These two cases, which for convenience will be referred to by number, arise out of bills in equity brought under the provisions of the Mechanics’ Lien Law, now R. S., 1954, Chap. 178, Sec. 34, et seq. The plaintiff is the same in both cases. Plaintiff furnished labor and material which went into the erection of a new school building. In case No. 2011 plaintiff acted as a sub-subcontractor and in case No. 2012 as a subcontractor. In case No. 2011 plaintiff attached to its bill in equity an account annexed (Exhibit “A”) in which appeared a detailed list of material and labor furnished, priced item by item. These items, totaled at $4470.02, were followed by three others, viz:
*147 ‘T21/2 % Tax & ins. $ 193.19
15% Overhead 670 50
10% Profit 447 00
5780.71”
In case No. 2012, Exhibit “A” set up only “Contract Price — $13,350.00” less certain credits. By amendment further credits were admitted leaving a claimed balance of $6790.00. There was admitted in evidence, however, a breakdown sheet which in similar fashion itemized labor and materials and then included as separate items:
“Insurance 10% of labor $ 501.98
Overhead 15% 1916 42
Profit 10% 1277 61”
It is not disputed that the itemized list of labor and materials represents the plaintiff’s actual cost for those items. The justice below disallowed as non-lienable all of the listed items for taxes, insurance, overhead and profit, and in addition in case No. 2011 disallowed an item: “Transportation —$78.00.”
The first issue therefore involves a determination as to the measure of the protection afforded by the lien security. We cannot discover that this question has ever been directly answered by this court.
At the outset, we have no hesitation in saying that such items as profit, overhead, taxes, insurance, and even transportation, as such and standing by themselves, are nonlienable. Our statute (supra) provides in part: “Whoever performs labor or furnishes labor or materials * * * in erecting * * * any public building * * * by virtue of a contract with or by consent of the owner, has a lien thereon and on the land on which it stands * * * to secure payment thereof, with costs.” Obviously such items as these are neither labor nor materials. But it does not follow that they can be completely and summarily disregarded in assessing the whole evidence as to just what the plaintiff has furnished.
*148
We think that there is a clear indication in the previous decisions and language of this court as to the way in which this issue must be resolved. The lien is dependent upon the existence of contract, express or implied, and the obligation of debt. The lien is incident and security to a legal liability to pay.
Cole
v.
Clark,
It is apparent that the learned justice below deemed that he was limited by law to the allowance of no more than plaintiff’s actual costs, regardless of the relationship between those costs and the fair and reasonable value of the labor and materials. He made no finding as to fair and reasonable value, although evidence was presented which, if believed, would have supported a finding of value in excess of those actual costs. The determination is primarily one of fact, and one which in such a case as this can best be made at the level where the witnesses are seen and heard. Such a determination can now be made in the light of the applicable law as here announced.
Still another factor arises in case No. 2012 in which plaintiff was subcontractor. The evidence indicates that the prime contractor submitted to the owner a list of his subcontractors and their bids, and that plaintiff and its bid were included. The owner reserved the right to approve or reject the proposed subcontractors and their bids. The owner, tacitly at least, accepted and approved plaintiff’s bid as representing the fair value of the labor and materials to be incorporated into its property, and this before plaintiff had begun work. In such a case we think that if the contract be fully and properly performed, the owner is estopped to assert that the fair value is less than the sum approved and agreed upon. The situation is not dissimilar to that which arises upon an express contract between owner and contractor fully performed.
We regard the item for transportation as in the same category as the items above discussed. In and of itself, it is non-lienable. If materials in place at the construction site have in fact a greater value because they have been transported there, the lien will reflect the enhanced value of the *151 material. Otherwise, transportation is not a factor to be considered.
Cases cited to us which construe lien laws other than the Mechanics’ Lien Law are not applicable to or decisive of the issues here. Defendants cite no case holding that actual costs are the measure of lien rather than fair and reasonable value.
The owner is not without protection. He may give the notice provided by R. S., 1954, Chap. 178, Sec. 35. He may insist upon a performance bond. He may control the payments to the prime contractor, or insist upon direct payments made by himself to the subcontractors. In the absence of any of these precautions, he cannot accept the enhancement of his property without submitting it to the lien security afforded by the statute.
The second issue which remains is whether or not the owner consented within the meaning of the lien statute to the furnishing of labor and materials by the plaintiff. In its prime contract the owner consented that others were expected to be employed as subcontractors and material men. The owner was thereby put upon notice.
Norton
v.
Clark,
For the reasons stated in the discussion of the first issue, the entry in each case must be,
Plaintiff’s appeal sustained with costs to plaintiff. Case remanded for further proceedings in accordance with this opinion.
