History
  • No items yet
midpage
650 F. App'x 811
3rd Cir.
2016
Read the full case

Background

  • E & R Enterprise LLC bought property in Rehoboth Beach intending to build a house and an in-ground pool and submitted a building-permit application on Sept. 15, 2014.
  • Four days later the City adopted a proposed moratorium on unenclosed swimming-pool permits in the relevant zoning district; on Oct. 14 the City orally told E & R its permit was denied and would not accept additional information.
  • City officials held hearings and on Nov. 17 informed E & R they would take no further action on the moratorium or the permit application; E & R then sued in Delaware Court of Chancery and later amended to assert federal and state claims against the City and officials.
  • Defendants removed to federal court; they moved to dismiss for lack of subject-matter jurisdiction (ripeness) and failure to state a claim. The District Court dismissed most federal claims as unripe for failure to appeal to the Board of Adjustment (BOA), dismissed one federal substantive-due-process claim on the merits, remanded an equitable-estoppel claim to state court, and denied leave to amend.
  • The Third Circuit reviewed de novo, concluded all federal claims were unripe because E & R did not seek a final administrative decision from the BOA, vacated and remanded with instructions that the case be sent back to state court under 28 U.S.C. § 1447(c).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Ripeness of § 1983 procedural due process and equal protection claims E & R argued the permit denial was final and not appealable to BOA because City officials "hijacked" the process and rendered a non-appealable decision Defendants argued E & R failed to obtain a final administrative decision by not appealing to the BOA, so federal claims are unripe Court held claims unripe; BOA appeal was required and E & R’s factual allegations did not show the denial was unappealable
Ripeness of substantive due process claim under § 1983 E & R claimed ‘‘shock the conscience’’ conduct by City in delaying/denying the permit; said conduct made claim ripe despite lack of BOA appeal Defendants urged finality rule applies and BOA review is necessary before federal suit Court held substantive due process claim also unripe; Blanche Road exception inapplicable where claim rests on permit denial
Exception for harassment or independent injury (Blanche Road/County Concrete) E & R suggested City’s conduct created an independent, egregious injury making judicial review ripe without BOA appeal Defendants responded that alleged misconduct was part of the permit-denial process and not the kind of distinct harassment that excused finality Court held exception did not apply; alleged conduct did not resemble the extraordinary harassment in Blanche Road/County Concrete
Leave to amend after dismissal for lack of jurisdiction E & R sought leave to amend to cure deficiencies Defendants argued amendment would be futile because ripeness/jurisdictional bar remained Court held denying leave was not an abuse of discretion but instructed remand to state court because federal jurisdiction was lacking

Key Cases Cited

  • Williamson County Reg'l Planning Comm'n v. Hamilton Bank of Johnson City, 473 U.S. 172 (ripeness/finality rule for land-use § 1983 claims)
  • Lauderbaugh v. Hopewell Twp., 319 F.3d 568 (3d Cir. rule applying Williamson County to zoning cases)
  • Taylor Inv., Ltd. v. Upper Darby Twp., 983 F.2d 1285 (finality rule bars premature procedural due process claims)
  • Blanche Road Corp. v. Bensalem Twp., 57 F.3d 253 (limited exception where harassment made review ripe)
  • County Concrete Corp. v. Town of Roxbury, 442 F.3d 159 (application/clarification of Blanche Road exception)
  • Sameric Corp. of Del. v. Philadelphia, 142 F.3d 582 (declining Blanche Road exception where claims rest on permit denial)
  • Acierno v. Mitchell, 6 F.3d 970 (BOA has final authority to interpret zoning in permit-denial context)
  • Armstrong World Indus. v. Adams, 961 F.2d 405 (remand required where federal court lacks subject-matter jurisdiction)
  • Bromwell v. Michigan Mut. Ins. Co., 115 F.3d 208 (§ 1447(c) remand instruction where removal improper)
Read the full case

Case Details

Case Name: E & R Enterprise LLC v. City of Rehoboth Beach
Court Name: Court of Appeals for the Third Circuit
Date Published: Jun 1, 2016
Citations: 650 F. App'x 811; 15-3117
Docket Number: 15-3117
Court Abbreviation: 3rd Cir.
Log In
    E & R Enterprise LLC v. City of Rehoboth Beach, 650 F. App'x 811