History
  • No items yet
midpage
Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
205 Cal. Rptr. 3d 21
Cal. Ct. App.
2016
Read the full case

Background

  • TEC submitted a written bid ($1,272,960) to Flintco for glazing work that expressly included material conditions: a 35% deposit, no bond, no liquidated damages, a 15-day acceptance period, and a 3% per-quarter escalation after 15 days.
  • Flintco used TEC’s bid price in its prime bid and was awarded the prime contract; Flintco listed TEC as the subcontractor.
  • After award, Flintco sent a letter of intent and its standard-form subcontract to TEC; those documents omitted or conflicted with TEC’s bid conditions (no 35% deposit, included liquidated damages, bond requirements, etc.).
  • TEC repeatedly raised the conflicts and ultimately notified Flintco it would not pursue the subcontract and withdrew its bid; Flintco then hired a replacement subcontractor and sued TEC for promissory estoppel damages.
  • The trial court found Flintco’s reliance on TEC’s price alone unreasonable because Flintco ignored material bid terms; Flintco’s letter/subcontract constituted a counteroffer that terminated its power to accept TEC’s original offer. Judgment for TEC affirmed on appeal.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Flintco reasonably relied on TEC’s bid such that promissory estoppel binds TEC to its bid price Flintco: industry custom permits relying on bid price alone at bid time; no indication TEC wouldn’t honor bid before August TEC: bid contained clear, material conditions affecting price; reliance on price alone was unreasonable Court: Reliance was unreasonable; substantial evidence supported that TEC’s conditions materially affected price and Flintco ignored them
Whether Flintco’s post-award communications constituted a counteroffer that let TEC withdraw Flintco: its letter of intent/subcontract were routine and did not terminate TEC’s offer TEC: letter and standard subcontract materially varied from TEC’s bid (qualified acceptance) and thus were a counteroffer, terminating Flintco’s power to accept Court: Flintco’s documents qualified the acceptance and were a counteroffer; TEC properly withdrew its bid

Key Cases Cited

  • Drennan v. Star Paving Co., 51 Cal.2d 409 (recognizes promissory estoppel where subcontractor’s bid is relied on by general contractor)
  • Saliba–Kringlen Corp. v. Allen Engineering Co., 15 Cal.App.3d 95 (customary practice of resolving post-award subcontract terms; reliance is fact-specific)
  • Diede Construction, Inc. v. Monterey Mechanical Co., 125 Cal.App.4th 380 (discusses promissory estoppel elements in subcontractor‑bid context)
  • H. W. Stanfield Constr. Corp. v. Robert McMullan & Son, Inc., 14 Cal.App.3d 848 (cases addressing mistaken bids and estoppel principles)
Read the full case

Case Details

Case Name: Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
Court Name: California Court of Appeal
Date Published: Jun 21, 2016
Citation: 205 Cal. Rptr. 3d 21
Docket Number: B258353
Court Abbreviation: Cal. Ct. App.