History
  • No items yet
midpage
Gadsden Industrial Park, LLC v. United States
956 F.3d 1362
Fed. Cir.
2020
Read the full case

Background

  • In 2002 Gadsden Industrial Park (GIP) bought certain assets from a bankrupt steel mill but expressly excluded the "Eastern Excluded Property" (real estate) while purchasing personal property that included kish, scrap, and an allotment of "420,000 cubic yards of slag."
  • The Eastern Excluded Property contained two large industrial-landfill piles (millions of cubic yards, >80 ft high) of slag, kish, and scrap. The Bill of Sale and GIP’s own exclusion list allocated 420,000 cu. yds. of slag and did not identify particular physical subsets.
  • Starting in 2003 the EPA investigated leachate and, in 2008, ran a remediation program (2009–2013) that recovered and sold material (245,890 tons, ≈$13.5M proceeds) and used 92,500 cu. yds. of slag onsite; contractors processed ~50% of the piles before the project ended.
  • GIP sued in the Court of Federal Claims alleging a Fifth Amendment taking of slag, kish, and scrap; it sought compensation for slag and expert fair-market valuations (or lost-profits) for kish/scrap.
  • The Court of Federal Claims found a taking occurred, awarded $755,494 for 92,500 cu. yds. of slag, but awarded zero for kish and scrap because GIP’s valuation (Mr. Gleason) relied on unreliable assumptions (inflated June 2008 price; speculative avoided-costs based on a non-final Watkins deal).
  • On appeal the Government contested the slag property interest ruling; GIP challenged the amount of slag compensated and the zero award for kish/scrap.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether GIP had a cognizable property interest in the slag the EPA recovered GIP: exclusion language conveyed ownership of 420,000 cu. yds. of slag and EPA’s remediation prevented recovery of that allotment, so compensation should cover remaining allotment (405,000 cu. yds.) Gov’t: GIP’s exclusion created an undifferentiated fungible allotment but gave no right to specific physical tons or to exclude others; sufficient slag remained on the parcel after EPA work Court: GIP had no property right to particular slag removed by EPA; trial court’s finding that EPA "embalmed permanently" remaining material was clearly erroneous; vacated award for 92,500 cu. yds. of slag (no cognizable taking of those tons)
Whether trial court erred by awarding $755,494 (and not more) for slag GIP: trial court should have awarded compensation for 405,000 cu. yds. remaining in its allotment Gov’t: GIP cannot show a right to specific slag tons and had no superior right blocked by EPA operations Held with first issue: GIP cannot establish right to particular slag recovered; cannot increase award; trial court’s award vacated
Whether the trial court erred in awarding zero for kish and scrap after finding they had value and were taken GIP: once taking is found, court must fashion an appropriate compensation award and should not award zero when value is established Gov’t: GIP failed to prove damages with reasonable certainty—expert used inflated prices and speculative avoided-costs; trial court properly exercised discretion Court: Plaintiff bears burden to prove actual damages with reasonable certainty; trial court did not err in awarding zero where GIP’s valuation was unreliable and critical avoided-cost evidence was insufficient

Key Cases Cited

  • Wheeler v. First Ala. Bank of Birmingham, 364 So. 2d 1190 (Ala. 1978) (written-document construction is a question of law)
  • Almota Farmers Elevator & Warehouse Co. v. United States, 409 U.S. 470 (1973) (just compensation measure for leasehold improvements—fair market value principles)
  • Otay Mesa Prop., L.P. v. United States, 779 F.3d 1315 (Fed. Cir. 2015) (trial court may fashion its own valuation when evidence supports it)
  • Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (plaintiff must prove damages with reasonable certainty)
  • Palmyra Pac. Seafoods, L.L.C. v. United States, 561 F.3d 1361 (Fed. Cir. 2009) (plaintiff bears burden to demonstrate protectable property interest)
  • Holland v. United States, 621 F.3d 1366 (Fed. Cir. 2010) (standard of review: legal questions de novo, fact findings for clear error)
  • United States v. General Motors Corp., 323 U.S. 373 (1945) (discussion of appropriate measures of just compensation)
Read the full case

Case Details

Case Name: Gadsden Industrial Park, LLC v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Apr 22, 2020
Citation: 956 F.3d 1362
Docket Number: 18-2132
Court Abbreviation: Fed. Cir.