OPINION
Appellant, Wesco Distribution, Inc., appeals the judgment of the district court of Bastrop County granting appellee West-port Group Inc.’s motion for summary judgment to remove a materialman’s lien and awarding Westport attorney’s fees in the amount of $16,140.77. Wesco raises two issues on appeal, asserting: (1) the district court misinterpreted the notice provisions of sections 53.003 and 53.056 of the property code, see Tex. Prop.Code Ann. §§ 53.003, .056 (West 2002); and (2) the district court abused its discretion in awarding Westport attorney’s fees. We affirm the judgment of the district court.
FACTUAL BACKGROUND
Westport, a general contractor, agreed to build a dental office for E & M Properties and hired J & D Electric as its electrical subcontractor for the project. J & D Electric agreed to provide all the labor and materials necessary to perform the subcontract work. J & D Electric purchased some of the materials used in the dental office from Wesco, but failed to fully pay Wesco for these materials. On July 11, 2001, Wesco attempted to send notice by mail to Westport of J & D Electric’s outstanding bill for materials purchased between March 2001 and June 25, 2001, in order to notify Westport of Wesco’s claim for a materialman’s hen on the property. The post office returned this notice to Wesco because Wesco failed to attach sufficient postage. Wesco added postage and again mailed its notice to Westport on July 25, 2001. On July 19, Westport, having received no notice of lien, made a payment to J & D Electric. Although it is unclear when notice was actually received, it is clear that no payments were made by Westport after receipt of notice. By the time it received notice, Westport had paid J & D Electric almost everything it was owed. Wesco filed an affidavit claiming a lien on September 13, 2001.
Westport filed suit to remove Wesco’s claimed lien, and Wesco filed suit for damages and foreclosure of its lien. The two lawsuits were consolidated. Westport filed a summary motion “to remove invalid or unenforceable lien” pursuant to section 53.160 of the property code, and Wesco opposed the motion. See id. § 53.160. The trial court initially denied Westport’s summary motion, but when the parties filed cross-motions for summary judgment, the trial court granted Westport’s request for summary judgment made on the same grounds as its earlier motion. Wesco then brought this appeal.
STANDARD OF REVIEW
Because the propriety of a summary judgment is a question of law, we review the trial court’s decision
de novo. Natividad v. Alexsis, Inc.,
DISCUSSION
Construction of the Notice Provision
In Wesco’s first issue, it argues that the trial court mistakenly interpreted the notice provisions contained in the ma-terialman’s lien statute 1 by finding that Wesco did not comply with its terms. The statute sets out deadlines for giving notice of unpaid balances owed by subcontractors to materialmen to the original contractor and the property owner and requires timely notice as a prerequisite for a valid lien claim. 2 For Wesco’s lien claim to be valid, Wesco must have effectively notified West-port by July 15 of any unpaid balance for materials delivered in May. 3 Because it attempted to send a notice on July 11, before the deadline, Wesco argues that it timely notified Westport under the statute. When that notice was returned to Wesco for insufficient postage, and the notice was re-sent on July 25, 2001, Westport argued that there was no timely notice of lien for nonpayment for supplies delivered to J & D Electric prior to the end of May.
Wesco contends that its deposit of the notice with insufficient postage substantially complies with the statutory requirements of section 53.003 of the property code because Westport eventually received a notice. Despite the insufficient postage, it argues, Wesco deposited the notice within the statutory time period, and the statute requires nothing more. Westport responds that notice mailed with insufficient postage does not comply with statutory requirements because “sending” notice by mail necessarily includes attaching sufficient postage. Because Wesco failed to timely notify Westport of its lien claim, Westport argues, the lien it claims is invalid. We agree.
This case calls for interpretation of the notice provisions of Texas’s mechanic’s and materialman’s lien statute.
See
Tex. Prop. Code Ann. §§ 53.003, .056. Statutory interpretation is a legal matter subject to
de novo
review.
