Petitioner Tom Hal-non appeals the Vermont Public Service Board’s denial of his application requesting a certificate of public good (CPG) for a wind turbine net metering system pursuant to 30 V.S.A. § 219a. Halnon claims the Board abused its discretion by relying exclusively on observations made during its site visit, instead of evidence contained in the record, and that the Board’s decision was contrary to the legislative intent and purpose underlying 30 V.S.A. § 219a. We find no abuse of discretion and therefore affirm the Board’s order.
Halnon and his wife own sixty-two acres of land on North Branch Road in East Middlebury upon which Halnon seeks to erect and use a wind turbine. As a facility for electricity generation that employs a renewable energy source, a wind turbine constitutes a “net metering system,” 30 V.S.A § 219a(3)(E), requiring a CPG issued by the Board. See 30 V.S.A § 248(a)(2). In accordance with CPG application requirements, Halnon sent notice to neighboring landowners, and other interested parties, informing them of his application. Various objections were made to Halnon’s CPG application, the bulk of which focused on the project’s perceived negative aesthetic impact.
Mr. and Mrs. Rimonneau are neighboring landowners and part-time residents of a parcel of land across North Branch Road from the Halnon property who are among those opposed to Hal-non’s application for aesthetic reasons. Their residence is located at a slightly higher elevation from the proposed project site and looks down into the portion of the four acre meadow where Halnon proposes to site the wind turbine. The proposed turbine has three 23-foot diameter blades installed on a 100-foot tall tubular tower approximately one foot in diameter; it will be directly in view of the Green Mountains from the Rimonneaus’ residence. Approximately 450 feet separates the Rimonneau residence and the proposed turbine site. The area is predominantly wooded, comprised of mature poplar trees 30-75 feet in height. There are a small number of one- and two- story homes and hunting camps hidden in the woods but no other man-made structures in the area.
Hearings were held on Halnon’s CPG application during which the Rimonneaus, among other parties, were *515 granted intervention pursuant to Board Rule 2.209. Halnon did not raise an objection to the intervention of any of these parties. The bulk of the hearings focused on the issue of aesthetics, and proper application of the “Qmchee test” utilized by the Board when reviewing issues of aesthetics under 30 V.S.A § 248. The hearing officer held two site visits and several technical healings and evaluated the proposed project under certain criteria detailed in 30 V.S.A. § 248. Applying the Quechee test the healing officer’s proposal for decision (PFD) determined that Halnon’s CP6 request should be denied “because the net metering system as proposed, would have an undue adverse effect on the aesthetics and scenic and natural beauty of the area in which it is proposed” in violation of 30 V.S.A. § 248(b)(5). The healing officer found that there were alternative suitable sites for the proposed project and that Halnon had not availed himself of obvious and potentially effective mitigation steps which would lessen the aesthetic impacts of the project. Further, the hearing officer found the project would be offensive and shocking to the Rimonneaus and the average person in a similar situation. The PFD also invited the Board to reconsider this recommendation if Halnon could provide evidence that he has taken significant steps to minimize the negative effects that the project has on the Rimonneaus’ direct view.
Fundamentally at issue in this case was whether Halnon’s proposed project survived scrutiny under the Quechee test. The parties in this matter offer differing interpretations regarding proper application of the Qmchee test, alternately referring to both a two-part, and a three-part Qmchee analysis. For purposes of clarification we restate the proper Qmchee test for determining whether a project will have an undue adverse effect on the aesthetics or scenic and natural beauty of an area.
The two-part
Qmchee
test was first outlined by the Environmental Board in a previous case and has since been followed by this Court. See
In re McShinsky,
The Board received comments on the hearing officer’s PFD from all parties and intervenors, including the Rimonneaus, Halnon and the Department of Public Service. A duly noticed site visit, followed by oral argument, was held before the Board. Applying the second prong of the Qmchee test analysis, the Board concluded Halnon has failed to present “any compelling reason why [he] could not use an alternative site,” “has failed to take generally available mitigating steps which a reasonable person would take to improve the harmony of the proposed turbine with its surroundings,” and further, that he had the “burden of proof in this case and has failed to *516 demonstrate this mitigation would be unreasonable.” Based on this conclusion and the conclusion that the turbine would offend the sensibilities of the average person faced with a situation similar to the Rimonneaus’, the Board accepted the hearing officer’s conclusion that the project failed the two-part Queehee test and would, therefore, have an undue adverse effect upon the aesthetic and scenic and natural beauty of the area.
Appellant argues on appeal that in reaching its decision the Board erred by improperly relying on information obtained through its site visit. Specifically, appellant cites portions of the Board’s decision which reference the site visit, unsupported by any citation to the record:
The Applicant has not fully addressed the feasibility of other possible alternative locations which we observed at the site visit.
