History
  • No items yet
midpage
251 A.3d 899
Vt.
2021
Read the full case

Background

  • Acorn Energy filed (Aug 2017) for a 150 kW ground-mounted solar net‑metering CPG on a leased ~3-acre area of a 41‑acre Shoreham farm; adjoining Holmeses opposed.
  • Project required grading, removal of four mature maples, temporary gravel access, a staging area, two small Class III wetlands on site, and disturbance of primary agricultural soils.
  • Acorn later proposed amendments (soil berms, array condensation, moving two maple trees, and overburden handling); Holmeses argued these were major amendments and that the application was incomplete (no drainage plan; unclear limits of disturbance).
  • PUC found the application administratively complete, treated the amendments as minor (including treating relocation of trees as aesthetic mitigation), found the site a preferred site, ruled no undue adverse impacts under 30 V.S.A. § 248(b), and issued a CPG.
  • Holmeses challenged completeness, amendment classification, preferred‑site status (and related Open Meeting Law issues), aesthetics/Quechee mitigation and alternative‑site burden, wetlands/water/soil impacts, noise, transportation, and setbacks. The Supreme Court affirmed.

Issues

Issue Holmeses' Argument Acorn / DPS Argument Held
1) Was the application complete absent a drainage plan? PUC unlawfully waived Rule 5.107(C)(5)(e); drainage plan required. Rule requires drainage plans only for projects that propose draining surface/subsurface water; Acorn addressed drainage protections. Affirmed PUC: "any" in rule means drainage plan required only if drainage is proposed; Acorn's filings sufficiently addressed drainage.
2) Were limits of disturbance timely disclosed? Limits not properly disclosed until revised site plan >1 year later; statutory rule requires early disclosure. Revised site plan submitted as part of a minor amendment process; Rule 5.108 permits updating pending applications. Affirmed PUC: initial site plan and subsequent revised plan satisfied § 248 and Rule 5.107 disclosure requirements.
3) Were proposed changes (berms, array reconfig, tree relocation, overburden handling) major amendments? Changes (esp. moving trees and increased disturbed area) were major and required refiling. Only moving trees could fit >50 ft threshold; PUC has discretion to treat additional aesthetic mitigation as minor. Affirmed PUC: berms and array change <50 ft; tree relocation—even though >50 ft—was allowed as a minor amendment because it provided additional aesthetic mitigation; PUC interpretation reasonable.
4) Preferred‑site designation and standing to challenge it / Open Meeting Law challenge to town letters Town letters invalid (not a single joint letter; Open Meeting Law violations); Holmeses attack preferred‑site finding. Holmeses lack standing on preferred‑site issue; preferred‑site affects pricing not property interests. Holmeses had injury in fact but no redressability re preferred‑site (pricing only); PUC could rely on town letters because selectboard/SPC ratified support at open meetings; Open Meeting Law enforcement belongs to superior court.
5) Aesthetics (Quechee) and alternative‑site burden Acorn failed to mitigate and should have considered alternative sites; burden should be on applicant. Opponents must show an available alternative; applicant need not evaluate locations it does not own/control. Affirmed PUC: alternative siting is a mitigation factor; consistent PUC practice places initial burden on opponents to show an available alternative; Holmeses failed to prove an available alternative on host parcel.
6) Wetlands, water supply, soils, noise, greenhouse gases, transportation Grading and lowering ridgeline would dewater Holmeses' spring/wetlands; jackhammering/blasting and excavation create undue impacts; greenhouse gas and traffic impacts unknown. Acorn presented site tests and permit consultations; no blasting allowed; construction emissions and traffic comparable to similar projects; PUC limited construction hours. Affirmed PUC: credited Acorn's experts over Holmeses'; PUC reasonably found no undue adverse effects and imposed conditions (no blasting, construction-hour limits); noise and GHG findings not clearly erroneous.
7) Setbacks Construction staging and disturbance violate statutory setbacks (Holmeses assert). Setback rules apply to solar panels/support structures, not temporary staging; PUC found project met setback distances. Affirmed PUC: relevant statutory setback distances met and staging area is not within "setback" definition for panels/supports.

Key Cases Cited

  • In re Halnon, 811 A.2d 161 (Vt. 2002) (mem.) (formulation of the Quechee two‑step aesthetics test)
  • Rutland Renewable Energy, LLC, 147 A.3d 621 (Vt. 2016) (applicant not required to show alternatives on land it does not own; initial burden on opponents)
  • In re Apple Hill Solar LLC, 219 A.3d 1295 (Vt. 2019) (permissive intervention and injury‑in‑fact analysis)
  • Valley Realty & Dev., Inc. v. Town of Hartford, 685 A.2d 292 (Vt. 1996) (local body may ratify actions taken in violation of Open Meeting Law)
  • Conservation Law Found. v. Burke, 188 A.3d 667 (Vt. 2018) (deference to agency interpretations of its own rules)
  • In re LK Holdings, LLC, 201 A.3d 373 (Vt. 2018) (procedural rules and standards for net‑metering CPG applications)
Read the full case

Case Details

Case Name: In re Petition of Acorn Energy Solar 2, LLC (Therese Holmes and Timothy Holmes, Appellants)
Court Name: Supreme Court of Vermont
Date Published: Jan 15, 2021
Citations: 251 A.3d 899; 2021 VT 3; 2019-398
Docket Number: 2019-398
Court Abbreviation: Vt.
Log In