*3 days after cutover. NEWMAN, DYK, Before LOURIE and Judges. Circuit dispute aspect here involves one relating contract to the implementation phase. issued, RFP Opinion for the court When the the Navy filed Circuit Judge Dissenting DYK. opinion quantities filed did not know the exact of cer- Judge Circuit PAULINE types NEWMAN. tain station/ancillary equipment In equipment approved January need. SDP. that it would This requested line item number to reduce the LTO listed under B007”). (“CLIN these in- to reflect overestimates. B007 Offerors were April May performed of 1992 prices unit for provide fixed structed equip- audit ascertain the amounts of under CLIN B007. The would items ment installed and submitted multiply prices by the unit its best then Navy, letter to the recommending that the quantity at a bid for estimate to arrive adjusted be downward $33.5 The RFP stated project. parties May million. The met in 1992 to rede- “total B007 shall be [CLIN] *4 modify price the LTO to but were unable equip- on of quantity termined based the agree to at that time. -modification . a¡ installed,” actually to the pursuant ment Thereafter, the a unilateral issued (J.A. 120.) Thus, the approved SDP. at that, among things, other modification equipment of included under amount the LTO price imple- stated for the B007 in the offer was to be original CLIN phase mentation at approximate- remained of adjusted to reflect actual amount the ly million. Cutover occurred $36.2 .on SDP, equipment according installed to the April system and acceptance oc- adjusted price the final to be and May curred on .1992. The of- accordingly. potential RFP asked quote prices implementa- the ferors to for to fund its expenditures during order under four methods of phase tion different implementation рhase, the CASI obtained (1) (2) straight lease purchase: purchase, corporation. a loan from its The parent (3) (“LTO”), option lease with ownership to upon full of this balance loan was due purchase, straight to lease. However, acceptance. system under the contract, project only begin CASI to would in CASI submitted ah offer accordance installment the im- payments receive for the RFP and the con- with was awarded system To plementation acceptance. after project September trаct for the in obligation repay parent corpora7 the to its imple- to opted purchase acceptance, system sought tion on CASI of phase mentation the contract at the third-party a under which it obtain loan $30,009,154.80 price paid of LTO be assign Navy’s pay- installment would monthly the LTO installments. Under Navy at ments to the lender. While Navy’s option, payments installment financing, no time CASI to obtain directed included an interest component. payments to make the third- refused prepared its initial SDP Janu- exactly unless party lender the invoices It was ary approved of 1991. ap- the official of price matched contract after, par- months later. a few Soon million. CASI conclud- proximately $36.2 price ties several modifications executed if it financing only that it could obtain ed price increased the LTO for tentative existing the full amount of the borrowed $36,223,371. implementation phase principal price. borrowed price This new tentative was based million, amount approximately $27 quantity estimates for several CLIN May equivalent price tо the 1992 contract parties that a recognized B007 items. The million, once inter- approximately $36.2 quantity number of these estimates were LTO term in. The est over the was added higher amount significantly than the actual million that was bor- approximately $27 under amount equipment principal would be installed rowed exceeded (“CO”) $2,121,106, equipment purchased under for explained which as it the SDP. The excess borrowed funds were represented additional interest costs it placed interest-bearing in an account. The suffered as a result of thе failure to deposited interest rate on the amount was price reconcile the LTO in 1992. In a final borrowing from far lower than cost decision dated March the CO third-party lender. denied this claim because there “was no agreement for any reimbursement of costs system acceptance, After be- incurred financing” gan monthly making payments of about a contractor “[h]ow finances its efforts ... $600,000(approximately one-sixtieth of the (J.A. is not the Government’s concern.” approximately official contract 248-249.) CO also blamеd the million) third-party to CASI’s lender. $36.2 finalizing the LTO on CASI’s fail- This continued until October 1996 when promptly provide ure to an “accurate ac- Navy finally issued a unilateral modifi- counting” of the equipment installed. reducing cation 248.) Further, the CO determined $32,351,679, a net decrease of approxi- *5 Navy actually overpaid that the had CASI, mately Curiously, million.1 $4.4 $279,464.32 repayment and demanded which Navy had earlier insisted that the in this amount. price, objected reduce the contract “that erroneous, the LTO reconciliation [ ] was later, Several months CASI submitted a Navy аuthority and the had no to unilater- second certified claim that asserted “alter- Contel, ally reduce the contract value.” (J.A. recovery.” native theories] slip op. at 22. At this time the had 251.) Specifically, argued made 52 installment payments. After price LTO