History
  • No items yet
midpage
785 F. Supp. 2d 1258
M.D. Ala.
2011
Read the full case

Background

  • Glenn Construction sued Bell Aero and BWSC over a $6,000,000 helicopter-hangar project in Ozark, Alabama, alleging breach of contract, negligence, wantonness, fraud, and intentional interference.
  • BWSC served as project engineer and Bell Aero owned the project; Glenn was the general contractor.
  • Contract allowed BWSC to supervise, interpret, and decide disputes, approve payments, and issue change orders; Glenn bid in 2007 and work commenced February 2007 with a 226-day window.
  • Project issues centered on an underground stream, miscalculated foundation loads, obsolete drawings posted online, and revised pedestal designs that affected construction timing and costs.
  • Plaintiff asserted BWSC knew of problems (underground stream, loads, drawings) and acted to delay or frustrate Glenn’s performance; Glenn sought damages and final payment under the contract terms.
  • The court granted in part and denied in part the motions for summary judgment, including determining agency relationships and various fraud and negligence claims.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Fraudulent suppression of underground stream existence Glenn shows BWSC had actual knowledge via prior site work and geotechnical reports. BWSC did not have preexisting knowledge; suppression claim fails on knowledge element. Denied summary judgment on suppression claim; genuine factual issue exists.
Promissory fraud regarding pre-bid on-site structural engineer BWSC promised to send a structural engineer on site to review submittals. Promise to perform future act lacks misrepresentation of existing fact; no intent evidence. BWSC entitled to judgment as a matter of law; promissory fraud claim granted for pre-bid promise.
Fraudulent misrepresentation regarding adequacy of designs (hangar and foundation) BWSC knew or should have known designs were inadequate and misrepresented adequacy. No proof BWSC knew designs were inadequate; misrepresentation of existing facts. Denied summary judgment; jury could find misrepresentation regarding adequacy.
Intentional interference with Glenn Construction’s contract with Bell Aero (tri-partite relationship) BWSC interfered beyond its rights, affecting Glenn’s contract with Bell Aero. BWSC was not a stranger to the contract; actions within its role. BWSC not a stranger; granted summary judgment for this interference claim.
Agency/respondeat superior liability of Bell Aero for BWSC's actions Bell Aero should be liable under agency or respondeat superior theory for BWSC’s conduct. No controlling agency or master-servant relationship shown; no liability. BWSC not Bell Aero’s agent; Bell Aero not liable on agency theory; upheld for Bell Aero on this point.

Key Cases Cited

  • State Farm Fire & Cas. Co. v. Slade, 747 So.2d 293 (Ala. 1999) (fraud elements and suppression burden)
  • Green Tree Acceptance, Inc. v. Doan, 529 So.2d 201 (Ala. 1988) (elements of fraud and reliance)
  • AmerUs Life Ins. Co. v. Smith, 5 So.3d 1200 (Ala. 2008) (misrepresentation of material fact; no intent required)
  • Collins Co. v. Decatur, 533 So.2d 1127 (Ala. 1988) (engineer not always agent; peculiarity of agency in tri-party relations)
  • Waddell & Reed, Inc. v. United Investors Life Ins. Co., 875 So.2d 1143 (Ala. 2003) (agency/partnership considerations in tort interference)
  • MAC East, LLC v. Shoney's, 535 F.3d 1293 (11th Cir. 2008) (multifactor tests for whether defendant is a stranger to contract)
  • Edwards v. Prime, Inc., 602 F.3d 1276 (11th Cir. 2010) (tri-party relationships and agency concepts in contract context)
Read the full case

Case Details

Case Name: Glenn Construction Co. v. Bell Aerospace Services, Inc.
Court Name: District Court, M.D. Alabama
Date Published: May 19, 2011
Citations: 785 F. Supp. 2d 1258; 2011 U.S. Dist. LEXIS 53949; 2011 WL 1899330; Case 1:09-cv-250-MEF
Docket Number: Case 1:09-cv-250-MEF
Court Abbreviation: M.D. Ala.
Log In