CAPITAL ELECTRIC COOPERATIVE, INC., Rеspondent and Appellee, v. PUBLIC SERVICE COMMISSION OF the STATE of NORTH DAKOTA, Respondent, and Montana-Dakota Utilities Co., a Division of MDU Resources Group, Inc., Applicant and Appellant.
Civ. No. 940401.
Supreme Court of North Dakota.
July 3, 1995.
537 N.W.2d 587
William P. Pearce (argued), Pearce & Durick, Bismarck, and Douglas W. Schulz (appearance), MDU Resources Group, Inc., Bismarck, for applicant and appellant.
NEUMANN, Justice.
This appeal involves a dispute under the Territorial Integrity Act,
In October 1992, the North Dakota Department of Transportation (DOT) applied to Capital Electric for electric service for a headbolt heater in a DOT tractor at a storage shed at Sterling, an unincorporated community in Burleigh County. The parties agree the DOT location is outside the corporate limits of a municipality under
Since 1928, MDU and its predecessor have provided central station electric service to Sterling under a certificate of need issued by the PSC‘s predecessor, the Board of Railroad Commissioners. MDU also provides electric service to Sterling under a municipal street lighting agreement with the Sterling Township Board. MDU‘s central station electric system is 335 feet from the DOT location, and MDU has an alternate point of service 250 feet from the DOT location.
In December 1993, MDU applied to the PSC under
Capital Electric appealed to the district court, which reversed the PSC‘s denial of Capital Electric‘s motion to dismiss. The court held the PSC lacked jurisdiction to entertain MDU‘s application, because the “Territorial [Integrity] Act has long been construed to require a customer‘s preference for regulated public utility service before the PSC exercises jurisdiction. During this period the legislature has not interfered and in fact this is a sign of acquiescence in such construction.” MDU appealed from the district court judgment.
MDU contends the district court erred in holding the PSC did not have jurisdiction under
Jurisdiction is the power to hear and determine a proceeding. See Rudnick v. City of Jamestown, 463 N.W.2d 632 (N.D. 1990). The PSC has only the powers and duties conferred upon it by the Legislature.
In construing the Act, our duty is to ascertain the intent of the Legislature. County of Stutsman v. State Historical Society, 371 N.W.2d 321 (N.D.1985). Statutes must be construed as a whole to determine the legislative intent, and they must be harmonized, if possible, to give full force and effect to each provision. Cass County Electric Coop., Inc. v. Northern States Power Co., 419 N.W.2d 181 (N.D.1988).
Before 1965, a rural electric cooperative was authorized to provide electric service in rural areas, see
Under the Act, an electric public utility must secure a certificate of public convenience and necessity from the PSC before extending service to new customers outside the corporate limits of a municipality; however, rural electric cooperatives may extend service to new customers in rural areas without securing a certificate of public convenience and necessity from the PSC. Cass County Electric Coop., Inc. v. Wold Properties, Inc., 249 N.W.2d 514 (N.D.1976); Tri-County Electric Coop., Inc. v. Elkin, 224 N.W.2d 785 (N.D.1974); Montana-Dakota Utilities Co. v. Johanneson, 153 N.W.2d 414 (N.D.1967). Although we have never said the Act gives rural electric cooperatives a preference for electric service in rural areas, it does allow cooperatives to serve customers in rural areas unless an electric public utility obtains a certificate of publiс convenience and necessity from the PSC. Wold Properties, supra; Application of Otter Tail Power Co., supra.
As originally enacted, section 3 of the Act precluded the PSC from issuing a certificate of public convenience and necessity to an electric public utility to extend its service beyond the corporate limits of any municipality unless the rural electric cooperative nearest the proposed service area consented to the extension. 1965 N.D.Laws ch. 319, § 3.4
The Territorial Integrity Act therefore explicitly gives the PSC jurisdiction to hear and determine an electric public utility‘s application for a certificate of public convenience and necessity to extend service to areas outside the corporate limits of a municipality. However, the narrower issue in this case is not whether the PSC has such jurisdiction, but whether the Act requires a customer request for electric service from a public utility in order to invoke the PSC‘s jurisdiction.
