The plaintiffs appeal from a judgment and amended judgment of the district court which dismissed their action seeking cancellation of two oil and gas leases and damages for slander of title. Defendants Russell L. Kiker, Jr., and Martin Oil Company (Martin) have cross-appealed from a portion of the amended judgment dismissing their counterclaims against the plaintiffs. We affirm in part, reverse in part, and remand for further рroceedings.
The plaintiffs collectively own 240 of the mineral acres in Billings County described as follows:
“Township 143 North, Range 98 West of the 5th P.M.
“Section 3: SVííNEVí, SEVí
“Section 10: SV2NWy4, NASWV-i”
The oil and gas interests owned by the plaintiffs were leased to Kiker through two leases executed on October 6 and 7, 1977, for primary terms of five years and ten years, respectively. The controversy in this case centers upon a cessation of production clause contained in eaсh lease. That clause states in pertinent part:
“If prior to discovery of oil or gas on said land, or on acreage pooled therewith, lessee should drill a dry hole or holes thereon, or if after discovery of oil or gas production thereafter should cease for any cause, this lease shall not terminate if lessee commences additional drilling or reworking operations within sixty (60) dаys thereafter, or (if it be within the primary term) commences or resumes the payment or tender of rental on or before the rental-paying date next ensuing after the expiration of three (3) months from the date of completion of a dry hole or cessation of production.”
During August 1978 a producing well, known as the Symionow Well, was completed by Gulf Oil Corporation (Gulf) in Section 10 on property pоoled by agreement of the plaintiffs. The Symionow Well was a marginal producer. On June 27, 1980, still within the primary term of both leases, production from the Symionow Well ceased. During a two-week period in July 1980, Gulf conducted tests on the Symio-now Well. This operation included pulling the tubing and running a pipe inspection log. Gulf determined that serious casing leaks existed which prevented the well from producing oil and gas. This problem was similar to that encountered by Gulf with other wells it operated in the Little Knife Field. On July 29, 1980, Gulf removed the workover rig from the Symio-now Well site and, except for routine maintenance visits by the pumper, all physical activity on the site ceased for approximately seven and one-half months. No delay rental payments were tendered on or before October 6 or 7, 1980, the anniversary dates of the leases.
After evaluating the test data, Gulf decided in October 1980 to develop a special casing liner as a possible remedy, a technique that previously had not been used in the Little Knife Field. Gulf decided to install the liner in a well known as the Kostelnak Well, which had problems similar to those encountered with the Symio-now Well, to test whether the liner concept was feasible from an engineering stаndpoint. The Kostelnak Well, in which the plaintiffs had no interest, was chosen by Gulf for installation of the liner because of its greater producing capacity and because Gulf was the only working interest holder, thereby obviating the need for obtaining consent from other parties.
*811 In late December 1980 and early January 1981, Kiker tendered delay rental payments to the plaintiffs, which they refused to accept and returned to him. By mid-January 1981, the special liner had arrived and Gulf installed it in the Kostelnak Well, but because of other problems at the well site, production was not restored. Gulf, however, determined that the concept of the liner was feasible and could be used in the other wells located in the Little Knife Field.
During March 1981, Gulf returned to the Symionow Well and attempted to perforate another zonе to determine whether sufficient additional quantities of oil and gas could be recovered to justify the cost of installing the special liner to correct the casing leaks. Pumping operations were continued until May 3, 1981, when Gulf determined that no oil or gas could be obtained from the additional zone. No liner was installed and the Symionow Well was abandoned. In the meantime, Martin, pursuant to a farm-out agreement with Kiker, had staked a well on March 12,1981, in Section 3 on lands pooled by agreement of the plaintiffs. The well was completed on August 1, 1981, and it produced oil in commercial quantities.
The plaintiffs, in February 1981, served written demands upon Kiker and Martin pursuant to § 47-16-36, N.D.C.C., that the two oil and gas leases be released of record. Kiker and Martin replied pursuant to the statute and asserted that the leases were in full force and effect. The plaintiffs instituted the present action against Kiker and Martin in September 1981 seeking cancellation of the leases and damages for slander of title. The plaintiffs claimed that the leases expired by their own terms because of the failure to timely pay delay rentals. Kiker and Martin asserted that the leases remained in effect because reworking operаtions were commenced within 60 days after the Symionow Well ceased production, and counterclaimed for damages for malicious prosecution. Kiker and Martin also brought a third-party action against Gulf seeking contribution or indemnity and asserting negligence in its operation of the Symionow Well.
