forfeiture in the event of violations of the prevailing wage provisions. Labor Code section 1775 is in pertinent part as follows: “The contractor shall, as a penalty to the State or political subdivision on whose behalf the contract is made or awarded, forfeit twenty-five dollars ($25) for each calendar day, or portion thereof, for each workman paid less than the stipulated prevailing rates for such work or craft in which such workman is employed for any public work done under the contract by him or by any subcontractor under him. The difference between such stipulated prevailing wage rates and the amount paid to each workman for each calendar day or portion thereof for which each workman was paid less than the stipulated prevailing wage rate shall be paid to each *446 workman by the contractor, and the body awarding the contract shall cause to be inserted in the contract a stipulation that the provisions of this section will be complied with.” (Italics added.)
Labor Code section 1727 provides that “[bjefore making payments to the contractor of money due under a contract for public work, the awarding body shall withhold and retain therefrom all amounts which have been forfeited pursuant to any stipulation in a contract for public work, and the terms of this chapter [which chapter includes the provisions with respect to the payment of prevailing wages]. But no sum shall be withheld, retained or forfeited, except from the final payment, without a full investigation by either the Division of Labor Law Enforcement or by the awarding body.” Labor Code section 1733 provides that suit may be brought “by the contractor or his assignee without permission from the State or other authority and is limited to the recovery of the penalties or forfeitures without prejudice to the contractor’s or assignee’s rights in regard to other matters affecting the contract.”
It is provided in Labor Code section 1729 that“[i]t shall be lawful for any contractor to withhold from any subcontractor under him sufficient sums to cover any penalties withheld from him by the awarding body on account of the subcontractor’s failure to comply with the terms of this chapter, and if payment has already been made to the subcontractor the contractor may recover from him the amount of the penalty or forfeiture in a suit at law.”
Plaintiffs contend that “[t]he right given to the state to withhold funds earned by plaintiffs is, in effect, the right to effect prejudgment attachment.” Plaintiffs rely on recent cases which have held various pretrial provisional remedies to be unconstitutional.
(Sniadach
v.
Family Finance Corp.,
The legislation with which we are concerned in the instant case is of a very different nature. Labor Code section 1775 provides for a forfeiture of $25 per day for each workman paid less than the prevailing wage by a contractor or a subcontractor on a public works project. That section also provides that the contractor shall pay each workman the difference between the prevailing wage and the amount actually paid to the workman for each day the workman was paid less than the prevailing wage. Labor Code section 1727 provides that the awarding body shall withhold such forfeited amounts from payments to be made to the contractor under the contract. This legislation does not concern a prejudgment remedy; rather, it involves the imposition by the state of a penalty for violation of the statutory prevailing wage requirements with respect to public works. It is apparent that the purpose of the penalty provisions of Labor Code section 1775 is primarily to secure proper payment to workmen paid less than the prevailing wage, for it is provided therein that “out of the money withheld or recovered or both there shall first be paid the amount due each workman and if insufficient funds are withheld or recovered or both to pay each workman in full the money shall be prorated among all such workmen.” As stated in
Shalz
v.
Union School Dist.,
The Legislature has the power to impose penalties for violations of its statutes. It is a usual method of compelling the performance of duties required by its statutory directives. “Thus a legislature may impose any reasonable penalty it sees fit for the violation of valid regulations. There is no inhibition upon the state to impose such penalties for disregard of its police power as will insure prompt
*448
obedience to the requirements of such regulations. [Citation.]”
(Shalz
v.
Union School Dist., supra,
In
Metropolitan Water Dist.
v.
Whitsett,
In
Atkin
v.
Kansas,
*450
In
West Coast Hotel Co.
v.
Parrish,
In
Perkins
v.
Lukens Steel Co.,
However, it is plaintiffs’ contention that under the prevailing wage legislation challenged here plaintiffs are subject to a deprivation of their property without notice or a hearing. . As was said by the United States Supreme Court in
Lambert
v.