Bragg v. Edwards Aquifer Auth.,
“The primary rule of statutory interpretation is to ascertain and give effect to the intent of the legislature.”
Southwestern Life Ins. Co. v. Montemayor,
Courts must also presume that the legislature intended a reasonable result.
Montemayor,
The materialman’s lien statute is liberally construed for the purpose of protecting laborers and materialmen.
Industrial Indem. Co. v. Zack Burkett Co.,
Wesco argues first that the statute does not require postage to be affixed in order for notice to be effective, and that the absence of the word “postage” in the statute indicates a legislative intent that postage not be required for mailed notice to be considered effective. It offers two other provisions of the property code for comparison. The first allows notice to debtors by certified mail to be considered complete when that notice is deposited with the United States post office, “postage prepaid and addressed to the debtor” at its last known address. Tex. Prop.Code Ann. § 51.002(e) (West 2002). The second considers notice by lessors to tenants delivered when deposited with the United States post office, “properly addressed with postage prepaid.” Id. § 59.043(b) (West 2002).
Section 53.003, in contrast, is silent on the proper address or prepayment of postage. It allows notice by certified or registered mail to be considered effective upon “deposit or mailing of the notice in the United States mail in the form required.” The previous two provisions do not include the phrase “in the form required,” perhaps because they specify the form required: correctly addressed and with postage prepaid. Section 53.003 permits use of certified or registered mail and recognizes compliance with whatever form the U.S. Postal Service requires. The Postal Service requires postage. 39 C.F.R. § 3030 *558 (2003). 4
Construing the statute to not require postage at all would produce absurd results. Here, the first attempt at notice would have been effective; there would be no need for Wesco to re-send the returned correspondence because the statute’s requirements for constructive notice would have already been met. According to that construction, “notice” that would never and could never arrive would nonetheless be considered effective against Westport.
In an attempt to temper this extreme result, Wesco asserts that its interpretation would indeed require some kind of notice. Because the statute should be liberally interpreted for the benefit of materi-almen, Wesco argues, its timely but postage-deficient notice should, combined with its postage-prepaid but untimely notice, qualify as substantial compliance with the statute. Wesco characterizes the return of its notice for insufficient postage as a delay in delivery by the Postal Service and argues that it substantially complied with the requirement that it mail its notice within the statutory time period because the initial mailing occurred on July 11, and the general purpose of the statute’s notice provision was achieved.
The liberal construction for which Wesco argues does not excuse failure to comply with the statutory requirement that the materialman provide “timely written notice.”
See Texas Constr. Assocs., Inc., v. Balli,
Because Wesco tried to mail its notice, it claims its efforts constitute substantial compliance with the statute. It is true that substantial compliance is sufficient to perfect a materialman’s lien.
First Nat’l Bank in Graham v. Sledge,
*559
However, “substantial compliance” is not a license to ignore statutory requirements.
See Conn, Sherrod, & Co. Inc. v. Tri-Electric Supply Co.,
The notice requirement, unlike the technical defects excused by substantial compliance, plays a critical role in achieving the purposes of this statute. The materialman’s lien statute is designed to protect contractors, subcontractors, and owners.
Cabintree, Inc. v. Schneider,
Neither the principles of statutory construction nor case law permit this interpretation because it does violence to the terms of the materialman’s hen statute by reading the notice provision
6
completely out of the statute.
See Kinnear,
Wesco draws comparisons between this case and
Don Hill Construction Company v. Dealers Electrical Supply Company,
Texas’s materialman’s lien statute strikes a balance between interests of materialmen and general contractors by imputing notice to contractors to whom notice has been properly mailed. This scheme mirrors the evidentiary presumption that a properly mailed notice is received at its destination. When a sender has done everything necessary for notice to arrive, notice is considered effective as to the intended recipient.
See Mosser v. Plano Three Venture,
In other contexts, Texas courts hold that mailing a notice requires proper postage. There has been a longstanding general rule that a mailed notice is only effective if it has been properly mailed, meaning properly addressed and bearing the correct amount of postage.