Following a bench trial on the- issue of liability alone, 1 the trial court dismissed the plaintiffs’ action. The court determined that, “as a matter of law, ‘reworking oрerations’ as contemplated in the leases commenced” on the Symionow Well within 60 days from the date that production ceased; that the actions of Gulf “were those of a prudent operator” and that Gulf “exhibited good faith and a bona fide intent to restore production” of the well; that reworking operations included “the testing and evaluation of the casing problems” on the Symio-now Well and “the efforts of Gulf to determine the engineering feasibility of a liner in the Little Knife Field that could be used” on the well; that the “subsequent determination of engineering feasibility and recompletion of the well constituted additional reworking operations in an attempt to restore production;” and that Gulf’s reworking operations “held the ... leases through the time that operations were commenсed by Martin ... which culminated in a producing oil well in Section 3, ...” In a subsequent separate order incorporated into the amended final judgment, the court granted the plaintiffs’ motion for partial summary judgment dismissing Kiker and Martin’s counterclaims for malicious prosecution. The court also dismissed as moot Kiker and Martin’s third-party action against Gulf. These appeals followed.
The oil and gas leases involvеd in this case are “unless” leases.
2
An “unless” clause does not obligate the lessee to do an act but provides that the lease shall terminate unless the lessee does some act. The “unless” clause does not state a condi
*812
tion subsequent upon which the lease may be forfeited, but it is construed as a clause of special limitation and if delay rental payments required by the lease are deficient in either time or the amount of payment, the lease terminates automatically, without any requirement of notice or demand on the part of the lessor.
Borth v. Gulf Oil Explor. & Prod. Co.,
This court has never before considered the meaning and application of the term “reworking oрerations” as used in lease provisions in the oil and gas industry. Decisions from other jurisdictions demonstrate that an exact definition of “reworking operations” applicable under all circumstances is difficult to formulate.
See
8 H. Williams and C. Meyers, Oil and Gas Law, Manual of Terms, 758-759 (1984). In
Lone Star Producing Company v. Walker,
“It would be difficult, if not impossible, to formulate a rule that would with exactness define reworking operations such as those contemplated by the terms of the leases in question because the problems of capturing and producing oil and gas located thousands of feet below the surface of the earth are many and varied. Reworking operations may encompass testing, evaluation and other acts performed necessary to reworking a given well, and each case will have to be considered in the light of faсts peculiar to that operation. One of the prime requirements is that the acts of the operator constitute a bona fide effort to rework a given well.”
An often-cited, rather broad, definition of the term is found in
Rogers v. Osborn,
“ ‘ “[R]e-working operations,” as used herein, means actual work or operations which have theretofore been done, being done over, and being done in good faith endeаvor to cause a well to produce oil and gas or oil or gas in paying quantities as an ordinarily competent operator would do in the same or similar circumstances.’ ” 3
In
Sheffield v. Exxon Corp.,
“The crucial test which must be met for an activity to constitute reworking is whether the operation is associated or connected with the physical site of the well or unit. Additionally, the operation must be intimately connected with the *813 resolution of whatever physical difficulty caused the well to cease production. ******
“Consequently, operations or activities which are not designed to revitalize a well, or to restore lost production, do not constitute reworking.”
From our review of the case law on the subject, certain guidelines appear to be fairly well established. While it is clear that routine maintenance procedures, such as the periodic starting of the pump on the lease to keep it in running operation, do not constitute reworking operations
[Hall v. McWilliams,
Furthermore, a lessee’s intent to сontinue reworking operations after commencement must be unqualified, and not dependent upon the happening of certain contingencies.
Cf. True Oil Company v. Gibson,
In the present case, following the two-week testing operations conducted on the Symionow Well in July 1980, no physical activity occurred at the well site until mid-March 1981. In the interim, Gulfs intent to continue any further operations on the Symionow Well was conditional. Indeed, Gulf did not reach a decision to take any further action with regard to the Sym-ionow Well until February 1981. It is clear from the record that continuance of operations on the Symionow Wеll was dependent upon two contingencies: the special casing liner would have to be tested and found successful in the Kostelnak Well, in which the plaintiffs had no interest, and if the liner was successful, Gulf would have to locate and establish more production from a lower zone in the Symionow Well to economically justify the placement of the liner in the well.
5
While Gulfs decision to test
*814
the liner on the Kostelnak Well before arriving at a decision on what course to take with regard to the Symionow Well might very likely have been reasonable and prudent from an overall economic standpoint, its actions did not comply with the 60-day provision of the leases covering the Symio-now Well. “The prudent-operator standard ... is inapplicable to operations necessary to keep a lease alive under a special limitation or condition.” 5 H. Williams and C. Meyers, Oil and Gas Law § 808, at p. 57 (1985).