From our site visit, it is apparent that there are some locations that could achieve approximately the same turbine height above surrounding terrain and vegetation with the same tower height as the proposed site.
Based upon our site visit to the area, we concur with the Hearing Officer’s conclusion that the project in its presently proposed location will offend the sensibilities of the average person faced with a similar situation.
Appellant argues that these references demonstrate improper reliance on site visits as the exclusive basis for the Board’s findings, in contravention of our case law mandating otherwise. See
In re Quechee Lakes Corp.,
Whether administrative fact-finders may base their findings on site visit observations was first addressed by this Court in
Queehee Lakes.
In that case, we recognized that administrative tribunals can base their decisions on a broader range of evidence than courts and so extended our previous holding that “judicial findings can be grounded on knowledge acquired from site visits, as long as such examinations are not the exclusive basis for the findings,” to administrative tribunals.
Id.
at 551,
*517
We disagree with appellant that the Board relied exclusively on its own site visit as the basis for its conclusions. Rather, it is reasonable to conclude that the Board used its site visit observations merely to verify and affirm the hearing officer’s conclusions. There is no evidence that the Board relied on its own site visit observations over and above, or to the exclusion of, other evidence before it. The Board’s site visit observations constitute only a part of its total findings regarding the proposed project. There were more than 60 other findings made in support of the Board’s final conclusion. Besides the site visit, the Board also heal’d testimony regarding the nature and scale of the turbine and the surrounding area and the project. This Court applies a deferential standard of review where the sufficiency of the evidence is challenged on review.
Quechee Lakes,
Halnon further argues that the Board’s denial of his application is contrary to the intent of 30 V.S.A. § 219a. Specifically, he cites legislative findings to demonstrate that with net metering, the Legislature intended to encourage investment in renewable energy resources, enhance diversification of Vermont’s energy resources, and stimulate economic growth. 1997, No. 136 (Adj. Sess.), § 1. Appellant also finds further support for the above legislative intent in the net metering statute’s mandate to the Board to “simplify the application and review process as appropriate.” 30 V.S.A. § 219a(c)(3). Halnon claims that putting the burden of proof upon him to show that mitigation would be unreasonable, and denying his application for failure to meet that burden, constitutes an abuse of discretion in the context of a net metering application, and contravenes the intent of § 219a.
Again we find appellant’s argument unpersuasive. The Board denied Hal-non’s application after carefully balancing all appropriate policy considerations and then succinctly detailing its reasons for denying the application. The Board’s decision-making process was neither careless, nor formed with any obvious disregard for the legislative intent and purpose of net metering. In denying Halnon’s CPG application, the Board is not contradicting the Legislature’s intent to facilitate the use of wind turbines as an alternative energy source. Abuse of discretion occurs when that discretion is exercised on grounds or for reasons clearly untenable, or to an extent clearly unreasonable.
In re Lunde Construction Co.,
Appellant also claims that the Board’s abuse of discretion is further evidenced when its order in this ease is contrasted with its order in In re Blittersdorf, CPG NM-11 (May 26, 2000). In that case the Board approved a CPG for a wind turbine in a neighborhood containing single family residences and inactive farms where the net metering system was ‘Very visible from surrounding property and roads, with clear views of the turbine ranging from a few hundred feet in some directions up to one mile or more in other directions.” Id. at 4-5. Appellant claims the Board’s decision in the instant case is inconsistent with its decision in Blittersdorf and thereby thwarts the purpose of vesting statewide authority with the Board in order to effectuate uniform and fair statewide administration of public utility and electricity matters. Because of this, appellant claims the Board’s decision was an abuse of discretion. We disagree. As the Board observed, the proposed wind turbine in Blittersdorf was not out of character with its less rural surroundings which included: residences, barns, silos, farm machinery, tall telephone poles and other large working structures. In addition, the neighbor opposing the Blittersdorf turbine was situated approximately 1300 feet from the turbine and possessed a panoramic view of the Adirondacks which would only be marginally affected by the wind turbine. By contrast, in the instant case, the area is predominantly rural and wooded, devoid of other large structures in the vicinity of the project and the Rimonneaus’ home is situated only 450 feet from the proposed site. Their already limited view will be more severely affected by the presence of a turbine located directly in front of them. Given that the proposal in Blittersdorf and in the instant case were for wind turbines sited in significantly dissimilar environments, it was not abuse of discretion for the Board to find Halnon’s proposed turbine offensive or shocking to the average person.
There is a strong presumption that orders issued by the Public Service Board are valid.
In re E. Georgia Cogeneration Ltd. P’ship,
Affirmed.