adjusted should not have been making another payment installment downward because it was set at a fixed partial payment November and a in De- price million, of approximately re- $36.8 cember concluded gardless quantities of the of equipment had repaid adjusted the entire contract installed. urged CASI also it was making and ceased pay- installment entitled the “administrative costs” and Following Navy’s ments. refusal attorney’s fees it incurred as a result of pay remaining payments, installment Navy’s “wrongful pay- cessation of third-party payment demanded lender third-party ments” to the lender. from negotiated CASI. CASI pay- new 252-53.) Both of these theories were also lender, ment third-party schedule with the rejected, and appealed the denial of required which it to pay the lender an both certified claims to the ASBCA. $2,121,106, additional representing interest owed on the funds borrowed in excess of On June the ASBCA issued a the final price, less the interest decision in favor of CASI on its first certi- CASI earned deposit from the of these fied claim. The Board held that “the prior funds to the determination of the duty had a to reconcile price] [LTO no final contract price. system later than acceptance and its refus- 4, February
On al CASI submitted a without a valid excuse to do so was a certified claim to the contracting officer duty breach of its to coopеrate and a 1. The October 1996 proposed purchase modification decreased cation also a switch $6,978,825.08 $2,527,769.00. price by upgrade to account for for The net decrease $4,451,056.08. the overestimates to CLIN B007. The modifi- in LTO Contel, entitled to recover on its first certified slip op. at 26 contract.” breach claim, remanded to the omitted). the ASBCA CO (citations rejected Navy’s It quantum. a determination unresolved obsta- that “various arguments reconciling the it from prevented cles duplicative as The Board dismissed be- system acceptance,” price by LTO[] recovery presented alternative theories of i.e., “reconciliation,” it found that cause certified claim. It ex- CASI’s second upon the reduction of the that the second certified claim did plained installed, claims, merely “pres- present not new but equipment quantity measuring an alternate method ent[ed] based on accomplished have been “could supple- CASI’s claimed and that the SDP”' the information spe- certified claim to ment[ed] [first] the reconcili- eager complеte “CASI in- cifically identify allegedly certain costs ation.” Id. at 30. repairing curred in its financial relations n “no- further held that The Board making ... ceased when recovery on the rule” did bar payment called for sched- payments claim, represented certified which first ule.” at 24. Id. interest costs CASI suffered additional Navy" the ASBCA’s deci- appealed promptly failure a result certified claim. sion on CASI’s first We rec price. The ASBCA
reconcile the LTO jurisdiction to 28 pursuant have U.S.C. the “no-interest generally ognized 1295(a)(10). § on de recovery of interest rule” bars the *6 from money payments or defaulted layed DISCUSSION the rule can be but that legal conclusions of We review in a Gov by including provision “a waived the ASBCA without deference. Rumsfeld of in payment for the ernment Contract (Fed. 1328, Cos., F.3d 1334 Applied v. 325 cut, ‘affirmative, clear is] terest [that ”). Cir.2003) in Companies (“Applied ” Contel, op. at 27 slip unambiguous.’ of a contract the ASBCA terpretation Thayer-West v. (quoting United States that is reviewed without question of law Co., 107 329 Point Hotel U.S. appeal. on Metric Constructors deference 398, 521 91 L.Ed. Ct.Cl. 67 S.Ct. Admin., Space Aeronautics and v. Nat’l (1947)). Board, no^ According to the (Fed.Cir.1999). 751 169 F.3d in case had been waived this un accepted interest rule fact are findings of Board’s “fraudulent, arbitrary, or was an or payment they of interest less are “[t]he because as to grossly erroneous capricious, or so contract.” Id. part parties’ of the integral faith, if such deci necessarily or imply bad in by the intentional This was evidenced by substantial evi supported is not sion in the for interest” component of “a clusion Eng v. E.L. Hamm & Assocs. dence.” monthly payments. installment required (Fed.Cir.2004). land, F.3d 1338 ... payment of interest Because “the Id. itself, the by the contract” required was I rule did that the no-interest ASBCA held must, whether we recovery on first certified first determine CASI’s We bar hear this case. CASI jurisdiction have Having decided claim.2 $279,464.32 overpayments to CASI. from CO’s determi- ASBCAalso reversed the 2. The Navy was entitled to recover nation that the question argues contends that the decision the ASBCA the of entitlement. CASI because, quantum CO decided only it decided enti- was not final because claims, rejecting addition to CASI’s reach quantum. tlement and did not We CO determined thаt had over- disagree. $279,464.32.
paid
the amount of
However,
Navy’s overpayment
claim
1295(a)(10)
§
Although 28 U.S.C.
against
separate
from
CASI’s
decision,”
appeal
to an
from a “final
refers
damages against
Navy.3
claim for
Be-
repeatedly
our
held that
cases have
cause the CO determined that CASI was
concept
finality
in this context is a flexi
damages,
not entitled to
the CO never
concept.
