History
  • No items yet
midpage
157 Conn.App. 139
Conn. App. Ct.
2015
Read the full case

Background

  • Coppola Construction contracted (through Signature Construction Services as agent) to perform site work and parking-lot construction for Hoffman Enterprises; the written contract set a $400,000 initial scope with provisions for written change orders and time/material pricing plus 20% fee when lump-sum pricing was not agreed.
  • Signature’s agent, Saunders, issued six written change orders and authorized additional extra work (some without written change orders); Coppola completed most work and received $780,950 total from Hoffman by mid-November 2009 but still owed subcontractors ~$455,500.
  • After Coppola’s counsel demanded payment (Nov. 17, 2009) and Coppola suspended work, Hoffman met with Coppola’s main subcontractor, Massey, then hired Massey to finish the job; Coppola did not return to work.
  • Coppola filed a $1.4 million mechanic’s lien and sued Hoffman for breach of contract, quantum meruit, unjust enrichment, tortious interference, and CUTPA violations; Hoffman counterclaimed for breach of implied covenant, fraud, aiding and abetting, and CUTPA.
  • Trial court found an enforceable contract, concluded the parties’ relationship effectively terminated (described as a "de facto" termination without proper notice), awarded Coppola damages on breach and unjust enrichment but reduced them by setoffs and awarded Hoffman damages and fees on counterclaims for abuse of process/CUTPA related to an excessive mechanic’s lien.

Issues

Issue Coppola's Argument Hoffman’s Argument Held
Whether court erred by treating dispute as contract termination for convenience (and applying that measure of damages) rather than as defendant breach/repudiation allowing expectation damages Court should have treated Hoffman's conduct as breach/repudiation; Coppola entitled to expectation damages including lost profits Court characterized the situation as a "de facto" termination with shared fault; measured damages under termination-for-convenience formula Appellate court held the trial court improperly characterized the action as a termination; Hoffman breached by effectively terminating without required notice — remanded for limited damages hearing to compute expectation damages for original contract work
Proper valuation and setoff for sixth change order (paving) Coppola argued it had no further claim for the $39,000 balance but was entitled to keep the $150,000 paid for upper lot Hoffman argued it overpaid Coppola and sought setoff based on subcontractor costs Court miscalculated setoff; on remand appellate court directed reduction of Hoffman's setoff (defendant overpaid by $9,897 rather than $29,455.80) and concluded no additional compensatory damages for Coppola on that change order
Whether Saunders’ oral approvals (agent) bound Hoffman for extra work not in writing Coppola: Saunders (construction manager/agent) orally authorized extra work; Hoffman is bound despite integration/ written-change requirement Hoffman: written-change requirement controls; no waiver Issue inadequately briefed by Coppola on appeal — appellate court declined to review (claim deemed abandoned)
Whether filing an excessive mechanic’s lien supported Hoffman’s counterclaims (abuse of process, CUTPA, breach of implied covenant) Coppola: mechanic’s lien statutes protect lienors; overstating amount alone insufficient for abuse of process/CUTPA; remedies are statutory reduction/bond Hoffman: Coppola knowingly filed a manifestly excessive lien to pressure payment; incurred ascertainable losses defending it Appellate court affirmed trial court: record supported findings that Coppola knowingly filed an excessive lien primarily to coerce payment; Hoffman proved ascertainable loss — awards for costs and CUTPA fees upheld

Key Cases Cited

  • United Technologies Corp. v. Groppo, 238 Conn. 761 (Connecticut Supreme Court) (standard of appellate review for mixed fact–law issues)
  • Argentinis v. Gould, 219 Conn. 151 (Connecticut Supreme Court) (substantial performance doctrine and damages for contractor)
  • Naples v. Keystone Building & Development Corp., 295 Conn. 214 (Connecticut Supreme Court) (plaintiff’s burden to prove damages with a fair and reasonable estimate)
  • Silliman Co. v. S. Ippolito & Sons, Inc., 1 Conn. App. 72 (Connecticut Appellate Court) (failure to make progress payments can be a material breach in construction contracts)
  • Suffield Development Associates Ltd. Partnership v. National Loan Investors, L.P., 260 Conn. 766 (Connecticut Supreme Court) (elements and gravamen of abuse of process)
Read the full case

Case Details

Case Name: Coppola Construction Co. v. Hoffman Enterprises Ltd. Partnership
Court Name: Connecticut Appellate Court
Date Published: May 12, 2015
Citations: 157 Conn.App. 139; 117 A.3d 876; AC35503
Docket Number: AC35503
Court Abbreviation: Conn. App. Ct.
Log In
    Coppola Construction Co. v. Hoffman Enterprises Ltd. Partnership, 157 Conn.App. 139