History
  • No items yet
midpage
107 Fed. Cl. 571
Fed. Cl.
2012
Read the full case

Background

  • K-Con contract with Coast Guard for St. Petersburg warehouse; base item awarded, options not funded; completion date July 26, 2004.
  • Liquidated damages rate set at $564 per day using Coast Guard personnel cost methodology; no formal written impact analysis documented.
  • Coast Guard used COMDTINST 7310.1F rates to compute administrative costs and fixed personnel costs for delay damages; no consistent policy guidance existed.
  • Plaintiff alleges delays caused by Coast Guard and contract changes; seeks remission of liquidated damages and, later, a monetary increase for additional work.
  • Coast Guard reduced contract price by liquidated damages and actions culminated in battlefield of approvals, extensions, and multiple contract modifications; jurisdiction under the CDA governs claims and remission requests.
  • Court previously ruled on Elizabeth City and Port Huron suits; this case addresses CDA notice, penalty issue, and remission for St. Petersburg delays.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Is the liquidated damages rate a penalty? K-Con argues $564/day bears no reasonable relation to probable damages. Coast Guard contends rate is a reasonable forecast; enforceable if reasonable. Enforceable; rate not a penalty.
Whether remission of 67 days is appropriate K-Con seeks remission for kickoff delay, foundation redesign, and hurricanes. Remission foreclosed by releases and lack of CDA-notice for some delays. Remission denied for some delays due to lack of proper CDA notice; remaining gaps viable.
Did July 28, 2005 claim letter adequately notify CDA basis? K-Con argues letter provided adequate notice of some grounds for remission. Broussard adequately understood basis for some grounds; letter not perfect. Letter provided adequate notice for at least some CDA grounds; valid claim for remission on those grounds.
Was the December 15, 2006 claim letter a valid CDA claim for an eighty-eight-day extension? Seeks additional time based on Coast Guard delays. Second claim arises from same facts; magistrate denied as divested by litigation. Not viable as to the eighty-eight-day extension; new monetary claim relates to different relief and is valid.
Can the Hurricanes-related remission be pursued given contract releases? Seeks additional remission for Charley, Frances, Ivan, Jeanne delays. Releases in contract modifications bar further relief for those hurricanes. Remission barred for Charley, Frances, Ivan, and Jeanne due to releases.

Key Cases Cited

  • Priebe & Sons, Inc. v. United States, 332 U.S. 407 (U.S. 1948) (liquidated damages judged at contract formation; reasonable forecast required)
  • Bethlehem Steel Co. v. United States, 205 U.S. 105 (U.S. 1907) (liquidated damages enforceable if not a penalty; consider at time of contract)
  • Jennie-O Foods, Inc. v. United States, 580 F.2d 400 (Ct. Cl. 1978) (administrative expenses may be considered in calculating liquidated damages)
  • DJ Mfg. Corp. v. United States, 86 F.3d 1130 (Fed. Cir. 1996) (reasonableness of rate not questioned; COF not required to show exact method)
  • Placeway Construction Corp. v. United States, 920 F.2d 903 (Fed. Cir. 1990) (contracting officer’s final decision; treatment of claims and set-off)
  • Sun Eagle Corp. v. United States, 23 Cl.Ct. 465 (Cl. Ct. 1991) (government claim; contractor may assert a CDA claim for remission)
  • Case, Inc. v. United States, 88 F.3d 1004 (Fed. Cir. 1996) (separate claims arising from same facts may be treated differently under CDA)
  • Sharman Co. v. United States, 2 F.3d 1564 (Fed. Cir. 1993) (doj control over litigation; when new, different claims may proceed)
Read the full case

Case Details

Case Name: K-Con Building Systems, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Nov 30, 2012
Citations: 107 Fed. Cl. 571; 2012 U.S. Claims LEXIS 1492; 2012 WL 5990374; No. 05-981C
Docket Number: No. 05-981C
Court Abbreviation: Fed. Cl.
Log In
    K-Con Building Systems, Inc. v. United States, 107 Fed. Cl. 571