Berkel & Co. Contractors v. Christman Co.Berkel & Co. Contractors v. Christman Co.
Berkel & Company Contractors appeals as of right from a judgment in the Washtenaw Circuit Court that held that Berkel, a subcontractor, was not entitled to payment for construction work until the general contractor was paid for that work by the owner. We affirm.
In October 1989, Christman Company entered into a contract with Anthony S. Brown Development Company, Inc., (asb) and Anthony S. Brown (Brown) to act as the construction manager on a certain project. Eventually, Christman sued asb and Brown, seeking payment for work performed. At the time that construction began, asb and Brown assured Christman that financing would be
The claim seeking foreclosure of the construction liens was made on behalf of both Christman and the numerous subcontractors, including Berkel, which was a subcontractor in the second phase of the construction project. The litigation against Brown and asb was settled, and a consent judgment was entered against them. As part of the settlement, all subcontractors, with the exception of Berkel, agreed to accept a pro-rata portion of the installment payments made by asb and Brown over time, whenever Christman received such payments.
Berkel filed a cross-claim against Christman and a claim against asb and Brown, seeking money due for work performed on the project. It specifically sought a money judgment against Christman under its subcontract with Christman, seeking immediate payment. Berkel had never before been involved in a project in which the financing had not been in place by the time that the subcontract was signed and relied, inter alia, on provisions in its final letter defining the scope of its work that provided that it would be paid within thirty days after the completion of its work. The trial court found that the contract between Christman and Berkel clearly provided that payments to Berkel would not be made until Christman was paid for the work by the owner.
Berkel first claims that the payment provisions of its contract with Christman are ambiguous and,
Berkel’s reliance on the provision in its bid proposal requiring payment within thirty days is unavailing. A reference by contracting parties to an extraneous writing for a particular purpose makes it a part of their agreement only for the purpose so specified.
Arrow Sheet Metal Works, Inc v Bryant & Detwiler Co,
Berkel next argues that even if considered operative, a "pay when paid” clause is merely a provision that postpones payment for a reasonable amount of time, not indefinitely. Again, we disagree. As indicated earlier, the trial court quite properly found that Christman was not required to pay Berkel until it received payment from the
Berkel also argues that Christman’s act of issuing the subcontract without notifying Berkel that financing was not in place renders the "pay when paid” proviso unenforceable. We find it unnecessary to address the issue whether the failure of a contractor to inform a subcontractor about a lack of financing before the signing of the contract with the subcontractor results in a breach of the contract. In this case, the trial court found that Berkel had notice of the lack of financing before signing the contract. This finding by the trial court was not clearly erroneous. See People v Vaughn, supra. Because Berkel had knowledge of the lack of financing, it has no cause of action for breach of contract with respect to this issue.
Finally, Berkel maintains that the amount Christman claimed was owing to Berkel, $59,000, was incorrect, and that the correct amount due was $65,799. Because we have held that the "pay when paid” provision precludes payment to Berkel until the owner pays Christman, we need not address this issue, Moreover, the trial court did not address the amount due and owing to Berkel,
Affirmed.