History
  • No items yet
midpage
C.G. Schmidt Incorporated v. Permasteelisa North America
825 F.3d 801
7th Cir.
2016
Read the full case

Background

  • CGS solicited bids for a glass curtainwall with a CGS contract manual stating bids require acceptance of CGS terms and a formal subcontract; CGS selected PNA as contractor of choice but negotiations continued toward a final subcontract; CGS had not secured the prime contract or GMPA before signing a subcontract and PNA likewise would not contract without them; over roughly a year, PNA repeatedly updated its bid and raised concerns about terms while CGS countered with its own proposals; PNA eventually disengaged due to production capacity issues in Thailand and civil unrest in May 2014, and CGS replaced PNA with another subcontractor; CGS filed a diversity action alleging breach of contract and promissory estoppel, and the district court granted summary judgment for PNA on both claims.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was there a binding contract formed by CGS’s selection of PNA’s bid? CGS accepted PNA’s bid by selecting it. No acceptance occurred; negotiations continued toward a formal subcontract. No binding contract existed.
Does promissory estoppel apply to enforce PNA’s bid? PNA’s bid was a promise relied on by CGS in its own bid. Courts limit promissory estoppel in bidding; no enforceable promise. Promissory estoppel does not apply.

Key Cases Cited

  • Gruen Indus., Inc. v. Biller, 608 F.2d 274 (7th Cir. 1979) (intent to be bound requires final written agreement; negotiations ongoing justify no contract)
  • Seater Construction Co. v. Rawson Plumbing, Inc., 619 N.W.2d 293 (Wis. 2000) (promissory estoppel enforceable when bid incorporated into public project bid)
  • Janke Construction Co. v. Vulcan Materials Co., 527 F.2d 772 (7th Cir. 1976) (promissory estoppel against subcontractor for reliance on bid in general bid)
  • Drennan v. Star Paving Co., 333 P.2d 757 (Cal. 1958) (general contractor reliance on subcontractor’s bid in bidding;)
  • Preload Tech., Inc. v. A.B. & J. Constr. Co., 696 F.2d 1080 (5th Cir. 1983) (limits on promissory estoppel when contractor counters; injustice not avoided by enforcing promise)
  • APAC- Southeast, Inc. v. Coastal Caisson Corp., 514 F. Supp. 2d 1373 (N.D. Ga. 2007) (promissory estoppel inappropriate where contractor counters with form subcontract)
Read the full case

Case Details

Case Name: C.G. Schmidt Incorporated v. Permasteelisa North America
Court Name: Court of Appeals for the Seventh Circuit
Date Published: Jun 16, 2016
Citation: 825 F.3d 801
Docket Number: 15-3617
Court Abbreviation: 7th Cir.