D2 Excavating, Incorporated v. Thompson Thrift Con
19-40745
5th Cir.Sep 2, 2020Background
- Thompson Thrift was GC for an apartment project; D2 Excavating was hired as subcontractor for site grading/excavation for $630,000.
- Contract incorporated Thompson’s standard terms, including D2’s representation that it had inspected the site and would not seek price adjustments for failing to do so; contract described the site as a “balanced site.”
- D2 used Thompson’s topo survey and software modelling to conclude the site was balanced; after work began, excavation produced substantially more spoil requiring off‑site export.
- Thompson orally promised to pay for the unanticipated exporting and to issue a written change order after work was complete, but never issued a change order or paid; D2 stopped work at 98.6% completion and sued.
- The district court awarded D2 $81,068 for unpaid contract work, $257,588.53 for excess excavation, interest under the Texas prompt‑pay statute, and attorneys’ fees; the Fifth Circuit reviewed contract interpretation and equitable‑remedy issues.
Issues
| Issue | Plaintiff's Argument (D2) | Defendant's Argument (Thompson) | Held |
|---|---|---|---|
| Whether D2 can recover beyond the contract price for removal of unanticipated excess soil | D2 argues Thompson should pay extra because site was not balanced and Thompson promised to pay for export work | Thompson argues the contract placed on D2 the risk of site conditions and fixed the price | Court: Vacated/excluded excess‑soil breach‑of‑contract award—contract placed the risk on D2, so no extra contract recovery |
| Whether oral promise/change order to pay for exporting was enforceable (consideration) | D2 contends Thompson’s oral promise to pay after work created a contract modification | Thompson contends no valid modification occurred—no new consideration and it never issued a written change order | Court: Oral change order invalid for lack of new consideration (D2 was already contractually obligated to perform the work) |
| Whether quantum meruit allows recovery for the excess excavation | D2 seeks quasi‑contract recovery for work allegedly outside the contract | Thompson argues work was within contract scope so equitable recovery is barred | Court: Quantum meruit unavailable because work fell within the contract and D2 substantially performed; equitable recovery cannot exceed contract price |
| Whether D2 breached and whether Thompson’s counterclaim offsets unpaid sum; applicability of prompt‑pay interest and lien remedies | D2 argues its cessation was excused by Thompson’s mismanagement and prior breach; seeks unpaid contract balance plus prompt‑pay remedies | Thompson argues D2 breached by stopping work and owes completion costs | Court: Affirmed $81,068 award to D2; district court’s finding that Thompson’s mismanagement excused D2’s stoppage was not clearly erroneous; prompt‑pay interest and lien relief remain for the affirmed contractual recovery |
Key Cases Cited
- Lyda Swinerton Builders, Inc. v. Okla. Sur. Co., 903 F.3d 435 (5th Cir. 2018) (standard of review for mixed fact‑law issues and contract interpretation)
- Interstate Contracting Corp. v. City of Dallas, 407 F.3d 708 (5th Cir. 2005) (contractor bears risk only if contract shifts it to owner; plans/specs can allocate risk)
- El Paso Field Servs., L.P. v. MasTec N. Am., Inc., 389 S.W.3d 802 (Tex. 2012) (party who contracts to do work for a fixed price generally cannot claim extra for unforeseen difficulties)
- Dall./Fort Worth Int’l Airport Bd. v. INET Airport Sys., Inc., 819 F.3d 245 (5th Cir. 2016) (need for clear contractual allocation of risk and mutual assent for change orders)
- Lonergan v. San Antonio Loan & Tr. Co., 104 S.W. 1061 (Tex. 1907) (default rule: performing party bears risk of greater difficulty unless contract shifts risk)
- Black Lake Pipe Line Co. v. Union Constr. Co., 538 S.W.2d 80 (Tex. 1976) (quantum meruit limited to services not covered by contract)
- Murray v. Crest Constr., Inc., 900 S.W.2d 342 (Tex. 1995) (partial performance exception allowing quasi‑contract recovery when contractor cannot recover under an express contract)
- Heldenfels Bros., Inc. v. City of Corpus Christi, 832 S.W.2d 39 (Tex. 1992) (quantum meruit is an implied promise to pay for benefits conferred)
