History
  • No items yet
midpage
Fairfield County Board of Commissioners v. Nally
34 N.E.3d 873
Ohio
2015
Read the full case

Background

  • Fairfield County operates the Tussing Road wastewater-treatment plant discharging into Blacklick Creek and applied for renewal of its NPDES permit; Ohio EPA issued a renewed permit on June 30, 2006 that added a new phosphorus limit based on Ohio EPA’s Big Walnut Creek TMDL report.
  • The county challenged the phosphorus limitation, arguing Ohio EPA failed to follow Ohio Administrative Procedure Act (R.C. Chapter 119) rulemaking before adopting the TMDL and thus denied stakeholders a meaningful opportunity to be heard.
  • ERAC upheld Ohio EPA’s factual foundation for the limit but vacated the limit for failure to consider technological feasibility and economic reasonableness under R.C. 6111.03(J)(3).
  • The Tenth District affirmed ERAC on the factual foundation and treated the federally approved TMDL as effectively unassailable in the permitting context.
  • The Ohio Supreme Court held that a TMDL issued by Ohio EPA is a “rule” under R.C. 119.01(C) and therefore must be promulgated pursuant to R.C. Chapter 119 before submission to U.S. EPA or use as a basis for NPDES permit limits.
  • The court vacated the phosphorus limitation in the permit (for lack of an adopted rule) and remanded to Ohio EPA to proceed with required rulemaking procedures before implementation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a TMDL is a “rule” requiring promulgation under R.C. Chapter 119 TMDL sets numeric pollutant ceilings and allocates loads broadly, functioning as a general, uniform standard that must be promulgated TMDL is guidance/technical tool, not a binding rule; permit process provides adequate review TMDL is a rule (standard with general and uniform operation) and must be promulgated under R.C. Chapter 119 before use in permits
Whether federal approval of a TMDL substitutes for state rulemaking and insulates it from state procedural challenge County: federal approval does not cure Ohio EPA’s failure to follow state rulemaking; stakeholders need state-level notice and comment first Ohio EPA: U.S. EPA approval makes TMDL binding and sufficient to base permit limits on U.S. EPA approval does not replace R.C. Chapter 119; Ohio EPA must complete state rulemaking before submitting to U.S. EPA or applying TMDL in permits
Whether permitting-phase review (ERAC) provides adequate due process to challenge a TMDL County: permitting adjudication is not a substitute for full rulemaking; ERAC review limited if TMDL treated as essentially unreviewable Ohio EPA: permit-level challenges and ERAC review are sufficient to test TMDL application Court: Rulemaking protections (notice, comment, hearings) under R.C. Chapter 119 are required to provide meaningful opportunity to be heard; permit review alone is insufficient

Key Cases Cited

  • State ex rel. Saunders v. Industrial Commission, 101 Ohio St.3d 125 (2004) (effect of a document depends on whether it enlarges or interprets existing rules)
  • Northeast Ohio Regional Sewer District v. Shank, 58 Ohio St.3d 16 (1991) (rulemaking procedures protect full and fair analysis of proposed standards)
  • Condee v. Lindley, 12 Ohio St.3d 90 (1984) (agency policies that replace case-by-case analysis require rulemaking)
  • Jackson Cty. Environmental Committee v. Schregardus, 95 Ohio App.3d 527 (10th Dist. 1994) (agency guidelines with general effects are rules requiring promulgation)
  • Asarco, Inc. v. State of Idaho, 69 P.3d 139 (Idaho 2003) (TMDL-based permit limits invalid without promulgation)
  • Friends of the Earth, Inc. v. Environmental Protection Agency, 446 F.3d 140 (D.C. Cir. 2006) (TMDLs must be incorporated into permits following approval)
Read the full case

Case Details

Case Name: Fairfield County Board of Commissioners v. Nally
Court Name: Ohio Supreme Court
Date Published: Mar 24, 2015
Citation: 34 N.E.3d 873
Docket Number: No. 2013-1085
Court Abbreviation: Ohio