Byron Montz, Inc. v. Conco Construction, Inc.Byron Montz, Inc. v. Conco Construction, Inc.
This is an action by a subcontractor against the owner to recover the balance due on the subcontract for work performed under a construction contract. The subcontractor failed to preserve its claim and privilege under the Private Works Act,
FACTS
In 1999, Internal Medicine Specialist, Inc. (IMS) contracted with Conco Construction Co., a general contractor, to renovate its medical office suite in New Orleans, Louisiana.
| ¡^Invoking the special notice provision in
In early 2000, Montz completed all the work under its subcontract and billed Con-co for $30,474.20. In August 2000, Conco paid Montz $10,000, leaving an outstanding balance owed of $20,474.20. On January 4, 2001, Montz filed a lien affidavit or statement of claim purportedly pursuant to
On June 11, 2001, IMS filed an exception of no cause of action and motion for summary judgment. IMS claimed that Montz failed to perfect a valid claim against it because Montz’s statement of claim was not filed timely, i.e., within the thirty or sixty day periods set forth in
In support of its summary judgment motion, IMS submitted an affidavit of its administrator, Rita Latour. Ms. Latour attested that on March 14, 2000, IMS filed the Certificate of Substantial Completion and, at that time, the work performed under the contract was substantially complete. Ms. Latour further attests that IMS made full and final payment to the contractor, Conco, on August 1, 2000. | aAttached to Ms. Latour’s affidavit was a “lien and privilege certificate” dated May 18, 2000, issued by the Recorder of Mortgages for Orleans Parish. The lien and privilege certificate stated that both the contract and the Certificate of Substantial Completion were filed in the public records on March 14, 2000 and documented that no liens were filed within sixty days from the Certificate of Substantial Completion. IMS thus contended that the statement of claim Montz filed on January 4, 2001 clearly was untimely under either the thirty or sixty day periods of
On October 26, 2001, the trial court granted summary judgment in IMS’ favor, dismissing Montz’s petition against IMS with prejudice. In its oral reasons for judgment, the court stated that Montz, as a subcontractor, had no claim and no privilege against IMS, as owner, unless Montz properly and timely filed a statement of claim pursuant to
• The construction work was substantially completed on January 8, 2000.
• The Lien and Privilege Certificate issued by the Recorder of Mortgages on May 18, 2000, shows that the contract itself and the Certificate of Substantial Completion were both filed on March 14, 2000.
14* IMS made full and final payment to contractor Conco on August 1, 2000.
• Plaintiff admittedly filed its statement of claim, that is its Lien Affidavit, on January 4, 2001, almost eight (8) months after IMS filed the notice of contract on March 14, 2000.
The trial court thus reasoned that pursuant to
Montz appeals from that judgment. Despite its failure to file its statement of claim timely, Montz claims that is has two claims against IMS: (1) a claim and privilege under the Private Works Act for the unpaid balance, and (2) a claim outside the Act for costs and attorney’s fees in pursuing its claims and privileges against IMS and Conco.
ANALYSIS
On appeal, the standard of review of a trial court’s decision granting summary judgment is de novo. Shelton v. Standard/700 Associates, 2001-0587, p. 5 (La.10/16/01),
The dispute in this case is not a factual, but a legal one. The parties do not contest the facts, but rather the consequences that result from an owner’s failure to comply with the special notice provision the Legislature added in 1988. to
K. (1) Any person to whom a privilege is granted by R.S. 9:4802 may give notice to the owner of an obligation to that person arising out of the performance of work under the contract. The notice shall be given prior to:
(a) The filing of a notice of termination of the work; or
(b) The substantial completion or abandonment of the work, if a notice of termination is not filed.
(2) The method of notice shall be under R.S. 9:4842(A). The notice shall set forth the nature of the work or services performed by the person to whom the obligation is owed and shall include his mailing address.
L. (1) When notice under Subsection K has been given by a person to the owner, the oumer shall notify that person as required by R.S. 9:4842(A) within three days of:
(a) Filing a notice of termination of the work; or
(b) The substantial completion or abandonment of the work, if a notice of termination is not filed.
|fi(2) The owner who fails to give notice to the person under the provisions of this Subsection within ten days of commencement of the period for preservation of claims and privileges shall be liable for all costs and attorney’s fees for the establishment and enforcement of the claim or privilege. (Emphasis added.)
For purposes of summary judgment, IMS conceded that Montz notified IMS of its work on the project as permitted by
Although Montz strongly disputes IMS’s contention that the sole basis of its claim is the filing of a statement of claim and argues, as discussed elsewhere, that it has a claim under
The Private Works Act was enacted to facilitate construction of improvements on immovable property and does so by granting to subcontractors, among others, two rights to facilitate recovery of the costs of their work from the owner with whom they lack privity of contract. The first right is a statutory “claim” — the right to personally sue the owner for the amount that is owed-that is provided by
If a notice of contract is properly and timely filed in the manner provided by R.S. 9:4811, the persons to whom a claim or privilege is granted by R.S. 9:4802 shall within thirty days after the filing of a notice of termination of the work:
(1) File a statement of their claims or privilege.
(2) Deliver to the owner a copy of the statement of claim or privilege. If the address of the owner is not given in the notice of contract, the claimant is not required to deliver a copy of his statement to the owner.
|7The validity of the claim and privilege granted a subcontractor by
Those persons granted a claim and privilege by R.S. 9:4802 for work arising out of a general contract, notice of which is not filed, and other persons granted a privilege under R.S. 9:4801 or a claim and privilege under R.S. 9:4802 shall file a statement of their respective claims and privileges within sixty days after:
(1) The filing of a notice of termination of the work; or
(2) The substantial completion or abandonment of the work, if a notice of termination is not filed.
The jurisprudence uniformly holds that a subcontractor has the burden of proving that its statement of claim was timely filed and unless it meets this burden cannot avail itself of any of the rights provided under the Private Works Act. Marshall Achord Electrical Contractor. Inc. v. Zeagler,
Applying those principles to the facts of this case,
Montz alleges that despite its failure to timely preserve its claim, it would be unfair to allow an owner, like IMS, who failed to comply with the mandatory notice requirement of
The Legislature, in adopting the Act, granted a special right in favor of specified claimants, but limited the time for enforcing that right in the manner prescribed in the Act, after which the right becomes extinguished and passes out of existence. The Legislature clearly intended to extinguish in short order the special rights of those claimants who did not file their privileges and their actions within the specified time limitations. The Act thus balances the private interest in asserting claims against the public interest in limiting special rights.
Landis,
Although in this case IMS had an obligation to notify Montz of completion of the project pursuant to
Montz’s second claim is that
The flaw in Montz’s argument, as the trial court recognized, is that
Finally, we find unpersuasive Montz’s argument that affirming the trial court’s decision granting IMS summary judgment would render
Summarizing, we find that recovery for attorney’s fees and costs under
AFFIRMED.
Notes
. At oral argument before this court, the parties acknowledged that IMS owns the immovable properly on which the renovations were made.
. The contract between the subcontractor and general contractor provided for mandatory arbitration of disputes between the parties. Invoking that provision, the general contractor filed an exception of prematurity to the petition. The claim against the contractor is not before us.
. Although the trial court refers to
.
.
. As noted, the trial court incorrectly refers to