California,
Labor Code section 1775 does provide for the giving of notice to the effect that violations of the prevailing wage law will result in the imposition of certain penalties. Thus it is there provided as follows: “. . . and the body awarding the contract shall cause to be inserted in the contract a stipulation that the provisions of this section [Labor Code section 1775] will be complied with.” The provisions of the section as to which the parties to the contract stipulate there will be compliance are, of course, those provisions relating to the $25 per day forfeiture by the contractor with respect to each workman paid less than the prevailing rate required for work done by the contractor or any subcontractor. The parties are also required to stipulate to those provisions of law relating to payment of wages to workmen representing the difference between prevailing wages and those paid workmen for each day the workmen were paid less than prevailing wages. In the case presently before this court such a stipulation with respect to prevailing wages was entered into by the parties. Thus, in the Standard Specifications section 7-1.01D it is provided in pertinent part as follows: “The Contractor shall comply with Labor Code Section 1775. In accordance with said Section 1775 the Contractor shall forfeit as a penalty to the State of California, $25 for each calendar day or portion thereof, for each workman paid less than the stipulated prevailing rates for such work or craft in which such workman is employed for any work done under the contract by him or by any subcontractor under him in violation of the provisions of the *452 Labor Code and in particular, Labor Code Sections 1770 to 1780, inclusive. In addition to said penalty and pursuant to said Section 1775, the difference between such stipulated prevailing wage rates and the amount paid to each workman for each calendar day or portion thereof for which each workman was paid less than the stipulated prevailing wage rate shall be paid to each workman by the Contractor.”
Furthermore, the trial court found as follows: “The State sent a letter to plaintiffs on December 23, 1971, giving notice that Wright and Heck had failed to pay prevailing wages and fringe benefits to their employees pursuant to the terms of the contract.”
Plaintiffs point out, however, and the trial court found that plaintiffs were not afforded a hearing prior to the imposition of the penalty. In
Merco Constr. Engineers, Inc.
v.
Los Angeles Unified Sch. Dist., supra,
That in
Merco
the appellate court was particularly concerned with the fact that the statute in question gave the awarding authority wide discretion with respect to the nature and extent of the penalty assessed is clear from the court’s discussion of the lack of need for a hearing under the prior law. Thus the court stated (
Under the California prevailing wage law the responsible awarding authority has no discretion with respect to the imposition of penalties. It is allowed only to assess $25 per calendar day for each workman paid less than the stipulated prevailing wage. Furthermore, the contractor may challenge the state’s assessment in a legal action, for which provision is made in Labor Code section 1733. In
Madonna
v.
State of California,
Devitt
v.
Haglin Co.,
In
Devitt
the prime contractors argued that the statute so construed deprived them of their property without due process of la,w. The appellate court disagreed, stating (289 N.Y.S. at pp. 631-632): “We are here dealing with an agreement between individual corporations and the state, and the law is well settled that one who undertakes to perform public work for the state must take the contract as the state tenders it, or leave it altogether. Campbell v. City of New York,
Under the statutory scheme presently before us, in acting pursuant to Labor Code section 1727 the state did not take property belonging to plaintiffs; rather, it withheld sums pursuant to the terms of its contract with plaintiffs. An involuntary burden was not placed upon plaintiffs by virtue of the legislation reviewed herein. Plaintiffs’ execution of the contract with knowledge of the penalties to be imposed if they or their subcontractors failed to pay the prevailing wages required under the contract was voluntary, and constituted consent to the provisions now challenged. (See
Winder Bros.
v.
Sterling,
The prevailing wage legislation herein involved provides for notice with respect to the governmental agency’s prevailing wage determination prior to the submission of bids on public works projects. (Lab. Code, § 1773.2.) It also provides a procedure for contesting the agency’s determination. (Lab. Code, § 1773.4.) Thereafter the contractor submits a bid based on the agency’s determination with respect to prevailing wages to be paid, and the contract, subsequently awarded for said public work in accordance with statutory requirements, contains notice of the forfeiture to be made by the contractor if either he or his subcontractor fails to comply with the contractual provisions relating to the payment of prevailing wages. (Lab. Code, § 1775.) The contractor cannot claim that he lacked notice of. or an opportunity to contest, the prevailing wage provision as determined by the agency.
When the contractor submits his bid based on the prevailing wage determination and freely enters into a contract for the public work involved, in which contract he stipulates to be subject to the penalty provisions of the prevailing wage law, he cannot be heard to say that he was denied due process of law with respect to the enforcement of the penalty provisions.
*456
As was stated by the court in
Schalz
V.
