132 F.4th 544
D.C. Cir.2025Background
- The Federal Energy Regulatory Commission (FERC) granted Driftwood Pipeline LLC a certificate to construct and operate two new natural gas pipelines (Lines 200 and 300) in southwestern Louisiana.
- Healthy Gulf and Sierra Club challenged FERC’s approval, alleging violations of the National Environmental Policy Act (NEPA) and the Natural Gas Act (NGA).
- Petitioners argued FERC’s environmental review was deficient, especially regarding greenhouse gas (GHG) emissions and cumulative impacts with a related terminal project.
- FERC conducted an environmental impact statement and found the project’s environmental impacts, including GHG emissions, not significant or unable to be characterized as significant/insignificant.
- The D.C. Circuit reviewed FERC’s actions for arbitrariness under the Administrative Procedure Act (APA) and ultimately denied the petitioners’ challenge, upholding FERC’s decision.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Upstream GHG effects in NEPA review | FERC failed to consider reasonably foreseeable upstream GHG emissions from new gas production | Sources and quantities of extra wells are unpredictable; reasonable foreseeability not established | FERC’s refusal to analyze upstream GHG was not arbitrary |
| Significance of GHG emissions | FERC should have determined if GHG emissions were significant using the social cost of carbon | No accepted criteria for NEPA significance using social cost of carbon; monetization ≠ significance | FERC’s explanation for not determining significance was sufficient |
| Cumulative impacts with Driftwood Terminal (connected actions) | FERC should have considered cumulative environmental impacts with the related Driftwood Terminal | Petitioners failed to timely raise the segmentation/cumulative impacts argument below | Challenge was forfeited due to procedural default |
| Market need and public benefit balancing under NGA | FERC erred in finding market need and in weighing project benefits over GHG-related costs | Substantial evidence supports market need and appropriate balancing of benefits and environmental harms | FERC’s findings were adequately supported and not arbitrary |
Key Cases Cited
- Atl. Refin. Co. v. Pub. Serv. Comm’n, 360 U.S. 378 (public convenience and necessity standard under NGA)
- Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87 (agency duty under NEPA is to consider and disclose impacts)
- Minisink Residents for Env’t Pres. & Safety v. FERC, 762 F.3d 97 (standards for reviewing agency environmental analysis)
- Sierra Club v. FERC, 867 F.3d 1357 (scope of review for pipeline approvals under NEPA and NGA)
- City of Oberlin v. FERC, 937 F.3d 599 (use of affiliate precedent agreements to show market need)
- EarthReports, Inc. v. FERC, 828 F.3d 949 (FERC need not determine significance of GHG emissions under NEPA)
- Del. Riverkeeper Network v. FERC, 45 F.4th 104 (precedent agreements as evidence of market need)
- B&J Oil & Gas v. FERC, 353 F.3d 71 (arbitrariness standard of review for agency certification)
- Environmental Defense Fund v. FERC, 2 F.4th 953 (limits of reliance on affiliate precedent agreements to demonstrate market need)
- Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752 (forfeiture for failing to raise issues at the agency stage)
- Ctr. for Biological Diversity v. FERC, 67 F.4th 1176 (NEPA does not require significance determination of GHG)