In Application of Otter Tail Power Co., supra, we outlined criteria for the PSC to consider in rendering a decision on an electric public utility‘s application for a certificate of public convenience and necessity. In that case, a customer asked an electric public utility to provide service to a rural area, and the utility applied to the PSC for a certificate. We said customer preference for service by the electric public utility was not determinative of public convenience and necessity, but should be considerеd along with:
“the location of the lines of the suppliers; the reliability of the service which will be rendered by them; which of the proposed suppliers will be able to serve the area more economically and still earn an adequate return on its investment; and which supplier is best qualified to furnish electric service to the site designated in the application and which also can best develop electric service in the area in which such site is located without wasteful duplication of investment or service.”
Application of Otter Tail Power Co., 169 N.W.2d at 418.
In Application of Montana-Dakota Utilities Co., 219 N.W.2d 174 (N.D.1974), we again сonsidered the effect of a rural customer‘s preference for service from an electric public utility. We said a rural customer does not have a constitutional right to receive electric service from a public utility. We reiterated that customer preference was not determinative of public convenience and necessity, but “subjects the customer‘s preference for a regulated public utility service to an inquiry and decision by the Commission on the question of public convenience and necеssity.” Id. at 181. See also Elkin, 224 N.W.2d at 792 (customer preference invokes consideration by the PSC, but is not determinative of public convenience and necessity).
In Wold Properties, supra, a customer outside the corporate limits of a municipality initially received service from an electric public utility and sought to change suppliers to a rural electric cooperative. We concluded the public utility had the right to serve the customer to the exclusion of the cooperative because the utility held an unrevoked certificate of public convenience and necessity. We repeated that customer preference was not determinative of public convenience and necessity; instead, it warranted further inquiry and a decision by the PSC on that issue.
None of our prior cases have involved an electric public utility‘s extension of new service to an area outside the corporate limits of a municipality without a customer request for
The Act specifically authorizes the PSC to regulate an electric public utility‘s extension of service to areas outside the corporate limits of any municipality, and does not specifically require a new customer‘s request for service by a public utility in order to invoke the PSC‘s jurisdiction.
Construing the Act otherwise would unduly infringe upon an electric cooperative‘s statutory right to extend service in rural areas without obtaining a certificate of public convenience and necessity and would authorize electric public utilities to extend service to areas outside the corporate limits of a municipality without a new customer‘s request for service. That interpretation is contrary to the purposes of the Act to minimize conflicts between electric public utilities and rural electric cooperatives and to provide territorial protection for rural electric cooperatives. It also would not give full force and effect to the entire Act, because it would indirectly subject a rural electric cooperative‘s extension of service in rural areas to regulation by the PSC. We do not believe the Legislature intended that result when it adopted the Act.
Our interpretation of the Act also is consistent with the PSC‘s prior construction. Before 1993, the PSC had effectively construed the Act to require a customer request for service by a regulated public utility in order to invoke the PSC‘s jurisdiction to decide the issue of public convenience and necessity. However, in 1993, the PSC changed its construction of the Act so that a customer request for service by a public utility was no longer deemed necessary to invoke the PSC‘s jurisdiction to determine public convenience and necessity. We decline to defer to the PSC‘s recent reinterpretation of its authority, because that construction contravenes the statutory framework and purpose of the Act. See W.W. Wallwork, Inc. v. Duchscherer, 501 N.W.2d 751 (N.D.1993) (administrative regulation that contrаvenes statutory language is invalid and not entitled to deference). Instead, we believe the PSC‘s prior longstanding interpretation of the Act is consistent with the language and purpose of the Act and has been acquiesced in by the Legislature. Effertz v. North Dakota Workers Compensation Bureau, 525 N.W.2d 691 (N.D.1994) (Legislature is presumed to know the construction of statute by executive departments of the state and the failure to amend the statute indicates legislative acquiescence).
