History
  • No items yet
midpage
C. Szabo Contracting, Inc. v. Lorig Construction Company
19 N.E.3d 638
Ill. App. Ct.
2014
Read the full case

Background

  • Lorig was the general contractor on an I-355 Tollway project and subcontracted storm-sewer work to JLA; JLA subcontracted pipe-jacking to Szabo at $1,746/linear foot (sub-subcontract price $266,274).
  • Lorig required DBE participation and directed JLA to assign its subcontract to a DBE; Lorig later exempted the pipe-jacking from that assignment.
  • Szabo performed the pipe-jacking, provided certified payroll and invoices, and sought payment from Lorig; Lorig never paid JLA or Szabo for the pipe-jacking though the Tollway paid Lorig in full.
  • JLA voluntarily dismissed its claims; Szabo pursued a bench trial on an unjust-enrichment (quasi-contract) claim against Lorig and obtained a $215,400 judgment (reduced for supplier payments Lorig made).
  • On appeal Lorig argued that an express subcontract bars quasi-contract relief and that Szabo cannot recover from a nonparty general contractor absent inducement or a promise of payment; the appellate court affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a sub-subcontractor may recover in quasi-contract from a general contractor who received but paid no one for the contracted performance Szabo: quasi-contract available where general contractor received the exact performance it requested and paid no one Lorig: express subcontract governs; unjust-enrichment remedy unavailable against a nonparty when an express contract covers the subject Held: quasi-contract available here — Lorig would be unjustly enriched because it requested and received the specific performance and paid no one
Whether plaintiff must show that the general contractor enticed performance or promised payment to pursue quasi-contract Szabo: not necessary where defendant requested and received the specific benefit and paid no one Lorig: recovery should be limited to cases of inducement or assurances (citing Midcoast) Held: inducement/assurance not required here; court could not affirm on those theories but found recovery justified on nonpayment for requested benefit
Whether allowing recovery risks double liability or shifts contractual risk to the general contractor Lorig: permitting recovery shifts risk and may force double payment to contractor and sub-subcontractor Szabo: no double recovery/risk here — JLA dismissed claims and Szabo does not seek payment from JLA Held: no double liability or unfair shifting of risk given facts (JLA dismissed; Lorig received Tollway payment)
Whether Szabo must exhaust contractual remedies against JLA before suing Lorig in quasi-contract Lorig: some authorities require exhaustion of remedies against the contracting party first Szabo: exhaustion not required for this legal (monetary) unjust-enrichment action Held: exhaustion not required; quasi-contract monetary claim allowed without first exhausting contractual remedies

Key Cases Cited

  • Eychaner v. Gross, 202 Ill. 2d 228 (Ill. 2002) (standard of review for bench-trial factual findings).
  • Reliable Fire Equipment Co. v. Arredondo, 2011 IL 111871 (Ill. 2011) (questions of law reviewed de novo).
  • HPI Health Care Services, Inc. v. Mt. Vernon Hospital, Inc., 131 Ill. 2d 145 (Ill. 1989) (unjust enrichment requires retention of a benefit under circumstances making retention unjust).
  • Hayes Mechanical, Inc. v. First Industrial, L.P., 351 Ill. App. 3d 1 (Ill. App. Ct. 2004) (general rule: quasi-contract relief ordinarily unavailable where express contract governs; analyses of third‑party recovery).
  • Midcoast Aviation, Inc. v. Gen. Elec. Credit Corp., 907 F.2d 732 (7th Cir. 1990) (permitting quasi-contract recovery where nonparty financier enticed plaintiff and fostered a reasonable expectation of payment).
  • Premier Electrical Construction Co. v. La Salle Nat. Bank, 132 Ill. App. 3d 485 (Ill. App. Ct. 1985) (knowledge that work is being performed is insufficient alone to impose restitution liability on the beneficiary).
Read the full case

Case Details

Case Name: C. Szabo Contracting, Inc. v. Lorig Construction Company
Court Name: Appellate Court of Illinois
Date Published: Nov 25, 2014
Citation: 19 N.E.3d 638
Docket Number: 2-13-1328
Court Abbreviation: Ill. App. Ct.