Johnson Serv. Co. v. Climate Control Contractors, Inc.,
The district court’s decision that Wesco’s lien is invalid because its attempt to timely notify Westport failed for lack of sufficient postage is consistent with the statute. The effort Wesco made did not satisfy the notice requirements mandated by the ma-terialman’s lien statute. We overrule the first issue.
*562 Attorney’s Pees
In Wesco’s second issue, it argues that the district court abused its discretion in awarding Westport the full amount of its attorney’s fees under section 53.156 of the property code. The award of attorney’s fees rests in the sound discretion of the district court and will not be reversed absent a clear showing of abuse of discretion.
Oake v. Collin County,
Wesco argues that the district court improperly awarded attorney’s fees because Westport incurred the majority of those fees after and because of the court’s error. The district court initially denied West-port’s summary motion to remove an invalid or unenforceable lien, but later granted Westport’s motion for partial summary judgment made on the same grounds: untimely notice because of insufficient postage. At the attorney’s fees hearing, the district court acknowledged that granting the first motion would have resulted in lower attorney’s fees. Wesco puts great emphasis on the court’s comment: “Some of this burden might need to be mine.”
Westport responds by identifying a variety of factors the district judge should consider in determining attorney’s fees, including the quality of legal work, the time and effort required, the nature and intricacies of the case, the extent and type of the attorney’s responsibilities, and any benefits from the litigation.
See Del Valle Indep. Sch. Dist. v. Lopez,
Obviously, disposing of any case earlier would result in lower attorney’s fees for all involved. Not all cases are resolved as efficiently as, in hindsight, they could have been. However, the touchstone of whether attorney’s fees can be awarded is whether they were reasonable and necessary at the time the party incurred them.
See Stewart Title Guar. Co. v. Sterling,
CONCLUSION
We hold that the district court did not err in granting summary judgment invalidating Wesco’s lien because Wesco failed to provide timely notice. The grant of attorney’s fees to Westport was not unrea *563 sonable, arbitrary, or made without reference to guiding principles. Accordingly, we affirm the district court on both points.
Notes
. "If notice is sent by registered or certified mail, deposit or mailing of the notice in the United States mail in the form required constitutes compliance with the notice requirement.” Tex. Prop.Code Ann. § 53.003 (West 2002).
. "A claimant other than an original contractor must give the notice prescribed by this section to be valid.” Tex. Prop.Code Ann. § 53.056(a) (West 2002).
“If the lien claim arises from a debt incurred by a subcontractor, the claimant must give to the original contractor written notice of the unpaid balance. The claimant must give the notice not later than the 15 th day of the second month following each month in which all or part of the claimant's labor was performed or material delivered....” Id. § 53.056(b) (West 2002).
. "Postage must be fully prepaid on all mail at the time of mailing, except as authorized by law or this Schedule. Except as authorized by law or this Schedule, mail deposited without prepayment of sufficient postage shall be delivered to the addressee subject to payment of deficient postage, returned to the sender, or otherwise disposed of as specified by the Postal Service. Mail deposited without any postage affixed will be returned to the sender without any attempt at delivery.” 39 C.F.R. § 3030 (2003).
. Here Wesco uses “notice” and "warning” interchangeably, but the warning is a portion of the notice to the owner that explains that personal liability might attach if the bill remains unpaid. See
Hunt Developers, Inc. v. Western Steel Co.,
. “If the lien claim arises from a debt incurred by a subcontractor, the claimant must give to the original contractor written notice of the unpaid balance. The claimant must give the notice not later than the 15 th day of the second month following each month in which all or part of the claimant's labor was performed or material delivered....” Tex. Prop.Code Ann. § 53.056(b).
. The
Don Hill
court held that, because the owner paid the general contractor after receiving the materialman's notice of lien, the funds it paid were trust funds held for the benefit of the materialman, and transfer of those funds did not change their character.
Don Hill Constr. Co. v. Dealers Elec. Supply Co.,
