History
  • No items yet
midpage
903 F.3d 881
9th Cir.
2018
Read the full case

Background

  • Metrolink contracted Parsons to design and install a federally‑mandated Positive Train Control (PTC) system; project was publicly funded and exceeded $216 million.
  • Prime contract split work into (a) field installation on the wayside (trenching, towers, welding, etc.) and (b) on‑board installation of electrical/PTC equipment on locomotives and rail cars.
  • Parsons subcontracted the on‑board work to Wabtec (approved by Metrolink); Wabtec performed only on‑board work and related back‑office support.
  • Plaintiff John Busker, a former Wabtec employee who did on‑board electrical work, filed a prevailing wage claim; the DLSE initially assessed wages/penalties but later released the assessment and the parties litigated in court.
  • The district court granted summary judgment for Wabtec; the Ninth Circuit panel certified to the California Supreme Court the question whether on‑board work is a “public work” under Cal. Lab. Code § 1720(a)(1), either as construction/installation or as integral to covered field work.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether on‑board installation qualifies as “construction” or “installation” under Cal. Lab. Code § 1720(a)(1) Busker: broad dictionary/ statutory reading—on‑board electrical assembly is construction/installation and should be liberally construed to protect workers Wabtec: rolling stock (trains) are not fixed public works; administrative guidance treats work on rolling stock as outside prevailing wage law Panel found text ambiguous and state law unclear; certified the question to the California Supreme Court for definitive interpretation
Whether on‑board work is covered because it is integral/connected to the field (wayside) work Busker: even if not independently a public work, on‑board work is sufficiently integrated with field work to fall within prevailing wage coverage Wabtec: contracts and project structure show on‑board work is separate from wayside construction and analogous to off‑site work courts have held noncovered Panel concluded outcome depends on choice of legal standard (integration into construction flow vs. forming a complete integrated object) and therefore certified the question to the California Supreme Court
Whether administrative agency interpretation (DIR/DLSE) excluding rolling stock controls Busker: agency position should not override liberal statutory construction favoring workers Wabtec: longstanding administrative guidance supports excluding on‑board/rolling stock work Panel noted agency guidance favors Wabtec but that adopting Busker’s view would be a state‑law extension better resolved by state high court
Whether federal court should decide novel question of California law Busker: state law governs prevailing wage scope; state court best placed to decide Wabtec: federal courts can resolve state law issues when necessary Panel: certified question to California Supreme Court under Cal. R. Ct. 8.548 for authoritative state‑law resolution; stayed further proceedings

Key Cases Cited

  • Kilby v. CVS Pharmacy, Inc., 739 F.3d 1192 (9th Cir. 2013) (federal court may certify state‑law questions for comity)
  • Klein v. United States, 537 F.3d 1027 (9th Cir. 2008) (federal court must follow state supreme court decision if accepted)
  • People v. Scott, 58 Cal.4th 1415 (2014) (statutory interpretation begins with text)
  • City of Long Beach v. Dep’t of Indus. Relations, 34 Cal.4th 942 (2004) (prevailing wage statute must be liberally construed to benefit workers)
  • Lusardi Constr. Co. v. Aubry, 1 Cal.4th 976 (1992) (overall purpose of prevailing wage law is to protect employees on public works)
  • Sheet Metal Workers’ Int’l Ass’n, Local 104 v. Duncan, 229 Cal. App.4th 192 (2014) (tests for when off‑site work is covered by prevailing wage law)
  • Williams v. SnSands Corp., 156 Cal. App.4th 742 (2007) (off‑hauling/materials removal treated as separate from onsite construction)
  • O. G. Sansone Co. v. Dep’t of Transp., 55 Cal. App.3d 434 (1976) (prevailing wage can cover off‑hauling when integral to project)
  • Oxbow Carbon & Minerals, LLC v. Dep’t of Indus. Relations, 194 Cal. App.4th 538 (2011) (focus on whether combined work yields a complete integrated object)
  • Cinema W., LLC v. Baker, 13 Cal. App.5th 194 (2017) (analysis of necessity/integration between publicly funded and privately funded work)
Read the full case

Case Details

Case Name: John Busker v. Wabtec Corp.
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Sep 6, 2018
Citations: 903 F.3d 881; 17-55165
Docket Number: 17-55165
Court Abbreviation: 9th Cir.
Log In
    John Busker v. Wabtec Corp., 903 F.3d 881