History
  • No items yet
midpage
Devin B. Strickland v. Arch Insurance Company
17-10610
| 11th Cir. | Jan 9, 2018
Read the full case

Background

  • Strickland supplied sand to Douglas for a GDOT road project; Arch issued a payment bond for Douglas.
  • Douglas was removed for default in 2007; Arch completed the project via a third-party contractor; Strickland did not supply materials after Douglas’s removal.
  • Inspections: substantial completion noted in Aug 2010; punch-list work completed by Sept 2011; GDOT accepted maintenance responsibilities retroactive to Sept 2011 and paid semi-final funds to Arch in July 2012.
  • Strickland sent a bond demand in Sept 2012; he failed to produce requested documentation; he filed suit in Aug 2014 after being told GDOT was closing out the project.
  • GDOT issued a written “final acceptance” in Sept 2014 stating acceptance as of April 17, 2012; GDOT testimony explained a multi-year internal closeout and materials-certification process.
  • The district court granted summary judgment for Arch, concluding Strickland’s bond claims were barred by Georgia’s one-year statute of limitations; the Eleventh Circuit affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
When does the 1-year limitations period on a payment bond begin? Begins when GDOT issued its written final acceptance (2014). Begins at completion and acceptance of actual construction work (Sept 2011 or earlier). Court: Begins at completion of actual construction and acceptance by the public authority, not GDOT's later paperwork.
Was the project "completed" within meaning of statute? Not complete until all contractor maintenance/repair obligations ended with written final acceptance. Substantial completion (only punch-list items remaining) constitutes completion. Court: Substantial completion (punch-list remaining) is completion for statute purposes.
Did GDOT "accept" the work before written final acceptance? Email statements show no final acceptance in 2014, creating dispute. GDOT inspected, accepted for maintenance, and paid prior to 2012; written final acceptance was merely a later administrative step. Court: Acceptance refers to acceptance of actual work; GDOT accepted earlier despite delayed written final acceptance.
Does an unpaid supplier keep tolling the limitations period while the bond remains in effect? The bond remains in force until suppliers are paid; limitations should not run while unpaid. Interpreting statute that way would nullify the limitations period; limitations run from completion/acceptance, not payment. Court: Rejected tolling argument; statute runs from completion/acceptance, not from final payment or bond expiration.

Key Cases Cited

  • U.S.F. & G. Co. v. Rome Concrete Pipe Co., 353 S.E.2d 15 (Ga. 1987) (statute begins at completion and acceptance; rejects reliance on public authority internal procedures)
  • Masonry Specialists of Ga., Inc. v. U.S. Fid. & Guar. Co., 616 S.E.2d 103 (Ga. Ct. App. 2005) (substantial completion and acceptance suffice to start limitations period)
  • Augusta Iron & Steel Works, Inc. v. U.S. Fid. & Guar. Co., 790 F.2d 852 (11th Cir. 1986) (completion for statute does not equate to final payment)
  • Josendis v. Wall to Wall Residence Repairs, Inc., 662 F.3d 1292 (11th Cir. 2011) (summary judgment standard)
  • Mississippi Valley Title Ins. Co. v. Thompson, 802 F.3d 1248 (11th Cir. 2015) (de novo review of statute-of-limitations application)
Read the full case

Case Details

Case Name: Devin B. Strickland v. Arch Insurance Company
Court Name: Court of Appeals for the Eleventh Circuit
Date Published: Jan 9, 2018
Docket Number: 17-10610
Court Abbreviation: 11th Cir.