History
  • No items yet
midpage
45 F.4th 104
D.C. Cir.
2022
Read the full case

Background

  • Adelphia Gateway, LLC applied to FERC for a certificate to acquire existing interstate pipeline assets and to construct two short laterals (including a 0.3-mile "Parkway Lateral") and the Quakertown Compressor Station in PA; collectively the "Adelphia Gateway Project."
  • FERC prepared an Environmental Assessment (EA), concluded "no significant impact," but declined to quantify certain upstream impacts and some downstream greenhouse‑gas (GHG) emissions because end users/destinations were unidentified.
  • Adelphia had four precedent agreements covering ~76% of the Project capacity; FERC relied on those agreements to find market need.
  • Petitioners challenged FERC’s Certificate and Rehearing Orders on three main grounds: (1) inadequate NEPA review (upstream, downstream GHGs, climate impacts, cumulative effects, alternatives for Quakertown), (2) inadequate market‑need finding, and (3) unconstitutional preemption of state/local authority.
  • The D.C. Circuit reviewed under the APA arbitrary-and‑capricious standard and denied the petitions, finding FERC’s judgments reasonable and supported by the record.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
NEPA — upstream impacts (drilling) FERC should have considered foreseeable upstream impacts (new wells) caused by increased demand. Upstream drilling was not reasonably foreseeable; no record evidence could predict number/location of wells. Affirmed: FERC reasonably declined to analyze upstream drilling; Birckhead controls.
NEPA — downstream GHG emissions (general/full‑burn) FERC should have estimated downstream combustion emissions (full‑burn or industry average) for gas transported on the Project. FERC could not identify end users/destinations for some volumes, so downstream emissions were not reasonably foreseeable. Affirmed: FERC permissibly declined a categorical full‑burn estimate; court defers to agency technical judgment.
NEPA — Parkway Lateral & precedent‑agreement volumes FERC should at least quantify emissions for the new Parkway Lateral and other specified volumes. FERC sought data; applicant said no contracts/quantified capacity to specific end users, so quantification was not feasible. Affirmed: FERC reasonably concluded it could not reliably quantify those emissions.
NEPA — Social Cost of Carbon / climate impacts FERC was required to use Social Cost of Carbon or similar methodology to evaluate climate impacts. FERC found no scientifically accepted methodology to link emissions to discrete environmental effects and rejected SCC in EA context; petitioners failed to raise the specific regulatory argument on rehearing. Court: mostly non‑reviewable for lack of preservation; where reviewed, FERC’s refusal to apply SCC in this EA was reasonable or barred by forfeiture.
NEPA — segmentation/cumulative effects (PennEast) FERC improperly segmented NEPA by not treating PennEast as connected/cumulative. PennEast is defunct; even if error, its vacatur rendered any error harmless (no cumulative impact now). Affirmed: any segmentation issue is harmless because PennEast was abandoned.
NEPA — Quakertown compressor alternatives & impacts FERC failed to adequately analyze alternative sites, safety, noise, air quality, and impacts to historic/farmland resources. FERC addressed site size, safety standards, mitigation, noise and air impacts, and explained tradeoffs (e.g., added compression/emissions at alternatives). Affirmed: FERC took the required "hard look"; EA was adequate and EIS not required.
Market‑need under NGA (reliance on precedent agreements) Precedent agreements alone were insufficient; other evidence showed overbuilding and lack of need; Spire STL and new policy guidance undermine reliance on precedent contracts. Precedent agreements are strong evidence of market need, especially here (four different shippers, open season, large share of capacity); new policy does not apply retroactively. Affirmed: FERC reasonably relied on precedent agreements; Spire STL is distinguishable and Updated Policy Statement not retroactive.
Constitutional preemption of state/local authority FERC’s interpretation of NGA unlawfully preempts state/local health/safety protections under 5th/9th/10th Amendments. Petitioners failed to raise constitutional objections to FERC on rehearing; exhaustion required. Dismissed for forfeiture: constitutional claim not exhausted before the agency; court will not consider it.

Key Cases Cited

  • Minisink Residents for Env't Pres. & Safety v. FERC, 762 F.3d 97 (D.C. Cir. 2014) (APA/NEPA standard and role of precedent agreements in need analysis)
  • Myersville Citizens for a Rural Cmty. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (NEPA EIS/EA standards)
  • Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017) (Sabal Trail) (downstream emissions foreseeability analysis)
  • Birckhead v. FERC, 925 F.3d 510 (D.C. Cir. 2019) (limits on when downstream and upstream impacts are reasonably foreseeable)
  • EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016) (agency need to identify feasible methods to quantify impacts)
  • Del. Riverkeeper Network v. FERC, 753 F.3d 1304 (D.C. Cir. 2014) (deference to agency technical expertise; segmentation principles)
  • Environmental Defense Fund v. FERC, 2 F.4th 953 (D.C. Cir. 2021) (Spire STL) (circumstances where single/affiliated precedent agreement insufficient)
  • Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council, 462 U.S. 87 (1983) (standard for judicial review of agency NEPA determinations)
Read the full case

Case Details

Case Name: Delaware Riverkeeper Network v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Aug 2, 2022
Citations: 45 F.4th 104; 20-1206
Docket Number: 20-1206
Court Abbreviation: D.C. Cir.
Log In
    Delaware Riverkeeper Network v. FERC, 45 F.4th 104