We hold that a new customer‘s request for service by an electric public utility is necessary to invoke the PSC‘s jurisdiсtion to consider the public utility‘s application for a certificate of public convenience and necessity to extend service to an area outside the corporate limits of a municipality.
We therefore affirm the district court judgment.
SANDSTROM and LEVINE, JJ., and KIRK SMITH, District Judge, concur.
KIRK SMITH, District Judge, sitting in place of MESCHKE, J., disqualified.
I agree with the majority opinion. I write separately in response to the Chief Justice‘s suggestion the legislature could clarify the meaning of the statute. That is certainly an option in the hands of others. In the meantime, I note:
“We have often held that in construing a statute of doubtful meaning the court will give weight to the long-continued, practical construction placed thereon by the officers charged with the duty of executing and applying the statute. Giese v. Engelhardt, 175 N.W.2d 578 (N.D.1970); Blair v. City of Fargo, 171 N.W.2d 236 (N.D.1969), cert. denied, 397 U.S. 990, 90 S.Ct. 1123, 25 L.Ed.2d 397 (1970); Walker v. Weilenman, 143 N.W.2d 689 (N.D.1966); State Tax Commissioner v. Tuchscherer, 130 N.W.2d 608 (N.D.1964).”
Horst v. Guy, 219 N.W.2d 153, 159 (N.D.1974).
The long-established, practical construction of the agency required a customer request.
LEVINE, J., concurs.
VANDE WALLE, Chief Justice, concurring in result.
Presumably the money Capital Electric spent in constructing a 1,450 foot line to serve the DOT location, the money MDU spent in applying for a certificate of public convenience and necessity to serve the same location, the mоney Capital Electric spent in opposing MDU‘s application and the money both Capital Electric and MDU spent in appeals to the district court and this Court have more significance than to determine whether Capital Electric or MDU will provide electricity for a headbolt heater!
My impression is that the money was spent because each party is concerned the other party will get a “leg up” in the construction and application of so called Territorial Integrity Law. If that be so, there must be a better way to resolve the meaning of the statutes. A legislative clarification might be one. When there is discussion of reduced federal funds available for rural electric cooperatives and consumers are complaining because public utility electric rates are too high, reasonable people should be able to find better and less expensive methods of resolving these long-standing disputes as to the authority to provide electric service. Nevertheless, the money has been spent and the dispute is befоre us for resolution. I agree with the result reached by the majority but for different reasons.
At the time MDU applied for a certificate of public convenience and necessity to provide electricity for the headbolt heater at the DOT site, Capital Electric had completed the 1,450 foot extension of its line and was providing service to the site. Service was being provided in accordance with the law. Under those circumstances, the PSC should have denied MDU‘s request. Whether Capital Electric was well advised to cоnstruct the line for this limited service is not material for our purposes, because under the current law it was permitted to do so. Whether the law should be amended to avoid an expenditure of this size to serve a limited need when closer service is available at presumably less cost is a matter for legislative determination.
I am skeptical of, and do not embrace, the majority‘s attempted fine-line distinction between the PSC‘s jurisdiction to hear a matter and its authority to consider public convenience and necessity. The distinсtion is, to me, without a difference. Indeed, I agree that whether or not a customer has requested service is a significant piece of evidence in determining whether or not public convenience and necessity requires a certificate to serve, but it is not conclusive. In this instance, the better rationale is that service was being legally provided so there was no need for the certificate.
