History
  • No items yet
midpage
Firstenergy Service Co. v. Federal Energy Regulatory Commission
411 U.S. App. D.C. 155
D.C. Cir.
2014
Read the full case

Background

  • FirstEnergy petitioned review after FERC denied a legacy-cost exemption and sustained PJM’s Schedule 12 allocations following FirstEnergy’s move from MISO to PJM.
  • FirstEnergy transferred ATSI from MISO to PJM in 2011 and sought to terminate MISO participation while joining PJM.
  • MISO and PJM socialize transmission-project costs differently; MISO uses project-by-project allocations, PJM uses annual reallocation under Schedule 12.
  • ATSI would pay for pre-2011 MISO regional facilities and also its share of PJM legacy costs for projects approved before joining PJM.
  • FERC denied the legacy-cost exemption under section 206, finding no unjust or unreasonable allocation; FirstEnergy sought rehearing and then review in this court.
  • The court deferentially reviews FERC’s findings under the arbitrary-and-capricious standard and affirms that Schedule 12 was not unjust or unreasonable as applied to ATSI.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether FERC erred under § 206 by upholding Schedule 12 as just and reasonable for ATSI. FirstEnergy; argue cost causation and sunk costs invalid. FERC; Schedule 12 justified by ‘costs to serve’ and benefits to ATSI. No reversible error; Schedule 12 not unjust or unreasonable.
Whether FERC properly treated FirstEnergy’s § 206 complaint given prior 205 finding. Petitioner asserts improper dismissal and mechanistic reliance on earlier 205 finding. FERC addressed the complaint on the merits; not barred by prior 205 finding. FERC’s treatment not predicated on improper dismissal; merits review upheld.
Whether cost-causation and sunk-cost reallocations are permissible here. Reallocation of sunk costs is unjust under cost-causation principles. Cost-causation includes benefits to the customer; sunk costs may be socialized. Permissible under the Commission’s reasoning; not unjust or unreasonable.
Whether waiver or modification of tariff provisions was required or appropriate. FirstEnergy sought exemption; argues tariff could be modified or waived. Waiver for auction procedures distinguished from exemption for legacy costs; no basis to modify here. No modification or exemption; tariff controls were reasonable and not unjust.

Key Cases Cited

  • Ala. Power Co. v. FERC, 993 F.2d 1571 (D.C. Cir. 1993) (section 206 burdens and standard align with section 205 standard)
  • Sithe/Independence Power Partners, L.P. v. FERC, 165 F.3d 944 (D.C. Cir. 1999) (section 206 burden-shifting and just-and-reasonable standard)
  • Md. Pub. Serv. Comm’n v. FERC, 632 F.3d 1283 (D.C. Cir. 2011) (dual burdens under § 206 and § 205 clarified by circuit court)
  • Ill. Commerce Comm’n v. FERC, 576 F.3d 470 (7th Cir. 2009) (seventh circuit on Schedule 12 cost causation and commensurate benefits)
  • Boston Edison Co. v. FERC, 233 F.3d 60 (1st Cir. 2000) (context on justness and reasonableness of rates under FPA)
Read the full case

Case Details

Case Name: Firstenergy Service Co. v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 18, 2014
Citation: 411 U.S. App. D.C. 155
Docket Number: 12-1461
Court Abbreviation: D.C. Cir.