History
  • No items yet
midpage
FairwindCT, Inc. v. Connecticut Siting Council
99 A.3d 1038
Conn.
2014
Read the full case

Background

  • BNE Energy petitioned the Connecticut Siting Council (Council) for declaratory rulings to approve two projects (three 1.6 MW turbines each) in Colebrook without a certificate under §16-50k(a); plaintiffs FairwindCT and local residents intervened under §22a-19 and received party status.
  • The Council held hearings, approved both petitions with multiple conditions (stormwater/erosion plans, post-construction noise monitoring, development & management plan, lower hub height for one site), and relied in part on agency comment letters and some materials filed under seal.
  • Plaintiffs appealed to the trial court challenging Council jurisdiction, authority to impose conditions, treatment of state noise law, the Council’s hub-height decision and evidentiary procedure, and alleged deprivation of fundamental fairness.
  • The trial court dismissed the appeals; the Supreme Court reviewed de novo statutory interpretation issues and for substantial evidence on factual determinations.
  • The Supreme Court affirmed: (1) Council had jurisdiction because wind turbines are „electric generating facilities" within the siting statutes; (2) plaintiffs lacked standing to challenge conditions per se but could challenge whether the Council’s substantive approval was supported by substantial evidence; (3) Council could consider (but was not required to enforce) state noise regulations and could approve despite noncompliance with laws outside the siting act; (4) the hub‑height change and other procedural contested practices did not require reversal because Council findings were supported by substantial evidence and any procedural errors were harmless.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Council jurisdiction under §16-50k(a): are wind turbines "facilities" using "fuel"? Wind is not "fuel" so turbines are not "facilities" under §16-50i(a)(3); Council lacks jurisdiction. Definition should include any electric generating facility; statutory context and legislative history show turbines fall within Council jurisdiction. Held: turbines are "electric generating facilities" within §16-50i(a)(3); Council has jurisdiction.
Authority to impose conditions on declaratory rulings; standing to challenge conditions Conditions improperly allow post-approval compliance; plaintiffs challenge conditions and Council authority. Plaintiffs lack standing to challenge conditions themselves; Council may condition declaratory rulings similar to certificates. Held: plaintiffs lacked standing to attack conditions per se but had standing to argue approvals lacked substantial evidentiary support; Council properly made substantive findings and conditions were not a post hoc substitute for required findings.
Whether Council had to apply/enforce state noise regulations when approving petitions Council was required to measure at property lines per DEEP regs and required to enforce noise law; approval without such compliance is unlawful. Council may consider other state laws as it deems appropriate under §16-50x(a) but is not required to enforce them; it may approve despite noncompliance. Held: Council may consider state noise law but is not required to apply or enforce it when ruling on declaratory petitions; approval despite noncompliance is permissible.
Lowering hub heights; was decision supported by substantial evidence and properly admitted? Late introduction of hub‑height feasibility evidence prejudiced plaintiffs and shorter hubs increase property-line noise; decision not supported by record. Evidence (product literature, Jiminy Peak example, BNE testimony) supported feasibility and reduced visual impact; any late presentation was harmless. Held: Council’s decision to require 80 m hubs was supported by substantial evidence; any late evidence introduction was harmless because it would not likely change outcome.
Procedural fairness (cross-examination of DEEP analyst, cumulative impacts, sealed records, continuances) Council denied rights to cross-examine agency commenter, limited cumulative-impact proof, overbroad sealing and denied continuances, depriving fundamental fairness. Council exercised discretion under hearing rules; withheld testimony was peripheral; sealed materials and schedule balancing were justified; no harmful prejudice shown. Held: Even assuming some procedural errors, plaintiffs failed to show material prejudice; Council proceedings were fundamentally fair and any errors were harmless.

Key Cases Cited

  • Wheelabrator Lisbon, Inc. v. Department of Public Utility Control, 283 Conn. 672 (deference to agency statutory interpretations and limits)
  • Finley v. Inland Wetlands Commission, 289 Conn. 12 (conditions indicating lack of substantive compliance can show insufficient evidence)
  • Connecticut Coalition Against Millstone v. Connecticut Siting Council, 286 Conn. 57 (judicial review limited to substantial evidence and deference to agency fact‑finding)
  • Grimes v. Conservation Commission, 243 Conn. 266 (common-law right to fundamental fairness in administrative hearings)
Read the full case

Case Details

Case Name: FairwindCT, Inc. v. Connecticut Siting Council
Court Name: Supreme Court of Connecticut
Date Published: Sep 23, 2014
Citation: 99 A.3d 1038
Docket Number: SC19090, SC19091
Court Abbreviation: Conn.