History
  • No items yet
midpage
Crest Condominium Association v. Royal Plus, Inc.
S16C-10-025 RFS
| Del. Super. Ct. | Dec 7, 2017
Read the full case

Background

  • The Crest Condominium Association and unit owner Judith Jeffcott sued contractors and subcontractors after water intrusion and structural balcony failures were discovered following 2010 fire repairs and subsequent reconstruction work.
  • The Association hired Royal Plus to oversee repairs; MAD Engineering prepared reconstruction plans after broader structural problems were found. Coldiron and Shore were subcontractors on the balcony work.
  • MAD notified the Association in January and August 2012 about nonconforming fascia and potential tile-related water infiltration; Coldiron reworked balconies and told the Association in May 2012 the problem was fixed.
  • Home Inspection Technologies investigated in November 2014 and issued a report in November 2015 documenting extensive defects, water damage, rot, and mold; plaintiffs have spent about $187,250 in repairs.
  • Defendants moved for summary judgment arguing the three-year statute of limitations for property damage claims accrued in 2012 (latest August 28, 2012) and the 2016 complaint was time-barred; Royal Plus also argued no contract/duty existed for the balcony work.
  • Plaintiffs argued tolling via inherently unknowable injury and fraudulent concealment (reliance on Coldiron’s assurances and alleged misleading acts), plus that discovery was incomplete; the court deferred summary judgment pending discovery because genuine factual disputes remain.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
When did the statute of limitations accrue? Accrual tolled until discovery/inquiry notice (earliest Nov 7, 2014); May/2012 representations kept plaintiffs ignorant. Accrual occurred by May 6, 2012 (repairs completed) or at latest Aug 28, 2012 (MAD letter); complaint filed too late. Court found factual disputes about accrual/tolling; could not decide on summary judgment.
Application of inherently unknowable injury doctrine Injury was not observable after Coldiron said repairs were fixed; plaintiffs blamelessly relied on contractor/expert. Plaintiffs had access to inspections, letters, and knew enough to investigate in 2012; objectively discoverable signs existed. Court held triable factual questions exist whether plaintiffs were blamelessly ignorant; denied summary resolution.
Fraudulent concealment tolling Coldiron made affirmative misrepresentations and repairs, which delayed discovery and tolled limitations. No concealment: work was supervised by MAD; any alleged concealment would be by MAD, and plaintiffs still had letters prompting inquiry. Court found factual disputes on concealment sufficient to preclude summary judgment.
Sufficiency of claim against Royal Plus (duty/contract) Royal Plus supervised/oversaw balcony reconstruction (on-site supervisor, submitted proposals, coordinated inspections) creating duty and possible liability. Royal Plus only supervised initial fire remediation; no contract for balconies beyond limited acts (e.g., unlocking door). Court concluded factual issues about Royal Plus’s role exist and are not resolvable on summary judgment.

Key Cases Cited

  • Wal-Mart Stores, Inc. v. AIG Life Ins. Co., 860 A.2d 312 (Del. 2004) (Delaware accrual rule: cause of action accrues at time of wrongful act even if plaintiff is ignorant)
  • Moore v. Sizemore, 405 A.2d 679 (Del. 1979) (summary judgment standard and movant’s initial burden)
  • Merrill v. Crothall-American, Inc., 606 A.2d 96 (Del. 1992) (burden shifts to nonmoving party once movant meets initial showing)
  • Ebersole v. Lowengrub, 180 A.2d 467 (Del. 1962) (summary judgment refusal where material facts are disputed or further inquiry is desirable)
Read the full case

Case Details

Case Name: Crest Condominium Association v. Royal Plus, Inc.
Court Name: Superior Court of Delaware
Date Published: Dec 7, 2017
Docket Number: S16C-10-025 RFS
Court Abbreviation: Del. Super. Ct.