Union School Dist., supra,
HI
The Equal Protection Issue
Plaintiffs contend as follows: “Legislative classification must rest upon some substantial and intrinsic difference which suggests a reason for and justifies the particular legislation. There is neither authority nor persuasive reasoning for the arbitrary imposition of burdens upon public works contractors. The prevailing wage laws, stripped of their immunity from constitutional limitations, deny public works contractors equal protection of the laws.” Plaintiffs argue that the prevailing wage laws discriminate against public works contractors by requiring them -to pay prevailing wages whereas contractors employed by private persons and entities are not required to pay prevailing wages. Furthermore, plaintiffs complain that the prevailing wage legislation is not applicable to all public works contracts in that the California legislation does not apply to contracts awarded by a charter city or other municipal corporation and, moreover, that the law does not apply to public works construction carried out by a public agency using its own public employees.
*457
Plaintiffs make no claim that the legislation here involved discriminates with respect to a “fundamental right” or is based upon a “suspect classification.” (See
In re Antazo,
In
Russell
v.
Carleson,
However, as was said in
McLaughlin
v.
Florida,
Little has been written in judicial opinions concerning the purpose of the California legislation. However, cases have expounded on the purpose of the Davis-Bacon Act (40 U.S.C. § 276a et seq.)
4
The Supreme Court stated in
U.S.
v.
Binghamton Construction Co.,
It has been said that the provision for payment of prevailing wages on state construction works serves a public policy in that the state will benefit from “the superior efficiency of well-paid labor working during reasonable hours” and that such benefit justifies the employment of men on “less favorable terms than could be secured by the stress of competition.” (65 Am.Jur.2d, Public Works and Contracts, § 199, p. 87.)
With respect to plaintiffs’ contention that the prevailing wage law discriminates against public works contractors because it does not apply to contractors working on private construction projects, it has been said
*459
that the myriad differences between public and private entities provides a sufficient rational basis for different legislative treatment. Thus in
Dias
v.
Eden Township Hospital Dist.,
It was specifically decided in
Bishop
v.
City of San Jose,
Plaintiffs contend that this legislative distinction between workers employed by private contractors on public works and public employees engaged in building public projects is unconstitutionally discriminatory. This claim has been considered by courts in other jurisdictions. Thus the reason for the different treatment accorded public and private employees working on public works projects was succinctly set forth by the court in
City of Monmouth
v.
Lorenz,
The differences between public employment and employment by a private contractor noted in
City of Monmouth
v.
Lorenz, supra,
Plaintiffs contend that there is no rational reason for application of prevailing wage laws to public works contracts and not to public contracts in general. Public works are defined in Labor Code section 1720 as follows: “As used in this chapter ‘public works’ means: [11] (a) Construction, alteration, demolition or repair work done under contract and paid for in whole or in part out of public funds, except work done directly by any public utility company pursuant to order of the Public Utilities Commission or other public authority. [U] (b) Work done for irrigation, utility, reclamation and improvement districts, and other districts of this type. ‘Public work’ shall not include the operation of the irrigation or drainage system of any irrigation or reclamation district, except as used in Section 1778 relating to retaining wages. [II] (c) Street, sewer or other improvement work done under the direction and supervision or by the authority of any officer or public body of the state, or of any political subdivision or district thereof, whether such political subdivision or district operates under a freeholder’s charter or not. [II] (d) The laying of carpet done under a building lease-maintenance contract and paid for out of public funds. [H] (e) The laying of carpet in a public building done under contract and paid for in whole or part out of public funds.”
*461 Public works are further defined for the purposes of the payment of prevailing wages to include certain contracts between private persons as set forth in Labor Code section 1720.2 as follows: “For the limited purposes of Article 2 (commencing with Section 1770) of this chapter, ‘public works’ also means any construction work done under private contract when all of the following conditions exist: [H] (a) The construction contract is between private persons, [i] (b) The property subject to the construction contract is privately owned, but, upon completion of the construction work, more than 50 percent of the assignable square feet of the property is leased to the state or a political subdivision for its use. [H] (c) The lease agreement between the lessor and the state or political subdivision, as lessee, was entered into prior to the construction contract.” And in Labor Code section 1771, with respect to the payment of prevailing wages it is provided in part as follows: “This section is applicable to contracts let for maintenance work.”
The statutory scheme, the cases decided under the California prevailing wage law and under the Davis-Bacon Act, as well as the legislative history available with respect to the Davis-Bacon Act, show clearly that prevailing wage legislation was designed to benefit the construction worker on public construction projects. The Legislature may constitutionally single out a particular segment of industry for regulation without necessarily running afoul of the equal protection clauses of the state and federal Constitutions. As was said in
Brown
v.
