History
  • No items yet
midpage
Claude Mayo Construction Company, Inc. v. United States
128 Fed. Cl. 616
| Fed. Cl. | 2016
Read the full case

Background

  • GSA awarded Claude Mayo Construction a $732,003 renovation contract for a federal office in Syracuse; work began after a Final Notice to Proceed in November 2013 and the contract was later modified and increased to $811,046.
  • Disputes arose over schedules, responses to modification requests (PS02/PS03), and completion timing; GSA issued a Notice to Cure, a Show Cause notice, a Stop Work Order, and ultimately assessed liquidated damages.
  • GSA issued a Notice of Termination for Default on June 12, 2014, stating the CO’s letter was the final decision and advising the contractor of appeal rights under the Disputes clause/CDA.
  • Claude Mayo appealed the termination to the CO on May 18, 2015; the CO denied relief on July 22, 2015 (final decision), and Claude Mayo sued in the Court of Federal Claims on October 27, 2015 alleging: (1) improper default termination; (2) breach of contract; (3) tortious interference with other contracts; and (4) unjust enrichment.
  • Government moved to dismiss counts 2–4 for lack of subject-matter jurisdiction, arguing Claude Mayo failed to present a proper CDA claim to the CO (no claim for breach in writing with a sum certain) and that counts 3 and 4 lie outside Tucker Act jurisdiction; Claude Mayo did not oppose dismissal of counts 3 and 4 and submitted a supplemental claim to the CO while this litigation was pending.
  • The Court granted the government’s motion: dismissed counts 2–4 without prejudice for lack of jurisdiction, and stayed Count 1 for 60 days to allow the CO to decide Claude Mayo’s supplemental claim.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Court has jurisdiction over Claude Mayo’s breach-of-contract claim under the Tucker Act/CDA (i.e., did Claude Mayo present a valid claim to the CO) May 18, 2015 appeal letter gave the CO adequate notice and requested payment for outstanding applications and lost profits; thus it presented a CDA claim May 18 letter was only an appeal of termination for default, did not assert breach as the basis, and did not state a sum certain required by the CDA Held: No. The May 18 letter did not present a written CDA claim for breach with a sum certain; Court lacks jurisdiction over count 2 (dismissed without prejudice)
Whether the Court has jurisdiction over the tortious-interference claim Tortious-interference arises from GSA’s improper termination and is part of contractor’s relief Tort claims are outside Tucker Act jurisdiction Held: No jurisdiction; count 3 dismissed (plaintiff did not oppose dismissal)
Whether the Court has jurisdiction over the unjust-enrichment claim (implied-in-law) Equitable relief/quantum for services rendered supports recovery against the government Unjust-enrichment is an implied-in-law claim and not within the Tucker Act waiver (only express or implied-in-fact contracts) Held: No jurisdiction; count 4 dismissed (plaintiff did not oppose dismissal)
Whether the case should be stayed to permit the CO to rule on a supplemental claim submitted while the lawsuit was pending If the Court finds the May 18 letter insufficient, permit the CO to issue a final decision on the April 25, 2016 supplemental claim so plaintiff can exhaust remedies Stay will allow exhaustion and preserve plaintiff’s ability to seek relief in this Court later Held: Stay granted for 60 days to allow CO decision on the supplemental claim; parties to file a joint status report thereafter

Key Cases Cited

  • Trusted Integration, Inc. v. United States, 659 F.3d 1159 (Fed. Cir. 2011) (pleading and jurisdictional standard in Rule 12(b)(1) context)
  • Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573 (Fed. Cir. 1993) (court may consider evidence extrinsic to the pleadings when jurisdiction is disputed)
  • Brandt v. United States, 710 F.3d 1369 (Fed. Cir. 2013) (plaintiff bears burden to establish subject-matter jurisdiction by preponderance)
  • England v. The Swanson Grp., Inc., 353 F.3d 1375 (Fed. Cir. 2004) (CDA exhaustion required for appeals of CO decisions)
  • M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010) (both a valid claim and a CO final decision are prerequisites to jurisdiction)
  • Keene Corp. v. United States, 508 U.S. 200 (1993) (Tucker Act excludes tort claims)
  • Lumbermens Mut. Cas. Co. v. United States, 654 F.3d 1305 (Fed. Cir. 2011) (Tucker Act covers express and implied-in-fact contracts but not implied-in-law/unjust enrichment)
  • Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586 (Fed. Cir. 1987) (claim must give CO adequate notice of basis and amount)
Read the full case

Case Details

Case Name: Claude Mayo Construction Company, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Oct 6, 2016
Citation: 128 Fed. Cl. 616
Docket Number: 15-1263C
Court Abbreviation: Fed. Cl.