History
  • No items yet
midpage
F.R. Carroll, Inc. v. TD Bank, N.A.
2010 ME 115
| Me. | 2010
Read the full case

Background

  • Village Station executed two promissory notes in favor of the Bank in June 2005, secured by mortgages on Village Station property.
  • Bank provided a Cost Estimate totaling $1,037,210 for the project, but paving was not separately apportioned though plans depict a paved lot.
  • Bank disbursed funds between July 2005 and September 2006; requests for payment did not reference paving.
  • By September 26, 2006, photographs showed an unpaved parking lot; final disbursement occurred September 28, 2006.
  • On October 27, 2006, Village Station contracted F.R. Carroll to pave the lot for $26,405; Bank was unaware of the contract and post-disbursement paving expenses.
  • F.R. Carroll completed paving in late October 2006; no payment was received; Carroll filed a mechanic’s lien in February 2007; District Court granted Carroll summary judgment for lien priority based on Bank consent.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Bank consent can be established as a matter of law Carroll contends Bank had knowledge of the work and its extent and thus consented. Bank argues there was no contract or explicit consent to paving and no post-disbursement funds or knowledge of the contract. Consent could not be determined as a matter of law; factual disputes remain.
Whether Bank’s knowledge of paving supports consent to the paving work Carroll asserts Bank knew paving was planned and progress showed paving would occur. Bank contends knowledge of planning does not prove consent to a specific post-disbursement paving contract. Ambiguity remains; feasible inferences support either consent or no consent.
Whether Bank’s conduct justifies Carroll’s belief that consent existed Carroll argues Bank’s monitoring and updates implied consent to paving. Bank maintains it did not authorize or fund the paving after final disbursement and had no involvement with Carroll’s contract. Reasonable inferences are conflicting; cannot resolve as a pure question of law.
Standard of review for cross-motions for summary judgment Meant to determine if undisputed facts support Carroll’s priority lien. Same standard applies; factual disputes preclude summary judgment. Cross motions treated under de novo standard; genuine issues of material fact exist.

Key Cases Cited

  • Platz Assocs. v. Finley, 2009 ME 55 (Me. 2009) (consent requires knowledge and conduct implying consent)
  • Carey v. Boulette, 158 Me. 204 (Me. 1962) (consent depends on case-specific facts)
  • Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 151 Me. 145 (Me. 1955) (consent may be inferred from circumstances)
  • E. Corey Co. v. H.P. Cummings Constr. Co., 118 Me. 34 (Me. 1919) (facts determine whether consent is established)
  • Gagnon's Hardware & Furniture, Inc. v. Michaud, 1998 ME 265 (Me. 1998) (bank knowledge of planned conversion not sufficient for consent)
  • John W. Goodwin, Inc. v. Fox, 1999 ME 33 (Me. 1999) (liberal construction of lien statutes to protect equitable interests)
Read the full case

Case Details

Case Name: F.R. Carroll, Inc. v. TD Bank, N.A.
Court Name: Supreme Judicial Court of Maine
Date Published: Nov 9, 2010
Citation: 2010 ME 115
Docket Number: Docket: Yor-10-55
Court Abbreviation: Me.