In re Petition of Stowe Cady Hill Solar, LLC
182 A.3d 53
Vt.2018Background
- Cady Hill filed a CPG application for a 496 kW group net‑metered solar project on December 30, 2016—two days before the new Rule 5.100 took effect on January 1, 2017.
- Under the pre‑2017 Rule 5.100 an application is “complete” if it substantially complies with filing requirements; applicants must give adjoining landowners advance notice and contemporaneous notice of filing.
- Cady Hill’s developer provided full 45‑day advance notice to all required recipients and submitted a correct adjoining‑landowner list with the application; contemporaneous notice was sent to owners of eight of nine adjoining parcels, but two landowners (owning one parcel together) were inadvertently not given contemporaneous notice at the time of filing.
- Cady Hill sent the omitted notice and notified the Commission on January 5, 2017; the Commission held the application incomplete until that cure date and applied the new Rule 5.100, then dismissed the application.
- The Court considered whether the application was complete as of filing (so governed by the prior rule) and whether the Commission’s completeness determination merited deference.
Issues
| Issue | Cady Hill's Argument | Department/Commission's Argument | Held |
|---|---|---|---|
| Whether Cady Hill’s application was “complete” on Dec 30, 2016 | Application substantially complied with pre‑2017 rule—advance notice given, accurate landowner list, only a single inadvertent clerical omission to contemporaneous notice | An omission in contemporaneous notice rendered the filing substantially insufficient until cured on Jan 5, 2017, so new rule applies | Court held application was complete as of Dec 30, 2016 and thus governed by pre‑2017 Rule 5.100 |
| Standard of review / deference to Commission’s interpretation of its own rule | Commission’s completeness application must be consistent with its prior practice; no special expertise justifies deference here | Commission’s interpretation is entitled to deference as an agency applying its rules and implementing legislative policy shift | Court declined to defer to Commission because its application contradicted its prior precedent and statutory directive; reviewed and reversed Commission decision |
Key Cases Cited
- In re UPC Vt. Wind, LLC, 185 Vt. 296, 969 A.2d 144 (Vt. 2009) (describing deference to Commission merits decisions)
- Auer v. Robbins, 519 U.S. 452 (1997) (agency interpretations of their own regulations ordinarily afforded deference)
- Westar Energy, Inc. v. Fed. Energy Regulatory Comm., 473 F.3d 1239 (D.C. Cir. 2007) (agency must treat like cases alike)
- Norfolk S. R.R. Co. v. Shanklin, 529 U.S. 344 (2000) (agency interpretations that contradict prior constructions are not owed deference)
- In re Nehemiah Assocs., Inc., 168 Vt. 288, 719 A.2d 34 (Vt. 1998) (deference to agency interpretation of its own regulation unless inconsistent with statute)