I assume the majority‘s attempted distinction is made because Montana-Dakota Utilities Co. v. Johanneson, 153 N.W.2d 414 (N.D.1967) held unconstitutional as an invalid delegation of legislative powers to determine who furnished electrical service in rural areas, a provision that required the rural electric‘s consent before a public utility could extend electric service to an area beyond the corporate limits of the municipality. But I see no substantial difference in requiring a custom
Ordinarily the question of a certificate of public convenience and necessity will not arise without a customer request, i.e., if no customer no necessity for service. However, I believe lack of a request is an evidеntiary rather than a jurisdictional matter, particularly in view of Montana-Dakota Utilities Co. v. Johanneson, supra, and Application of Montana-Dakota Utilities Co., 219 N.W.2d 174 (N.D.1974) holding that customer preference does not govern the PSC in its decision.
Because the evidence reveals that electricity was being provided for the headbolt heater within the law, there was no need for the certificate of public convenience and necessity. I concur in the result.
Notes
“49-0301. Certificate of Public Convenience and Necessity; Secured by Public Utility.
“No public utility henceforth shall begin in the construction or operation of a public utility plant or system or extension thereof, without first obtaining from the commission a certificate that public conveniеnce and necessity require or will require such construction and operation. This section shall not be construed to require any such public utility to secure such certificate for:
“1. An extension within any municipality or district within which it has lawfully commenced operations;
“2. An extension within or to territory already served by it necessary in the ordinary course of its business; or
“3. An extension into territory contiguous to that already occupied by it and not receiving similar service from another utility, or electric cooperative corporation or if no certificate of public convenience and necessity has been issued to any other public utility.
“... If any public utility in constructing or extending its line, plant, or system, unreasonably interferes with or is about to interfere unreasonably with the service or system of any other public utility, or any electric cooperative corporation, the commission on complaint of the public utility or the electric cooperative corporation claiming to be injuriously affected, after notice and hearing as provided in this title, may make such order enforcing this section with respect to such public utility and prescribe such terms and conditions as are just and reasonable.”
“Certificate of public convenience and necessity—Secured by electric public utility.—No electric public utility henceforth shall begin construction or operation of a public utility plant or system, or of an extension of a plant or system, except as provided below, without first obtaining from the commission a certificate that public convenience and neсessity require or will require such construction and operation. This section does not require an electric public utility to secure a certificate for an extension within any municipality within which it has lawfully commenced operations. If any electric public utility in constructing or extending its line, plant, or system, unreasonably interferes with or is about to interfere unreasonably with the service or system of any other electric public utility, or any electric cooperative corporation, the commission, on complaint of the electric public utility or the electric cooperative corporation claiming to be injuriously affected, after notice and hearing as provided in this title, may order enforcement of this section with respect to the offending electric public utility and prescribe just and reasonable terms and conditions.”
Section
“Limitation on electric transmission and distribution lines, extensions and service by electric public utilities.—No electric public utility henceforth shall begin in the construction or operation of a public utility plant оr system or extension thereof without first obtaining from the commission a certificate that public convenience and necessity require or will require such construction and operation, nor shall such public utility henceforth extend its electric transmission or distribution lines beyond or outside of the corporate limits of any municipality, nor shall it serve any customer where the place to be served is not located within the corporate limits of a municipality, unless and until, after application, such electric public utility has obtainеd an order from the commission authorizing such extension and service and a certificate that public convenience and necessity require that permission be given to extend such lines and to serve such customer.”
“§ 3. Limitation on Issuance of Orders and Certificates of Public Convenience and Necessity to Electric Public Utilities.) The public service commission of the state of North Dakota shall not issue its order or a certificate of public convenience and necessity to any electric public utility to extend its eleсtric distribution lines beyond the corporate limits of a municipality or to serve a customer whose place to be served is located outside the corporate limits of a municipality unless the electric co-operative corporation with lines or facilities nearest the place where service is required shall consent in writing to such extension by such electric public utility, or unless, upon hearing before the commission, called upon notice, it shall be shown that the service required cannot be provided by an electric co-operative corporation. Such certificate shall not be necessary if the public service commission approves an agreement between a public utility and the rural electric co-operative serving the area which includes the station to be served and which agreement designates said station to be in an area to be served by the public utility.”