History
  • No items yet
midpage
Lemoine Co. v. Durr Heavy Construction, LLC
206 So. 3d 244
La. Ct. App.
2016
Read the full case

Background

  • Lemoine was general contractor on a Covington, LA office/athletic club project; Ceco and Durr were subcontractors. The owner recorded the last certificate of substantial completion on June 26, 2009.
  • Owner Cypress Bend sued Lemoine (and initiated arbitration) in 2014 for alleged construction defects. Lemoine then sued Ceco and Durr on April 2, 2015 seeking indemnity/contribution under the subcontracts.
  • Lemoine moved to stay litigation and compel arbitration under subcontract arbitration clauses that incorporate the AAA Construction Industry Rules.
  • Ceco and Durr responded with peremptory exceptions of peremption under La. R.S. 9:2772, arguing Lemoine’s claims were time-barred (filed more than five years after registry of acceptance).
  • The district court denied Lemoine’s motion to compel arbitration, found peremption on the face of the pleadings, and dismissed Lemoine’s claims. Lemoine appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the court should stay proceedings and compel arbitration Arbitration clause (incorporating AAA rules) delegates arbitrability (including peremption) to arbitrator Subcontract does not clearly and unmistakably delegate issues raised by Lemoine’s suit; no arbitration was initiated by defendants Court refused to compel arbitration; arbitration provision did not clearly delegate peremption for claims filed by Lemoine against subcontractors
Whether peremption under La. R.S. 9:2772 applies Lemoine contends subsection C might save its claims (argued below) and that arbitrator should decide arbitrability Ceco/Durr: claims are perempted because suit filed >5 years after registry of acceptance (June 26, 2009) Court held claims were perempted as a matter of law; Lemoine’s suit (filed April 2, 2015) was beyond five-year peremptive period
Who decides arbitrability when a construction contract may be extinguished by peremption Lemoine: incorporation of AAA Rule 9 is clear and unmistakable delegation to arbitrator Ceco/Durr: if contract-based arbitration right is extinguished by peremption, there is no arbitration agreement to enforce; courts must decide peremption first Court held that when peremption extinguishes the cause of action/contract, the court must decide peremption first; no arbitration where claim is perempted
Burden of proof on peremption at preliminary stage Lemoine: peremption not evident; facts could bring subsection C into play Ceco/Durr: peremption evident on face of pleadings (recorded completion date) Court found peremption evident on face of pleadings; burden shifted and Lemoine failed to show exception to peremption

Key Cases Cited

  • Arkel Constructors, Inc. v. Duplantier & Meric, Architects, L.L.C., 965 So.2d 455 (La. App. 1st Cir.) (standards for reviewing motion to compel arbitration)
  • Collins v. Prudential Ins. Co. of Am., 752 So.2d 825 (La.) (threshold inquiry for arbitration: valid agreement and scope)
  • AT&T Techs., Inc. v. Comm. Workers of Am., 475 U.S. 643 (U.S. 1986) (arbitrator authority derives from parties’ agreement)
  • Howsam v. Dean Witter Reynolds Inc., 537 U.S. 79 (U.S. 2002) (arbitrability is for courts unless parties clearly and unmistakably provide otherwise)
  • Breaux v. Stewart Enterprises Inc., 883 So.2d 983 (La.) (arbitrability principles)
  • Jasper Contractors, Inc. v. E-Claim.com, LLC, 94 So.3d 123 (La. App. 1st Cir.) (incorporation of AAA rules can be clear and unmistakable delegation)
  • Cohen v. Audubon Constr. Corp., 404 So.2d 528 (La. App. 4th Cir.) (contract prescription/peremption can defeat enforceability of arbitration clause)
  • Parker v. St. Tammany Parish Hosp. Serv. Dist., 670 So.2d 531 (La. App. 1st Cir.) (court decides whether arbitration agreement exists when underlying contract is time-barred)
  • Naghi v. Brener, 17 So.3d 919 (La.) (nature of peremption and non-suspension rules)
  • Ebinger v. Venus Const. Corp., 65 So.3d 1279 (La.) (date registry of acceptance triggers peremptive period)
  • Carter v. Haygood, 892 So.2d 1261 (La.) (burden of proof on peremptory exception of peremption)
  • Rando v. Anco Insulations, Inc., 16 So.3d 1065 (La.) (when peremption is evident on face of pleading, burden shifts)
  • Stobart v. State through DOTD, 617 So.2d 880 (La.) (manifest error standard for factual findings)
  • Lasseigne v. Schouest & Sons, Builders, 563 So.2d 371 (La. App. 1st Cir.) (purpose of La. R.S. 9:2772 to limit long-term liability)
Read the full case

Case Details

Case Name: Lemoine Co. v. Durr Heavy Construction, LLC
Court Name: Louisiana Court of Appeal
Date Published: Oct 31, 2016
Citation: 206 So. 3d 244
Docket Number: NO. 2015 CA 1997
Court Abbreviation: La. Ct. App.