History
  • No items yet
midpage
Capital Electric Cooperative, Inc. v. North Dakota Public Service Commission
2016 ND 73
| N.D. | 2016
Read the full case

Background

  • Menard, Inc. planned a 1.2 MW manufacturing/distribution facility near McKenzie in Burleigh County and solicited service estimates from the two nearby suppliers: investor-owned Montana‑Dakota Utilities Co. (MDU) and rural cooperative Capital Electric Cooperative (Capital).
  • MDU held a longstanding certificate of public convenience and necessity to serve McKenzie to a point adjacent to the Menard site; both suppliers would need three‑phase extensions to serve Menard.
  • MDU’s bid projected ~ $513,670 annual customer cost under its rates; Capital’s bid projected ~ $575,884 annually. MDU’s physical three‑phase facilities were closer to the site.
  • MDU applied to the North Dakota Public Service Commission for a certificate to serve the Menard site; Capital protested and requested a hearing.
  • The Commission (2–1) granted MDU the certificate, finding MDU would serve more economically, had closer/longstanding facilities, and that customer preference (Menard’s choice) and orderly economic development favored MDU. The district court affirmed and the Supreme Court affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether customer preference may be considered Capital: customer preference is not a proper criterion Commission/MDU: preference is a proper, though not controlling, consideration Court: Preference is admissible; Commission did not give it undue weight
Accuracy/relevance of local customer counts and proximity Capital: Commission erred about which supplier has more nearby customers and adjacency of McKenzie Commission/MDU: MDU serves more customers in the broader vicinity; McKenzie is adjacent and MDU’s certificate covers adjacent land Court: Findings on adjacency and customer counts supported by evidence; broader vicinity may be considered
Which supplier’s physical extension is shorter/closer Capital: Capital’s proposed one‑mile conversion is shorter than MDU’s total proposed construction Commission/MDU: MDU’s existing three‑phase system is closer; MDU needs only short extension/upgrades Court: Commission reasonably found MDU’s extension of its existing three‑phase system would be shorter/closer
Comparative cost, adequate return, and duplication concerns Capital: Its lower extension cost and used‑transformer allocation show Commission erred; decision causes wasteful duplication Commission/MDU: MDU showed lower annual customer costs, revenue contribution to system, and system benefits; Capital failed to present full revenue/upgrade analysis; duplication would not be wasteful Court: Commission’s cost/revenue findings supported by record; Capital’s incomplete evidence undermines its challenge; duplication not wasteful as a matter of fact

Key Cases Cited

  • Capital Elec. Coop., Inc. v. Pub. Serv. Comm’n, 534 N.W.2d 587 (N.D. 1995) (factors for issuing certificate of public convenience and necessity)
  • Application of Otter Tail Power Co., 169 N.W.2d 415 (N.D. 1969) (list of criteria to weigh customer preference, reliability, economics, and duplication)
  • North Cent. Elec. Coop., Inc. v. N.D. Pub. Serv. Comm’n, 837 N.W.2d 138 (N.D. 2013) (standard of review for agency decisions on appeal)
  • Power Fuels, Inc. v. Elkin, 283 N.W.2d 214 (N.D. 1979) (preponderance/weight‑of‑evidence standard for agency factfinding)
  • N. States Power Co. v. Pub. Serv. Comm’n, 452 N.W.2d 340 (N.D. 1990) (treatment of duplication of distribution facilities and agency factfinding)
Read the full case

Case Details

Case Name: Capital Electric Cooperative, Inc. v. North Dakota Public Service Commission
Court Name: North Dakota Supreme Court
Date Published: Mar 28, 2016
Citation: 2016 ND 73
Docket Number: 20150227
Court Abbreviation: N.D.