History
  • No items yet
midpage
Energy Northwest v. United States
2011 U.S. App. LEXIS 7055
| Fed. Cir. | 2011
Read the full case

Background

  • Energy Northwest entered into the NWPA-based Standard Contract with the United States to dispose of SNF, with the government agreeing to begin accepting SNF by 1998.
  • DOE later advised it could not begin accepting SNF until 2010, creating storage capacity pressures at Energy Northwest's Columbia plant.
  • Energy Northwest decided to build an ISFSI for indefinite storage and began a design/construction contract in 1999; ISFSI approval occurred in September 2002.
  • To implement the ISFSI, Energy Northwest incurred three cost categories: (i) site modifications (~$1M), (ii) indirect overhead costs (~$2.9M allocated to mitigation), and (iii) financing costs (~$6M).
  • Energy Northwest sued the government in 2004 for breach of contract; the Court of Federal Claims awarded damages in three categories and the government appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Causation standard for site modifications Yankee Atomic governs but-for causation. Carolina Power allows offset for avoided costs; but-for not required for all costs. Causation must be proven for modifications; but-for standard applies.
Allowance of indirect overhead damages Overhead attributable to mitigation is recoverable via reasonable allocation. Overhead needs direct causation proof linked to breach. Overhead damages affirmed; allocation based on labor time spent on mitigation is acceptable.
Recovery of interest costs Interest costs should be recoverable as part of mitigation financing. Sovereign immunity bars interest absent an express waiver (e.g., Changes clause). Interest recovery reversed; sovereign immunity bars such damages.
Procedural posture and standard of review Trial court properly applied Yankee Atomic and related precedent. Lower court misapplied causation standards. Remand for separate consideration of site-modification causation under Yankee Atomic.

Key Cases Cited

  • Yankee Atomic Electric Co. v. United States, 536 F.3d 1268 (Fed. Cir. 2008) (causation requires comparing but-for world with actual costs)
  • Carolina Power & Light Co. v. United States, 573 F.3d 1271 (Fed. Cir. 2009) (avoidance offsets require caution; future costs not presumed zero)
  • Ind. Mich. Power v. United States, 422 F.3d 1369 (Fed. Cir. 2005) (but-for causation and damages must be shown with reasonable certainty)
  • Bell v. United States, 404 F.2d 975 (Ct. Cl. 1968) (changes clause implies waiver of immunity for interest as equitable adjustment)
  • Wickham Contracting Co. v. Fischer, 12 F.3d 1574 (Fed. Cir. 1994) (interest may be recoverable in equitable-adjustment contexts with breach-related financing)
  • J.D. Hedin Constr. Co. v. United States, 456 F.2d 1315 (Ct. Cl. 1972) (sovereign immunity bars interest for breach absent waiver)
  • Contel Advanced Communications v. United States, 384 F.3d 1372 (Fed. Cir. 2004) (sovereign immunity limits interest recovery absent waiver)
  • Southern Nuclear Operating Co. v. United States, 637 F.3d 1297 (Fed. Cir. 2011) (offset analyses require moving evidence about avoided costs)
  • Bluebonnet Savings Bank v. United States, 266 F.3d 1348 (Fed. Cir. 2001) (non-EBA damages context; discussed in interest/waiver framework)
Read the full case

Case Details

Case Name: Energy Northwest v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Apr 7, 2011
Citation: 2011 U.S. App. LEXIS 7055
Docket Number: 2010-5112
Court Abbreviation: Fed. Cir.