Opinion
Dеfendant, a painting subcontractor, appeals from a money judgment awarding damages to plaintiffs, general contractors, on account of defendant’s refusal tо do painting work in compliance with a bid submitted to plaintiffs.
In preparation of a bid on the prime contract to do construction work for the United States Navy, plaintiffs advеrtised for bids from subcontractors on various phases of the work. On January 25, 1968, a few hours before the time for submission of bids on the prime contract, defendant, in a telephonic communication with plaintiffs, submitted a bid of $9,384 on the painting work required by Section 9F of the plans and specifications for the construction project. Plaintiffs checked defendant’s bid with others they had received and noted the latter were for $18,500, $18,713, $19,475 and $24,463; thereupon, because of the apparent discrepancy between defendant’s bid and the othеr bids, by telephone communication advised defendant the latter’s bid was quite low, and requested defendant review and verify it before bid time, which was 2 o’clock; and thereafter, on the same day,
Plaintiffs caused the painting work upon which defendant had bid to be performed by another subcontractor for the sum of $18,713, and sued for $5,452 which is the difference bеtween this amount and the amount of defendant’s bid. The judgment awarded plaintiffs $5,239 which is the difference between defendant’s bid and the next lowest bid received. Plaintiffs make no complaint respecting the difference between the amount they sought and the amount they were awarded.
In a written opinion the trial judge expressed his belief the facts in the casе were substantially similar to those in the case of
Drennan
v.
Star Paving Co.,
In
Drennan
v.
Star Paving Co., supra,
Defendant contends the doctrine of promissory estoppеl does not apply here because (1) plaintiffs’ reliance upon defendant’s bid was not justifiable or reasonable; (2) plaintiffs unreasonably delayed acceptаnce of defendant’s bid; and (3) plaintiffs submitted a counteroffer constituting a reopening of the bid which forecloses application of the doctrine.
The contention plaintiffs’ reliance on defendant’s bid was not justifiable or reasonable, in substance, is premised upon the claim the finding of the court to the contrary was not supported by the evidence; relies upon the fact plaintiffs knew defendant’s bid was substantially lower than other bids submitted; but disregards the fact plaintiffs expressed concern respecting defendant’s first bid аnd inferentially were entitled to assume its second bid was not the product of any misconception, misunderstanding or mistake. Once having alerted defendant to the possibility of errоr in its bid, plaintiffs should not be held knowledgeable of or responsible for any subsequent mistake allegedly resulting in the second bid as a matter of law. The finding of the trial court plaintiffs had no knowledge of any such mistake and their reliance upon the second bid was justifiable and reasonable is supported by inferences reasonably deducible from the evidence.
Defendant’s contentions plaintiffs unreasonably delayed acceptance of defendant’s bid and made a counteroffer in lieu of acceptance attempt to apply the limitation on application of the doctrine of promissory estoppel which is expressed in
Drennan
v.
Star Paving Co., supra,
We deem immaterial to a decision in the case defendant’s contention an enforceable contract was not created between plaintiffs and defendant because mutual assent was lacking and for this reason the judgment is in error. Obviously the doctrine of promissory estoppel is not premised upon the existence of an enforceable contract. The judgment in the case at bench was proper under the facts found and the law as declared in
Drennan
v.
Star Paving Co., supra,
The judgment is affirmed.
Brown, P. J., and Ault, J., concurred.
