City of Riverview v. Prudential Security Inc
353950
| Mich. Ct. App. | Jul 15, 2021Background
- Prudential Security had provided landfill security for Riverview since 2011 and in 2014 entered a three-year contract (extended by addendum in 2017 through July 2020) to provide uniformed guards and an all-terrain vehicle to perform hourly perimeter rounds on unpaved gravel/dirt roads.
- Prudential had previously noted rising vehicle-maintenance costs but did not seek a contract price change in the 2017 extension; the only negotiated change was a minimum-wage-based hourly-rate escalation clause.
- After the extension, Prudential repeatedly requested higher contract payments to cover vehicle costs; Riverview denied those requests. Prudential continued performance but terminated service effective January 18, 2019.
- Riverview hired Slater on a 180-day emergency contract, then awarded Slater the subsequent three-year contract; Riverview sued Prudential for breach seeking $48,423.48 (the excess Riverview paid Slater over Prudential’s contract rate).
- At summary disposition the trial court ruled for Riverview: (1) impossibility/impracticability and an implied condition precedent to maintain roads did not excuse Prudential’s performance; and (2) Riverview reasonably mitigated damages by selecting Slater. This appeal was affirmed.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether impossibility or impracticability discharged Prudential’s duty | Prudential could still perform; site conditions were foreseeable and did not excuse performance. | Road conditions made performance impracticable or impossible due to excessive vehicle damage/costs. | Held for plaintiff: road conditions were foreseeable; performance was not impracticable or impossible. |
| Whether an implied condition precedent (Riverview maintaining roads) excused Prudential’s duty | No implied condition; Riverview maintained roads reasonably and logs show rounds were completed. | Contract required Riverview to keep roads in suitable condition; failure discharged Prudential. | Held for plaintiff: no evidence Riverview breached any implied condition; performance obligation arose. |
| Whether Riverview failed to mitigate damages by not choosing the cheapest replacement | Riverview reasonably selected Slater based on prior emergency performance and total cost. | Other bidders submitted lower hourly bids and Riverview should have chosen them to minimize damages. | Held for plaintiff: Riverview’s selection was reasonable (comparing total fees and service suitability); mitigation defense fails. |
Key Cases Cited
- Roberts v Farmers Ins Exch, 275 Mich App 58 (2007) (impossibility/impracticability discharges require unforeseeable, extreme difficulty or expense).
- Rogers Plaza, Inc. v SS Kresge Co, 32 Mich App 724 (1971) (foreseeability relevant to impossibility defenses).
- Archambo v Lawyers Title Ins Corp, 466 Mich 402 (2002) (definition and effect of a condition precedent).
- Berkel & Co Contractors v?, 210 Mich App 416 (1995) (failure of a condition precedent precludes performance claim).
- Morris v Clawson Tank Co, 459 Mich 256 (1998) (duty to mitigate damages and burden on defendant to prove failure to mitigate).
- 1300 LaFayette East Coop, Inc. v Savoy, 284 Mich App 522 (2009) (summary-disposition review of factual issues when reasonable minds cannot differ).
- Pontiac Police & Fire Retiree Prefunded Group Health & Ins Trust Bd of Trustees v City of Pontiac, 309 Mich App 611 (2015) (de novo review standard for summary disposition).
- West v Gen Motors Corp, 469 Mich 177 (2003) (standard for MCR 2.116(C)(10) summary disposition).
- Nuculovic v Hill, 287 Mich App 58 (2010) (when to apply C(10) standard where parties rely on evidence beyond pleadings).