DynCorp,
ble
Brownlee v.
determined the quantum required by
(Fed.Cir.2003)
(“Dyn-
F.3d
recognized
CASI’s claims. The ASBCA
”).
1295(a)(10),
Corp
Under section
“[t]he
scope
the limited
of the CO’s decision. It
determining
...
inquiry
finality
relevant
“[o]nly
stated that
entitlement
is before
contracting
scope
‘the
officer’s
the Board” and
parties
“remanded to the
decision, for this determines the extent of
Contel,
negotiate quantum.”
slip op. at
right
appeal
contractor’s
and the
Thus,
we conclude that
the ASBCA’s
”
jurisdiction.’
(quoting Dewey
board’s
Id.
decision was a “final
decision”
the issue
States,
Elecs.
Corp.
United
803 F.2d
jurisdiction
of entitlement. There is
under
(Fed.Cir.1986)).
650, 655
In eases where
1295(a)(10)
section
Navy’s ap-
hear the
contracting
yet
officer had not
reached
peal.4
thus,
quantum
only
issues of
entitle
Board,
ment
was before
we have re
II
peatedly found the Board’s decision on en
merits,
Navy argues
On
jurisdiction
titlement “final” and
our
within
seeking
that CASI is
damages
interest
1295(a)(10).
under section
See DynCorp.,
that are barred
the no-interest
rule.
1347;
Cos.,
Applied
F.3d at
325 F.3d The no-interest
rule bars the award of
3;
at 1333 n. Dewey,
In jurisdiction this we have 1295(a)(10) under section because the urges the no-interest rule scope of the CO’s decision was limited to not apply does because “[t]he interest challenge interest,” i.e., appeal The does not pay on eminent is liable to wheth- overpаyment. ASBCA's denial of its claim for anything er CASI (Reply can recover at all. 8.) Appellant Br. of at In its determination of reject argument 4. We also CASI’s that the properly entitlement the ASBCA reached this Navy’s appeal timely is not because it ad- question and decided it in CASI's favor. We only damages dresses issues and not entitle- jurisdiction Navy's appeal have to hear the appeal ment. The is not directed to the from that decision. Rather, quantum damages. "challenges holding the board’s that the Gov-
1379
456
on a
borrower
not recoverаble.”
F.2d at
is not interest
substantive
CASI seeks
claim,
plain
1330. The
noted that had the
money that the Gov-
court
cost of
but the
money
tiff “used
and so lost
his own
pay
order to defer
agreed
ernment
13.)
(Br.
might
interest which it
have earned for
at
Appellee
payment.”
him, the claim ...
not have
would
differed
an aspect
rule is
no-interest
in principle.”
(quoting Myerle,
Id.
33 Ct.
sovereign immunity.
basic
See
rule
25).
atCl.
Shaw,
315,
2957;
106
see
U.S. at
S.Ct.
478
too,
So
no-interest rule is appli
Principi,
Apache
207 Ct.Cl.
F.2d
(alteration
original)).
B
only
has
held
to bar the
rule
been
claims
recovery of interest on substantive
alternative,
CASI argues
see,
Smith,
e.g.,
rule has been waived
no-interest
but also interest costs
F.3d
Navy.
with the
by provision of its contract
money
bоrrowed
a result of
incurred
only by
The no-interest rule can be waived
government’s
or
in pay
breach
statute,
“specific provision by contract or
ment, see, e.g.,
Hedin Constr. Co. v.
J.D.
Shaw,
Congress.”
express
or
consent
*8
States,
782,
(internal
197 Ct.Cl.
456 F.2d
United
317,
at
2957
478 U.S.
106 S.Ct.
1315,
(1972);
Mfg.
see also Komatsu
omitted);
1330
quotation
alterations
see
States,
314,
132 Ct.Cl.
131
Co. United
Thayer-West Point
also United States v.
(1955);
949,
Ramsey
Co.,
950
v. Unit
F.Supp.
