History
  • No items yet
midpage
393 S.W.3d 68
Mo. Ct. App.
2012
Read the full case

Background

  • Contractor and Owner entered into a February 28, 2007 cost-plus contract to renovate a historic Springfield building.
  • Project relied on historic tax credits; Exhibit 29 documented final project costs though not signed or attested.
  • Owner leased the building to Inspired Commerce, LLC (Tenant) under a 33-year master lease with occupancy expectations around December 2008.
  • Contractor was terminated January 29, 2009 for cause; dispute included alleged overcharges and defective work; judgment awarded net $228,138.72 to Owner after offset.
  • Trial evidence included Day’s defect inspections (basement slab, windows, tuck-pointing) and Martin’s testimony valuing diminution in value at $450,000.
  • Trial court found Contractor breached, awarded Owner costs for repair/diminution, and denied Contractor’s claims for attorney fees and interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Damages from leasehold and rent impact Owner sustained damages beyond merely rent; leasehold interest remained exploitable and damages accrued. Owner’s damages depended solely on rent loss under the master lease; Tenant's duties obviated Owner's liability. Point denied; Owner could recover damages beyond rent.
Waiver of notice to cure termination Waiver of the 10-day cure notice was intended by Buche’s email; proper authorities support waiver. No explicit waiver of cure rights; termination for cause remained valid regardless of form. Point denied; clear waiver established; termination for cause proper.
Labor cost mark-up (30%) recoverability Contractor’s labor costs, including burden, were within the cost of work; 30% markup justified by contract terms. 30% markup was not supported by the contract; wages defined narrowly; markup not recoverable. Point denied; 30% markup not allowed; damages limited to actual costs.
Diminution in value vs. cost of repair Diminution or repair cost both applicable; evidence supported diminution and repair costs for windows and basement floor. Evidence insufficient to prove diminution amounts; preferred measure is cost of repair where feasible. Point denied; trial court properly balanced diminution and repair costs with evidence; no prejudice.
Attorney fees and interest Contractor breached; Owner entitled to remedies including attorney fees under the agreement. Contractor was not prevailing party or breach did not warrant fees; interest may not apply. Point denied; contract breach by Contractor barred fee recovery; interest denied.

Key Cases Cited

  • McCullough v. Doss, 318 S.W.3d 676 (Mo. banc 2010) (standard of review in bench trials)
  • Grider v. Tingle, 325 S.W.3d 437 (Mo.App. S.D.2010) (definition of substantial evidence)
  • Houston v. Crider, 317 S.W.3d 178 (Mo.App. S.D.2010) (against-the-weight-of-the-evidence standard)
  • Wildflower Cmty. Ass’n, Inc. v. Rinderknecht, 25 S.W.3d 530 (Mo.App. W.D.2000) (deference to trial court findings of witness credibility)
  • Tower Prop. Co. v. Allen, 33 S.W.3d 684 (Mo.App. W.D.2000) (judgment affirmed under any reasonable theory supported by the evidence)
Read the full case

Case Details

Case Name: Matt Miller Co. v. Taylor-Martin Holdings, LLC
Court Name: Missouri Court of Appeals
Date Published: Oct 25, 2012
Citations: 393 S.W.3d 68; 2012 Mo. App. LEXIS 1359; 2012 WL 5258713; No. SD 31478
Docket Number: No. SD 31478
Court Abbreviation: Mo. Ct. App.
Log In
    Matt Miller Co. v. Taylor-Martin Holdings, LLC, 393 S.W.3d 68