History
  • No items yet
midpage
Central Ceilings, Inc. v. Suffolk Construction Co., Inc.
AC 15-P-1117
| Mass. App. Ct. | Mar 29, 2017
Read the full case

Background

  • Central Ceilings, Inc. contracted with Suffolk Construction as a subcontractor on a large dormitory project at Westfield State University; subcontract price ≈ $3.6M.
  • Project required sequential "flow" (exterior-to-interior, floor-by-floor); timely completion was critical because general contract included bonuses for on-time completion and heavy liquidated damages for delay.
  • Suffolk repeatedly failed to coordinate other trades, set control lines, deliver materials, and provide climate control, causing frequent remobilizations, "go-backs," stacking of trades, and compressed schedules.
  • Central claimed lost labor productivity ($321,315) and unpaid change order requests (~$82,538); judge found Suffolk breached in multiple respects and awarded $321,315 but denied the COR recovery based on a pay-if-paid clause.
  • Suffolk appealed, arguing the subcontract’s no-damages-for-delay clause barred recovery and that the judge erred in using the total-cost method; Central cross-appealed the denial of CORs.
  • The trial judge awarded attorney’s fees to Central under G. L. c. 149, § 29; Suffolk challenged denial of discovery and lack of a hearing on fees. Court affirmed judgment and fee award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Enforceability/applicability of no-damages-for-delay clause Central: clause does not bar damages because Suffolk foreclosed the exclusive remedy (time extensions) and damages sought were for increased manpower, not delay per se Suffolk: clause is unambiguous and bars damages caused by delays Court: Affirmed — clause interpreted strictly; Suffolk materially deprived Central of the contractual remedy (extensions) and damages were for compressed schedule/increased manpower, not idle-time delay, so clause did not bar recovery
Use of "total cost" method to calculate lost productivity Central: measured-mile analysis impossible; total-cost method appropriate as last resort; bid realistic and costs reasonable Suffolk: plaintiff failed to satisfy elements for total-cost method and could have used other methods; also fault for some added costs Court: Affirmed — trial judge credited expert; total-cost use justified because measured-mile infeasible, bid realistic, costs reasonable, and plaintiff not responsible for added expenses
Recovery of unpaid change order requests (pay-if-paid clause) Central: some CORs were pass-throughs or directly owed by Suffolk; some CORs paid by owner Suffolk: subcontract conditions precedent (pay-if-paid) not satisfied; no proof owner paid Court: Affirmed — Central failed to prove owner paid or that amounts were direct Suffolk obligations; judge’s factual finding not clearly erroneous
Attorney’s fees: discovery and hearing Central: fees recoverable under G. L. c. 149, § 29; no requirement to produce billing/payment records to establish reasonable value Suffolk: denial of discovery on billing/payment and absence of hearing prejudiced defense Court: Affirmed — denial of requested discovery was not an abuse of discretion or prejudicial; no hearing was requested appropriately by Suffolk, and judge considered Suffolk’s written objections before awarding reduced fees

Key Cases Cited

  • Trace Constr., Inc. v. Dana Barros Sports Complex, LLC, 459 Mass. 346 (Mass. 2011) (standard of review on bench trial and legal rulings)
  • Worcester v. Granger Bros., 19 Mass. App. Ct. 379 (Mass. App. Ct. 1985) (enforceability of no-damages-for-delay clauses)
  • B.J. Harland Elec. Co. v. Granger Bros., 24 Mass. App. Ct. 506 (Mass. App. Ct. 1987) (no-damages-for-delay clause discussion)
  • John E. Green Plumbing & Heating Co. v. Turner Constr. Co., 742 F.2d 965 (6th Cir. 1984) (construing delay damages to mean costs of an idle workforce)
  • United States Steel Corp. v. Missouri Pac. R.R. Co., 668 F.2d 435 (8th Cir. 1982) (strict construction of no-damages-for-delay clauses)
  • Servidone Constr. Corp. v. United States, 931 F.2d 860 (Fed. Cir. 1991) (describing limits and safeguards for total-cost method)
  • Raytheon Co. v. White, 305 F.3d 1354 (Fed. Cir. 2002) (four-element test for total-cost method)
  • Farina Bros. v. Commonwealth, 357 Mass. 131 (Mass. 1970) (refusal of time extensions reviewed in contractor-context)
  • Manganaro Drywall, Inc. v. White Constr. Co., 372 Mass. 661 (Mass. 1977) (right to a hearing on fee applications only when requested)
  • Heller v. Silverbranch Constr. Corp., 376 Mass. 621 (Mass. 1978) (reasonableness of fees assessed by objective value rather than billing/payment evidence)
Read the full case

Case Details

Case Name: Central Ceilings, Inc. v. Suffolk Construction Co., Inc.
Court Name: Massachusetts Appeals Court
Date Published: Mar 29, 2017
Docket Number: AC 15-P-1117
Court Abbreviation: Mass. App. Ct.