History
  • No items yet
midpage
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
198 Cal. Rptr. 3d 47
Cal. Ct. App.
2015
Read the full case

Background

  • JMR Construction was prime contractor for a federal public-works dental clinic; EAR was subcontractor on separate electrical and plumbing subcontracts; SureTec issued performance bonds for EAR under each subcontract.
  • Project completion was delayed (beneficial occupancy May 14, 2008) and JMR withheld approximately $121,893 in retention from EAR.
  • JMR sued EAR and SureTec for breach of the two subcontracts and foreclosure on the performance bonds; EAR cross‑complained seeking withheld retention.
  • After trial the court entered judgment for JMR of $315,631 (net after offsets), rejected EAR’s cross‑complaint, and reserved attorney fees; later the court awarded expert witness fees under CCP § 998 (order later challenged).
  • On appeal the court (published part) affirmed use of the Eichleay formula for home‑office overhead, affirmed use of a modified total‑cost method for framing/drywall disruption damages, and held SureTec liable on the bonds without a prior formal default notice; (unpublished) reversed the award of expert fees under § 998 and remanded for further post‑judgment proceedings.

Issues

Issue Plaintiff's Argument (JMR) Defendant's Argument (EAR / SureTec) Held
Sufficiency of evidence that EAR caused delays JMR relied on project managers, superintendent, scheduling expert, and documents showing EAR caused concurrent critical‑path delay EAR argued its testimony showed JMR caused delays and that JMR’s proof was insufficient Substantial evidence supported trial court: JMR’s witnesses and expert testimony credible; EAR’s contrary testimony rejected by trial court
Use of Eichleay formula for home‑office overhead JMR: Eichleay is appropriate to allocate unabsorbed overhead where owner granted time but not compensable time due to concurrent subcontractor delay EAR: California has no published adoption; Eichleay typically applies against government, not subcontractor; elements not proven (standby/unable to take other work) Court held Eichleay is a legally permissible method in California contracts; elements (including inability to take other work) had substantial evidence
Use of modified total‑cost method for framing/drywall disruption JMR: Modified total cost appropriate for the discrete framing/drywall phase; bid reasonable; actual costs reasonable; JMR not responsible for added costs EAR: Total cost disfavored; JMR failed Amelco elements; coding miscoding errors undermined damages Court held modified total cost permissible here; trial court reasonably found Amelco elements satisfied and rejected EAR’s alternative explanations
Liability of SureTec under performance bonds without formal notice of default JMR: No written default declaration to surety not required; bonds and law do not make notice a condition precedent SureTec: Obligee must declare principal in default and notify surety; default notice is implied condition precedent Court held bonds and subcontracts lack clear language making notice to surety a condition precedent; civil code and suretyship principles mean surety liable upon principal’s default without prior default notice

Key Cases Cited

  • Crawford v. Southern Pacific Co., 3 Cal.2d 427 (Cal. 1935) (standard for substantial evidence review)
  • Altmayer v. Johnson, 79 F.3d 1129 (Fed. Cir. 1996) (discussion of Eichleay and home‑office overhead)
  • E.R. Mitchell Const. Co. v. Danzig, 175 F.3d 1369 (Fed. Cir. 1999) (Eichleay as exclusive method in federal circuit precedent)
  • Wickham Contracting Co. v. Fischer, 12 F.3d 1574 (Fed. Cir. 1994) (steps of Eichleay calculation)
  • Amelco Electric v. City of Thousand Oaks, 27 Cal.4th 228 (Cal. 2002) (four‑part test for total‑cost method)
  • Cates Construction, Inc. v. Talbot Partners, 21 Cal.4th 28 (Cal. 1999) (performance bond interpretation and coextensive liability of surety with principal)
  • Pacific Allied v. Century Steel Products, 162 Cal.App.2d 70 (Cal. Ct. App. 1958) (contract interpretation re: implied conditions precedent and forfeiture)
Read the full case

Case Details

Case Name: JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
Court Name: California Court of Appeal
Date Published: Dec 30, 2015
Citation: 198 Cal. Rptr. 3d 47
Docket Number: H039055
Court Abbreviation: Cal. Ct. App.