398,
67 S.Ct.
Hotel
329 U.S.
States,
”)
101 F.Supp.
ed
121 Ct.Cl.
(“Thayer-West
fund the provided second certified claim an “alter The ASBCA that “in- found theory recovery” not native that was that the amount reflect sist[ed] borrowed based on the additional amount of interest current contract аmount” and LTO[] lender, that owed the third-party CASI “CASI’s decision to as it proceed that did and therefore is not barred no- it [by borrowing money more than knew it (Br. 20.) Appellee interest rule. at Un a re- due] was was reasonable theory, argues der this alternative CASI Contel, sponse.” slip op. at 16. basis of the implementation the cost phase findings these clear. for is less than on price was awarded a fixed basis for explain Navy’s does how the insistence price LTO of approximately million. $36.8 rendering corresponding invoices fixed, Because the con May price compelled contract tends it is entitled to “the difference than money CASI to borrow more it knew the current between fixed LTO[ ] ultimately the con- paid would be under $36,802,685.08 paid and the amount date However, assuming that tract. even for implementation [the correct, findings Board’s were most the 252.) phase].” argument This Navy required only that CASI borrow fails for a number of reasons. equivalent May amount to the 1992 LTO First, both contract and the RFP if price, assign CASI elected to quantities make clear the estimated payments. sug- installment is no There equipment, upon CLIN B007 which gestion Navy required CASI to based, subject were financing, or otherwise instructed obtain change. project contract stated that: Indeed, money. borrow is an indefinite-quantity “[t]his *9 specifically Board Navy “[t]he found that or supplies specified services ... in the not money, did instruct to CASI borrow quantity Schedule. The of supplies and express any nor opinion as to whether or in specified the Schedule esti- any particular not CASI should services are enter into Contel, only purchased of mates and аre not financing agreement.” slip form this (J.A. 93.) Navy too, at 8. The op. fact that the was aware contract.” So RFP of the financing arrangement, appar- that made clear the LTO not reject a matter We also as price for was erroneous. that total “[t]he It recited fixed. theories as set of law CASI’s “alternative” be redetermined B007 shall [CLIN] certified claim. Ac- actually in- forth the second equipment of quantity the decision of the ASBCA is cordingly, the Govern- in accordance with stalled Plan.” Design Station ment-approved REVERSED. 120.) Morеover, clearly under- parties both COSTS not fixed. price was the LTO stood Navy repeatedly urged in fact CASI No costs. actual to reflect the
adjust the LTO Accord- equipment installed. quantity NEWMAN, Judge, Circuit PAULINE asked findings, CASI to the ASBCA’s ing dissenting. ap- adjust the LTO appeal the decision of did prior system million proximately $33.5 Ap- Board of Contract the Armed Services in a parties later met acceptance. The breached to peals that this contract was modify price to attempt to the LTO failed by the Board. Nor is the extent found under the installed equipment reflect (CASI) mon- suffered disputed that Contel in June and system acceptance After SDP. injury panel etary breach. urge continued to July of majority’s holding damages cannot be Contel, price. the LTO Navy to decrease they are measured assessed because slip op. at 19. money contrary to fundamen- the cost of reasons, we conclude For these relationships, of commercial principles tal implementation phase price for the scope of the “no-interest and outside the fixеd, to be was not but was project must, respectfully, I dissent. rule.” Thus quantity actual adjusted according to the with the between accordance re- therefore equipment installed. We CASI, provided and recovery” theory of ject this “alternative system, in- a telecommunications installed certified in CASI’s second presented for which esti- cluding equipment claim.5 at an quantity maximum esti- mated the $36,223,371. This estimate cost of mated CONCLUSION per cost the line item derived from B007) (CLIN Navy’s esti- times the unit applies rule that the no-interest We hold units; number of of the maximum matе claim for interest first certified to CASI’s indefi- of this parameters these were a result of the damages incurred as contract, validity of and the nite-quantity price to reflect reducing The con- dispute. adoption is not install- their equipment quantities the actual Navy in by the payment provided tract that there has we conclude ed. Because installments, to commence rule, monthly sixty no-interest no waiver of the been in- completed acceptance following was entitled decision ASBCA’s understood, con- and the It was stallation. certified claim under the first stated third-party the reasons lender. For “adminis- reject CASI’s claim for 5. We also above, payment was not Navy's the cessation stemming from the trative costs” *10 wrongful. “wrongful payments” to cessation of 1382 provides,
tract
the total cost would be
are
“interest” and therefore barred
on the number of units that were
proper
no-interest
rule. That
is not a
application
installed.
damages
of the rule. These
are not
interest on a claim
completion
Before
installation it
government, whereby
on а
interest
mone
recognized by
Navy
both
tary obligation of
government
is not
CASI that the actual cost would be several
available unless
authorized
statute or
million dollars
the stated maximum.1
below
agreed by contract. See Library
Con
Starting
January
requested
1992 CASI
Shaw,
gress
310, 317,
478 U.S.
106 S.Ct.
adjustment
a downward
of the contract
(1986)
2967,
(interest
ages be treated should the LTOP borrow-
identity as interest on Plan includ- Lease-to-Ownership
ing, the Board found: interest. The
ed a factor for option the LTOP
“The chose a 10% analysis based on value present offered the rate.” Thus CASI