See also Trinidad Petroleum v. Pioneer Natural Gas,
Under the circumstances, operations conducted on the Kostelnak Well as a preliminary contingency to taking any further action on the Symionow Well did not constitute the diligent prosecution of efforts to restore the Symionow Well to production as soon as possible. Thus, because the preliminary testing conduсted on the Symio-now Well was not followed by diligent prosecution of efforts to restore the well to production, those testing activities did not constitute the “commencement” of reworking operations within the meaning of the 60-day clause in the leases. Consequently, we conclude that, as a matter of law, the trial court erred in determining that reworking operations on the Symionow Well were cоmmenced within 60 days after production ceased.
We note, as did the court in
Jardell, supra,
Kiker and Martin have raised numerous equitable defenses to cancellation of the leases which the trial court did not rule upon in view of its disposition of the case. This court has held that equitable relief under certain circumstances may be applied to prevent the automatic termination of an “unless” lease.
E.g., Borth v. Gulf Oil Explor. & Prod. Co.,
In their cross-appeals, Kiker and Martin assert that the trial court erred in dismissing their action for malicious prosecution.
6
A party alleging malicious prosecution of a civil action has the burden of establishing that the other party instituted the action with malice and without probable cause.
Nisewanger v. W.J. Lane Co.,
The plaintiffs assert that the trial court erred in dismissing their slander of title action against Kiker and Martin. In order to maintain an action for slander of title, it must be shown that the defendant acted maliciously.
Briggs v. Coykendall, 57
N.D. 785, 790,
Accordingly, we affirm the trial court’s dismissal of the plaintiffs’ slander of title action and Kiker and Martin’s counterclaims; we reverse the trial court’s dismissal of the plaintiffs’ action seeking cancellation of the oil and gas leases; because Kiker and Martin’s third-party action against Gulf is no longer moot, we reverse the trial court’s dismissal оf that action; and we remand to the trial court for consideration of Kiker and Martin’s equitable defenses to cancellation of the leases. No costs are allowed on the appeal.
Notes
. The trial court bifurcated the liability and damage questions and also left for later consideration the counterclaims of Kiker and Martin against the plaintiffs as well as the third-pаrty actions against Gulf.
. Contrary to the assertion of Kiker and Martin, the leases involved in this case are not "drill or pay” leases. See 8 H. Williams and C. Meyers, Oil and Gas Law, Manual of Terms, 251-252, 905-906, 941 (1984).
. The definition of "reworking operations" in
Rogers v. Osborn,
. Although the decisions in
True Oil Company v. Gibson,
We further note that this court’s recent decision in
Johnson v. Hamill,
. During the trial, the following colloquy occurred between counsel for the plaintiffs and Edward A. McKinnon, the Williston Basin project manager for Gulf:
"Q [By Mr. Dynes]: Now, is it correct then that with, for the Symionow Well to have been reworked in this fashion, you needed two things? You needed a success picture on the liner in Kostelnak and you had to find some more production in that lower zone in the Sym-ionow Well?
"A [By Mr. McKinnon]: Yes.
*814 “Q And the order was this, wasn’t it that you tried it with Kostelnak to see whether the liner would work?
"A That’s correct.
“Q Because if it didn’t work then you forget about Symionow?
"A That’s right.
“Q And then if it did work, then the next step was to get the second area of production in Symionow?
"A That’s right.
"Q So that you could increase the taking of oil out of thаt well?
"A Correct.
"Q So what actually happened then was that although the Kostelnak Well wasn’t rejuvenated, you passed the first stage and you were satisfied that another liner would work in another well in the Little Knife?
"A Yes.
"Q Then you went to try to get the additional production in Symionow and it didn’t work?
"A That’s correct.
“Q It was unsuccessful?
“A Yes.
"Q So, because of that, you never even attempted to put a liner in the Symionow Well?-
“A That’s correct."
. The trial court also dismissed Kiker’s counterclaim аgainst Joseph Romanyshyn for breach of warranty. Kiker has neither briefed nor argued this issue, and we therefore deem it abandoned.
See City of Fargo v. Windmill, Inc.,
We further note that generally, a malicious prosecution action is premature when it is instituted as a counterclaim to a pending civil proceeding.
See Farmers Elevator Company
v.
David,
. This general rule is not applicable if the initial judgment against the person bringing the malicious prosecution action "was obtained by fraud, perjury, or other improper means, ...” Annot.,