Merlo,
Appellants contend that the California prevailing wage law constitutes a denial of equal protection because it does not apply to public works contracts awarded by charter cities, citing
City of Pasadena
v.
Charleville,
Plaintiffs claim that the federal Davis-Bacon Act is also arbitrary and discriminatory in that it does not generally apply to employees of contractors on public contracts for the manufacture or furnishing of materials, supplies, articles and equipment. This argument is akin to the argument presented with respect to the distinction made by the California law between public works projects and other public contracts. As set forth hereinabove, the distinction has a rational basis in the light of the purpose of the law.
Plaintiffs contend that “[a] statute which subjects property to liability without the fault of the owner thereof is invalid.” The case cited by plaintiffs in support of this proposition,
State
v.
A/S Nye Kristianborg
(D.Md. 1949)
In the case presently before this court there is no question of retroactive application of a statute so as to impair property rights. Plaintiffs entered into a contractual agreement to the effect that they would comply with Labor Code section 1775 and that they would forfeit to the state $25 per day for each workman paid less than *463 the prevailing wage by either plaintiffs or by their subcontractors, as well as pay to each such workman the difference between the prevailing wage and the amount the workman had received. Thus when subcontractors Wright and Heck failed to pay prevailing wages to their workmen, plaintiffs became contractually liable to pay the penalty to the state as well as to pay the wronged workmen the difference in wages. Accordingly, it cannot be said that the statute subjects plaintiffs’ property to a taking without due process or equal protection of the law.
Finally plaintiffs contend that “[t]he submission of certified payrolls by a subcontractor showing payment of prevailing wages satisfies all obligations of the contractor under the prevailing wage statutes.” As noted hereinabove, Labor Code section 1775 requires the contractor to pay penalties assessed by the state as well as the difference owed to workmen paid less than the prevailing wage. These statutory obligations are imposed on the contractor whether the contractor or a subcontractor failed in his obligation to pay prevailing wages. Thus the statutory scheme requires more of the contractor than procurement of certified payrolls from a subcontractor showing payment of prevailing wages. It must be remembered that a prime contractor subcontracts work on a construction project primarily for his own convenience. The Legislature has expressed its intention that the prevailing wage provisions apply to all workmen on public projects and that the provisions of the act not be frustrated because of the subcontracting of work required to be done under the provisions of the prime contract. It is not unreasonable to require that the contractor assume contractual responsibility for his subcontractor’s compliance with the prevailing wage law.
The legislation in question does not violate either due process or the equal protection of the law. No unconstitutional burdens have been imposed on plaintiffs. No basis for a reversal of the judgment has been shown.
The judgment is affirmed.
Allport, 1. and Potter, 1, concurred.
Appellants’ petition for a hearing by the Supreme Court was denied April 15, 1976.
Notes
As was said in
Randone
v.
Appellate Department,
In
Kugler
v.
Yocum,
Plaintiffs question the validity of
Whitsett
and
Atkin,
contending that they have been overruled by implication by those more recent cases which hold that while employment by the state' is not a right, still such employment and the granting of privileges by the state cannot be conditioned on a deprivation of a party's constitutional rights. (See
Frost Trucking Co.
v.
R.R. Com.,
In
Purdy & Fitzpatrick
v.
State of California, supra,
It is clear that, contrary to plaintiffs’ contention, the court in Purdy & Fitzpatrick did not question the validity of the basic decision in Atkin v. Kansas which upheld the Kansas maximum hour and prevailing wage law.
It has been stated by the California State Attorney General (
The relevant portion of Labor Code section 1771 as amended is as follows: “This section is applicable only to work performed under contract, and is not applicable to work carried out by a public agency with its own forces."
The determination made in Bishop has been set forth hereinabove.
The language relied on by plaintilfs is as follows; “Even if it were possible, as a matter of statutory construction, to find that it was the intention of the Maryland Legislature to make the amending statute retroactive in effect, it still would not be possible to do so. because that w'ould run counter to both Maryland and federal constitutional limitations. It requires no elaboration to demonstrate that a statute which, as we have seen, would impair a property right, bv subjecting one’s property to the claims of another, without personal fault or legal liability of the owner, destroys vested rights of property, and is therefore clearly invalid. It is a taking of property without due process of law’ contrary to the 14th Amendment of the Federal Constitution and also contrary to established constitutional principles in Maryland."
