Horob v. Zavanna, LLC
2016 ND 168
| N.D. | 2016Background
- John and Bernice Shae leased 1,057.72 acres (the Shae lease) in Williams County in 1969; lease primary term 10 years and extends so long as oil or gas is produced; lease includes a 60‑day cessation-of-production "unless" clause requiring additional drilling or reworking within 60 days after production stops.
- The Rolfstad well (on a spacing unit including 21.61 net acres of the Shae lease) began producing in 1979; the well experienced production lapses including April–Sept 2004, Nov 2006–Jan 2007, and Dec 2010–Feb 2011.
- In 1987 Wiser Oil executed a federal communitization agreement that committed 40 gross acres of the Shae lease to a 160‑acre communitized area including the Rolfstad well; the agreement deems production under the agreement to be production as to each committed lease and contains a 60‑day cessation clause tied to BLM notice.
- Continental (operator since 2001) received a BLM notice Aug 30, 2004 directing restoration to production within 60 days and reported production resumed Sept 10, 2004; no BLM notices in the record for the later cessations.
- Horob plaintiffs (successors to the Shaes) sued, arguing the Shae lease terminated under its cessation clause; defendants moved for summary judgment asserting production was timely restored and, alternatively, the communitization agreement (and plaintiffs’ acceptance of royalties) preserved the lease.
- The district court granted summary judgment for defendants; the Supreme Court affirms, holding the lease was preserved by the communitization agreement even though the Shae lease’s cessation clause was triggered in 2004.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Shae lease terminated under its 60‑day cessation‑of‑production clause after the 2004 lapse | Shae lease terminated because production ceased for >60 days and no drilling/reworking commenced within 60 days | Cessation was temporary and operator had reasonable time/maintenance to restore production; clause not triggered | Court: Cessation clause was triggered (temporary‑cessation doctrine inapplicable to a clear "unless" clause) |
| Whether the federal communitization agreement preserved the Shae lease despite the 2004 lapse | Plaintiffs: not bound by communitization because they were not parties; if bound, only the committed 40 acres are preserved | Defendants: Shae lease’s pooling clause authorized Wiser to enter the communitization agreement; production under the agreement is production as to the lease | Held: Plaintiffs bound via their lease pooling clause; because BLM notice and operator compliance restored production under the communitization agreement, the entire Shae lease remained in effect |
| When the 60‑day cure period runs under the communitization agreement | Plaintiffs: 60 days should run from actual cessation, not BLM notice | Defendants: Agreement (and regulation) make the 60‑day period run upon BLM notice directing resumption | Held: Under the communitization agreement and 43 C.F.R., the 60‑day period runs upon BLM notice; Continental complied with BLM notice in 2004 |
| Whether only the 40 committed acres remain and the rest of the lease severed | Plaintiffs: statute on segregation/unitization requires segregation of committed vs. noncommitted acres | Defendants: Communitization (not unitization) and lease pooling clause preserve the entire lease; no Pugh clause severing noncommitted acreage | Held: Communitization and pooling clause keep the whole lease in effect; segregation principles for unit plans do not compel severance here |
Key Cases Cited
- Poppe v. Stockert, 870 N.W.2d 187 (N.D. 2015) (summary judgment standard and review)
- Tank v. Citation Oil & Gas Corp., 848 N.W.2d 691 (N.D. 2014) (contract interpretation governs by parties’ intent)
- Serhienko v. Kiker, 392 N.W.2d 808 (N.D. 1986) (an "unless" cessation clause is a special limitation that causes automatic termination if its conditions are not met)
- Greenfield v. Thill, 521 N.W.2d 87 (N.D. 1994) (doctrine of temporary cessation and equitable allowance of reasonable time where no specific cessation clause)
- Egeland v. Continental Res., Inc., 616 N.W.2d 861 (N.D. 2000) (governmental pooling/unitization ordinarily does not divide a lease; production anywhere in pooled unit can hold entire lease)
- Bedore v. Ranch Oil Co., 805 N.W.2d 68 (Neb. 2011) (where parties contract a specific time for cessation cure, that agreed period controls over common‑law reasonable‑time doctrine)
