History
  • No items yet
midpage
04-19-00088-CV
Tex. App.
Oct 9, 2019
Read the full case

Background

  • ELG contracted Turn‑Key to add natural gas bullet storage tanks at the KDB Central Treatment Facility; Turn‑Key subcontracted Stranco to perform work.
  • Stranco sued Turn‑Key and ELG claiming, among other things, a mineral subcontractor’s lien against ELG’s property; after Turn‑Key’s bankruptcy Stranco’s claims against ELG were severed and Stranco moved for summary judgment to foreclose the lien.
  • Stranco’s summary judgment proof relied primarily on its owner’s affidavit claiming Stranco performed hydrostatic testing, torqueing, dewatering, drying, and furnished materials “in connection with constructing, repairing, or maintaining oil or gas pipelines and the pipeline terminal station.”
  • ELG submitted affidavits from a project manager and engineer stating the Facility was operational before the contract, the Turn‑Key scope was limited to adding bullet tanks inside the Facility, and the Facility’s import/export pipelines are segregated from Facility piping.
  • The court held Stranco was required to conclusively establish its labor and materials were “used in” statutorily defined mineral activities (per Adams) and found Stranco’s affidavit conclusory because it failed to show how the tank work was connected to oil/gas pipelines; summary judgment was reversed and the case remanded.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Stranco furnished materials/machinery/supplies "used in" mineral activities Stranco: materials and supplies supplied for the tank work were used in operating/completing/maintaining pipelines ELG: work was limited to adding tanks inside Facility; pipelines are segregated and not part of the Facility work Court: Stranco failed to conclusively show materials were "used in" mineral activities; summary judgment reversed
Whether Stranco performed labor "used in" mineral activities Stranco: performed hydrostatic testing, torqueing, dewatering, drying tied to pipeline-related activities ELG: the work was internal to the Facility and did not serve the segregated pipelines Court: owner’s affidavit was conclusory and did not establish the necessary link; Stranco did not meet its summary judgment burden
Whether proof that work was merely "related to" mineral activities suffices Stranco: statute should be liberally read; "related to" or "used in" are satisfied by tank work that serves pipelines ELG: statutory language requires work to be "used in" the listed mineral activities per statutory definitions Court: must show work was "used in" mineral activities (Adams); "related to" argument insufficient without facts proving the link
Whether Stranco was "under contract with a mineral contractor" as required Stranco: subcontract with Turn‑Key makes it a mineral subcontractor ELG: contested factual relationship and scope Court: did not reach this question because Stranco failed to prove the "used in" element

Key Cases Cited

  • Schlumberger Tech. Corp. v. Pasko, 544 S.W.3d 830 (Tex. 2018) (summary‑judgment de novo review; resolve doubts for nonmovant)
  • Adams v. Starside Custom Builders, LLC, 547 S.W.3d 890 (Tex. 2018) (courts must adhere to statutory definitions when applying mineral lien statute)
  • Gonzales v. Shing Wai Brass & Metal Wares Factory, Ltd., 190 S.W.3d 742 (Tex. App.—San Antonio 2005) (affidavits must state facts, not mere conclusions)
  • Lenoir v. Marino, 469 S.W.3d 669 (Tex. App.—Houston [1st Dist.] 2015) (conclusory affidavits lack probative force)
  • Wesco Distrib., Inc. v. Westport Group, Inc., 150 S.W.3d 553 (Tex. App.—Austin 2004) (liberal statutory construction cannot override statutory language)
Read the full case

Case Details

Case Name: ELG Oil, LLC and ELG Utility, LLC v. Stranco Services, LLC
Court Name: Court of Appeals of Texas
Date Published: Oct 9, 2019
Citation: 04-19-00088-CV
Docket Number: 04-19-00088-CV
Court Abbreviation: Tex. App.
Log In