History
  • No items yet
midpage
Golden Nugget Lake Charles, L.L.C. v. W.G. Yates & Sons Construction Co.
2017 WL 892407
5th Cir.
2017
Read the full case

Background

  • Golden Nugget (owner) contracted with W.G. Yates (general contractor) to build the Golden Nugget Lake Charles casino/hotel; the parties recorded a notice of contract and bonds in Calcasieu Parish.
  • Project was occupied and a certificate of substantial completion was signed on December 1, 2014; Golden Nugget continued to withhold roughly $18.7 million alleging Yates breaches.
  • Golden Nugget sued Yates in federal court (Nov. 25, 2015); Yates counterclaimed (Dec. 21, 2015) and stated it would file a LPWA lien; Yates recorded a lien statement on Dec. 23, 2015.
  • Golden Nugget moved to dismiss Yates’s lien claim as untimely under La. Stat. § 9:4822; the district court dismissed with prejudice, concluding Yates missed the statutory filing period.
  • Yates appealed; the Fifth Circuit considered whether the phrase “substantial completion of the work” in § 9:4822(B) refers to an event (the project’s completion/occupancy) or a filed document (a recorded notice), which determines when the 60-day filing clock starts.

Issues

Issue Golden Nugget's Argument Yates's Argument Held
Whether “substantial completion of the work” in La. Rev. Stat. § 9:4822(B) is an event or a filed notice, i.e., what triggers the 60-day period to file a lien statement for a general contractor when a notice of contract is recorded The phrase refers to an event (e.g., occupancy/certificate of substantial completion); once the project was substantially complete in Dec 2014, the 60-day period expired before Yates filed The phrase refers to a filed document (a recorded notice of substantial completion); because Golden Nugget never filed such a notice, the 60-day period never began and Yates’s Dec. 23, 2015 lien was timely The court held the statute refers to a filed notice: when a contract is recorded, the owner must file a notice of termination or notice of substantial completion to trigger the filing period; because no such notice was filed here, Yates’s lien remains valid and the dismissal is reversed

Key Cases Cited

  • In re Whitaker Constr. Co., 439 F.3d 212 (5th Cir.) (interpreting LPWA filing triggers and holding recorded-contract situations require an owner filing to trigger claim period)
  • Bernard Lumber Co. v. Lake Forest Construction Co., 572 So. 2d 178 (La. Ct. App.) (places onus on owner to file notice of termination when a notice of contract is recorded)
  • Byron Montz, Inc. v. Conco Construction, Inc., 824 So. 2d 498 (La. Ct. App.) (treated filing date of certificate/notice as trigger for subcontractor lien period)
  • Clark Constr. Co. v. Warren, 760 So. 2d 677 (La. Ct. App.) (used filing date of notice of substantial completion to assess lien timeliness)
Read the full case

Case Details

Case Name: Golden Nugget Lake Charles, L.L.C. v. W.G. Yates & Sons Construction Co.
Court Name: Court of Appeals for the Fifth Circuit
Date Published: Mar 6, 2017
Citation: 2017 WL 892407
Docket Number: 16-30496
Court Abbreviation: 5th Cir.