Kellogg Brown & Root Services, Inc. v. Murphy
2016 U.S. App. LEXIS 9044
| Fed. Cir. | 2016Background
- In 2001 the Army contracted with KBR under a cost-plus-award-fee LOGCAP contract; KBR subcontracted work to KCPC/Morris to build dining facilities and provide meal services in Iraq.
- KBR terminated the KCPC/Morris subcontract for default on July 31, 2003; KCPC/Morris disputed the termination and continued performance until transition on September 12, 2003.
- KCPC/Morris sued KBR in 2004; in January 2005 KBR and KCPC/Morris executed a written agreement splitting KCPC/Morris’ costs into a $17.4 million “Settlement Amount” (paid) and additional costs/profit (the group (b) costs) to be pursued cooperatively.
- KCPC/Morris submitted a certified claim to KBR on August 26, 2006; KBR forwarded that claim to the Army on November 3, 2006, but the Army declined to deal directly with subcontractors and required KBR to resolve subcontract issues first.
- KBR later certified and then withdrew a claim (2007–2010); after settling with KCPC/Morris in February 2012, KBR filed a certified CDA claim with the Army on May 2, 2012 for $10,464,493; the contracting officer’s inaction created a deemed denial and KBR appealed to the ASBCA.
- The ASBCA dismissed for lack of jurisdiction on statute-of-limitations grounds, holding the claim accrued either on September 12, 2003 (subcontract end) or January 24, 2005 (settlement agreement); this appeal followed.
Issues
| Issue | KBR's Argument | Army's Argument | Held |
|---|---|---|---|
| Whether KBR's CDA claim accrued before May 2, 2006 (six-year limit) | Claim did not accrue until KCPC/Morris presented a sum certain (Aug 26, 2006) and until KBR could reasonably present a sum certain to the Army | Accrual fixed when prime became liable to subcontractor (either Sept 12, 2003) or when parties agreed to cooperate (Jan 24, 2005); amount need not be exact to accrue | Reversed: claim did not accrue before May 2, 2006; dismissal on limitations grounds improper |
| Whether subcontract termination was a per se non-routine government action triggering immediate accrual | Termination of subcontract by prime was not an unforeseen government action; routine/resolution requirements prevented accrual | Termination fixed liability and thus triggered accrual as a non-routine event | Rejected Army/Board: non-routine doctrine misapplied; accrual depends on circumstances and a sum certain must be knowable |
| Whether Severin doctrine makes prime’s accrual coterminous with subcontractor’s accrual | Accrual requires ability to demand a sum certain from government; Severin governs liability relationships but not accrual timing under FAR §33.201 | When subcontractor’s claim accrued against the prime, the prime’s claim against the government accrued as well | Rejected Army: Severin addresses liability, not FAR accrual timing; accrual occurs when contractor can reasonably state a sum certain |
| Whether equitable tolling or prior withdrawn claims tolled the limitations period | Tolling unnecessary because accrual occurred after May 2, 2006; withdrawn 2008 claim did not toll | Argued limitations had run; Board found no equitable tolling | Court did not reach equitable tolling because it held claim did not accrue before the critical date |
Key Cases Cited
- Parsons Global Servs. v. McHugh, 677 F.3d 1166 (Fed. Cir.) (accrual assessed by FAR, contract language, and facts)
- James M. Ellett Constr. Co. v. United States, 93 F.3d 1537 (Fed. Cir.) (distinguishes routine vs non-routine requests for payment)
- Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir.) (defines routine/non‑routine request and claim accrual principles)
- Crown Coat Front Co. v. United States, 386 U.S. 503 (U.S.) (limitations may not run until required administrative procedures are complete)
- Bay Area Laundry & Dry Cleaning Pension Trust Fund v. Ferbar Corp., 522 U.S. 192 (U.S.) (limitations should not begin where suit would be premature due to required pre-suit procedures)
- Sikorsky Aircraft Corp. v. United States, 773 F.3d 1315 (Fed. Cir.) (CDA statute of limitations is nonjurisdictional)
