History
  • No items yet
midpage
L.H. Controls, Inc. v. Custom Conveyor, Inc.
2012 Ind. App. LEXIS 464
| Ind. Ct. App. | 2012
Read the full case

Background

  • LH Controls, Inc. (LH) and Custom Conveyor, Inc. (CCI) engaged on a Honda Greensburg project under a Honda Master Construction Agreement incorporated into the LH-CCI subcontract.
  • CCI hired LH to provide programming and control boxes for four conveyor lines for $685,754.30, later increased to $788,582.30 after two LH change orders.
  • LH’s performance fell behind schedule; LH failed to provide timely progress reports and milestone schedules, and its programming for the door line was late, causing downstream costs for CCI.
  • Honda began withholding progress payments due to delays, and after project completion Honda negotiated over cost overruns, with CCI ultimately accepting a settlement of $975,000 to resolve issues unrelated to LH’s performance.
  • LH filed a mechanic’s lien and Honda PLN against Honda for non-payment; CCI withheld $82,184.10 in chargebacks from LH’s final invoices; LH sued Honda and CCI, and CCI asserted indemnity and other counterclaims against LH.
  • The trial court awarded CCI $1,409,896.97 in damages, plus later attorney-fee adjustments, totaling $1,467,587.61; LH appealed challenging lost profits, indemnity, and chargebacks conclusions.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether LH’s breaches support lost profits for CCI LH argues no causal link; lost profits unsupported CCI contends breaches caused compensable lost profits Lost profits reversed; no evidence of causation or foreseeability
Whether LH must indemnify CCI for attorney fees and costs Indemnity clause does not clearly cover first-party claims Indemnity clause covers all costs Indemnity limited to third-party costs; attorney fees reversed; third-party costs affirmed
Whether chargebacks were recoverable and properly calculated Chargebacks valid to offset LH’s final payment Chargebacks overstated and improper offset; waiver of conditions precedent Waiver established; double recovery avoided; remand for corrections; partial affirmances

Key Cases Cited

  • Fresh Cut, Inc. v. Fazli, 650 N.E.2d 1126 (Ind. 1995) (indemnity terms construed strictly; first-party implications)
  • Eden United, Inc. v. Short, 653 N.E.2d 126 (Ind. Ct. App. 1995) (lost profits require concrete basis; no implied after-the-fact profits)
  • Sawmill Creek, LLC v. Marion County Auditor, 964 N.E.2d 213 (Ind. 2012) (two-tiered review for findings; defer to trial court on facts; de novo on law)
  • Berkeley & Co. Contractors v. Palm & Associates, 814 N.E.2d 649 (Ind. Ct. App. 2004) (consequential damages must be foreseeable; lost profits require certainty)
  • Clark’s Pork Farms v. Sand Livestock Systems, Inc., 563 N.E.2d 1292 (Ind. Ct. App. 1990) (consequential damages may be awarded if loss flows naturally and is contemplated)
Read the full case

Case Details

Case Name: L.H. Controls, Inc. v. Custom Conveyor, Inc.
Court Name: Indiana Court of Appeals
Date Published: Sep 19, 2012
Citation: 2012 Ind. App. LEXIS 464
Docket Number: 16A05-1111-PL-606
Court Abbreviation: Ind. Ct. App.